INSP - Letter of compliance | | | 4/3/1997 | | PASS |
|
|
|
ISSUED C OF C #13371 AS PER PERRY PAINE THIS DATE.
|
INSP - Final | 3/31/1997 | 3/31/1997 | 3/31/1997 | P | NR |
|
|
|
SHELL FINAL OK, WAITING ON OTHER SIGNATURES/ OK TO SIGN OCC ONCE PW SIGNS
|
INSP - Final | 11/25/1996 | 11/25/1996 | 11/25/1996 | P | PASS |
Joe Tawney
|
|
|
11/25/96 406 - BRIAN ###-#### PLANS & CARDS ARE IN MECHANICAL ROOM OK FOR SHELL ONLY PERMIT
|
INSP - Occupancy Sign-off | 11/14/1996 | 11/12/1996 | 11/12/1996 | | F |
|
|
|
Insp. by Art Yingling/cmpliance w/DR-96-95 - signed Final Occ. for PHASE ONE ONLY.
|
INSP - Framing/Rough-in | 10/8/1996 | 10/8/1996 | 10/6/1996 | P | PASS |
|
|
|
10/08/96 338 - ok to cover with the elec division blessing
|
INSP - Framing/Rough-in | 10/3/1996 | 10/4/1996 | 10/3/1996 | A | PASS |
|
|
|
10/04/96 338 - made ok to insulate only
|
INSP - Flatwork | 9/23/1996 | 9/23/1996 | 9/22/1996 | P | PASS |
|
|
|
09/23/96 338 - SLAB INSP...ON CLOSURE STRIP - ROUTING PANELS - ROOF DECKING..... made ok special insp passed
|
INSP - Footings | 9/6/1996 | 9/6/1996 | 9/6/1996 | P | PASS |
|
|
|
09/06/96 338 - MADE OK INSPECTED BY SPECIAL INSP AGENCY
|
INSP - Flatwork | 9/3/1996 | 9/3/1996 | 9/3/1996 | P | PASS |
|
|
|
09/03/96 338 - STRUCTURAL CONCRETE - "TILT-UP WALL PANELS....." SPECIAL INSP MADE OK
|
INSP - Foundation | 8/27/1996 | 8/27/1996 | 8/26/1996 | P | PASS |
|
|
|
08/27/96 338 - CONCRETE INSP...
|
INSP - Foundation | 8/23/1996 | 8/23/1996 | 8/23/1996 | P | PASS |
|
|
|
08/23/96 338 - WALL PANELS special insp made ok
|
INSP - Masonry | 8/22/1996 | 8/22/1996 | 8/22/1996 | P | PASS |
|
|
|
08/22/96 338 - special insp done on the tilt up panel reinforcing
|
INSP - Footings | 8/20/1996 | 8/20/1996 | 8/20/1996 | P | PART |
|
|
|
08/20/96 338 - made ok pending engineering fix for 1st part of the footi
|
INSP - Footings | 8/7/1996 | 8/7/1996 | 8/7/1996 | P | FAIL |
|
|
|
08/07/96 338 - reinforcing to close to the earth in the exterior footing w/o forms
|