INSP - Final | 8/11/1997 | 8/13/1997 | 8/13/1997 | A | PART |
Wes Worcester
|
|
|
08/13/97 342 - fire dept did not pass
|
INSP - Final | 7/23/1997 | 7/23/1997 | 7/23/1997 | P | PASS |
Wes Worcester
|
|
|
still has to do some fire issues
|
INSP-Final Inspection | 7/16/1997 | 7/18/1997 | 7/18/1997 | P | NR |
|
|
|
SHELL FINAL, ALARMS NOT READY TO TEST, NOT REQ'D FOR SHELL sprinklers not monitored yet
|
INSP - Framing/Rough-in | 4/4/1997 | 4/4/1997 | 4/4/1997 | P | PART |
Carl Dependahl
|
|
|
04/04/97 340 - NE CORNER 1ST FL OK, KEEP CN RE 2HR WALLS
|
INSP - Framing/Rough-in | 3/31/1997 | 3/31/1997 | 3/30/1997 | P | PASS |
|
|
|
03/31/97 333 - south west half of 2nd floor
|
INSP - Framing/Rough-in | 3/24/1997 | 3/25/1997 | 3/25/1997 | A | PART |
Carl Dependahl
|
|
|
03/25/97 340 - C/N RE PENETRATIONS OF SHAFT & 2HR WALL (HORIZ EXIT) BRAC OK TO COVER BATH AREA. NEED FIRE SPRINKLER R/I
|
INSP - Framing/Rough-in | 3/21/1997 | 3/21/1997 | 3/21/1997 | P | PASS |
|
|
|
west end 3rd floor
|
INSP - Framing/Rough-in | 3/14/1997 | 3/17/1997 | 3/16/1997 | A | PART |
|
|
|
03/17/97 333 - stair detail ok to cover
|
INSP - Framing/Rough-in | 3/12/1997 | 3/13/1997 | 3/12/1997 | A | PASS |
|
|
|
03/13/97 333 - FRAM-OK FRAMING third floor west
|
INSP - Framing/Rough-in | 2/18/1997 | 2/19/1997 | 2/18/1997 | A | PART |
|
|
|
02/19/97 333 - exterior walls 3rd floor 1side only on second floor third floor north wing (east)
|
INSP - Framing/Rough-in | 1/21/1997 | 1/22/1997 | 1/22/1997 | P | PART |
Alan Hauser
|
|
|
01/22/97 350 - partial inspection on exterior soffit and north stair tow jim sly
|
INSP - Framing/Rough-in | 1/21/1997 | 1/22/1997 | 1/22/1997 | P | PART |
Jim Sly
|
|
|
01/21/97 316 - Inspection of Ext. walls...North 1/2f of E. wall and Nort story and parapet same walls..C/N on north wall stair tower...continuous membrane.
|
INSP - Framing/Rough-in | 1/21/1997 | 1/21/1997 | 1/21/1997 | P | CANC |
Jim Sly
|
|
|
01/21/97 316 - Cancel...Reschedule for 1/22/97
|
INSP - Footings | 1/8/1997 | 1/9/1997 | 1/9/1997 | A | PASS |
Wes Worcester
|
|
|
|
INSP - Foundation | 1/9/1997 | 1/9/1997 | 1/9/1997 | P | PASS |
Wes Worcester
|
|
|
retaining wall rebar at blk out moved for more cover
|
INSP - Footings | 1/2/1997 | 1/3/1997 | 1/3/1997 | A | PART |
Wes Worcester
|
|
|
special inspector on site
|
INSP - Masonry | 12/18/1996 | 12/19/1996 | 12/18/1996 | A | PART |
Wes Worcester
|
|
|
CONCRETE STAIRS special inspector on site will recheck on Friday
|
INSP - Conference | 12/9/1996 | 12/9/1996 | 12/9/1996 | A | PASS |
Wes Worcester
|
|
|
discussed 2 hr construction
|
INSP - Masonry | 12/5/1996 | 12/6/1996 | 12/6/1996 | A | PASS |
Wes Worcester
|
|
|
COLUMNS REBAR & RETAINING WALL
|
INSP - Masonry | 12/3/1996 | 12/4/1996 | 12/4/1996 | P | PASS |
Wes Worcester
|
|
|
REBAR-CONCRETE COLUMNS. SPECIAL INSPECTOR WILL BE ON JOB. THEY ARE POURING IN A.M. GEORGE SAID OK.
|
INSP - Masonry | 11/25/1996 | 11/27/1996 | 11/27/1996 | P | PART |
Wes Worcester
|
|
|
WIRE MESH FOR FLOOR SLAB 1st floor deck mesh. spec insp on site
|
INSP - Masonry | 11/25/1996 | 11/26/1996 | 11/26/1996 | A | PASS |
Wes Worcester
|
|
|
LATE AM
|
INSP - Masonry | 11/21/1996 | 11/22/1996 | 11/22/1996 | A | PASS |
Wes Worcester
|
|
|
COLUMN REBAR ok and special inspector on site
|
INSP - Masonry | 11/19/1996 | 11/20/1996 | 11/20/1996 | P | PART |
Wes Worcester
|
|
|
COLUMNS POUR
|
INSP - Foundation | 11/14/1996 | 11/15/1996 | 11/15/1996 | A | PART |
Wes Worcester
|
|
|
FND.REBAR
|
INSP - Foundation | 11/6/1996 | 11/7/1996 | 11/7/1996 | P | PASS |
Wes Worcester
|
|
|
11/06/96 342 - early pm. TURNED ANCHOR BOLTS FOR CLEARANCE
|
INSP - Foundation | 11/6/1996 | 11/6/1996 | 11/6/1996 | P | PART |
Wes Worcester
|
|
|
11/06/96 342 -
|
INSP - Carpentry | 11/5/1996 | 11/5/1996 | 11/5/1996 | P | PASS |
Wes Worcester
|
|
|
11/05/96 342 - REBAR COLUMNS EARLY A.M.
|
INSP - Carpentry | 11/4/1996 | 11/4/1996 | 11/4/1996 | P | PASS |
Wes Worcester
|
|
|
11/04/96 342 - columns
|
INSP - Footings | 10/31/1996 | 11/1/1996 | 11/1/1996 | A | PASS |
Wes Worcester
|
|
|
11/01/96 342 - REBAR
|
INSP - Foundation | 10/31/1996 | 10/31/1996 | 10/31/1996 | P | PASS |
Wes Worcester
|
|
|
10/31/96 342 - EARLY PM. REBAR
|
INSP - Footings | 10/30/1996 | 10/30/1996 | 10/30/1996 | P | PASS |
Wes Worcester
|
|
|
10/30/96 342 -
|
INSP - Footings | 10/25/1996 | 10/25/1996 | 10/29/1996 | P | PASS |
Wes Worcester
|
|
|
10/29/96 342 - REBAR - EARLY P.M.
|
INSP - Foundation | 10/28/1996 | 10/28/1996 | 10/28/1996 | P | PASS |
Wes Worcester
|
|
|
10/28/96 342 - FND. REBAR
|
INSP - Foundation | 10/23/1996 | 10/24/1996 | 10/24/1996 | A | PASS |
Wes Worcester
|
|
|
FND. REBAR
|
INSP - Foundation | 10/21/1996 | 10/22/1996 | 10/22/1996 | A | PART |
Wes Worcester
|
|
|
REBAR ok for column, not ready for wall or ftg
|
INSP - Framing/Rough-in | 10/21/1996 | 10/21/1996 | 10/21/1996 | P | PASS |
Alan Hauser
|
|
|
10/21/96 350 - RE-BAR OK IN WEST 3 STRY COLUMN AND BACK PLANTER AND SHOR
|
INSP - Foundation | 10/17/1996 | 10/17/1996 | 10/17/1996 | P | PASS |
Wes Worcester
|
|
|
REBAR FOR LAST TALL COLUMN FOR THIS PHASE
|
INSP - Foundation | 10/16/1996 | 10/16/1996 | 10/16/1996 | P | NH |
Wes Worcester
|
|
|
10/16/96 342 - FND. REBAR ...locked gate, however general called and spe site.
|
INSP - Footings | 10/15/1996 | 10/15/1996 | 10/15/1996 | P | PART |
Wes Worcester
|
|
|
10/15/96 342 - 1:30-2 PM
|
INSP - Foundation | 10/11/1996 | 10/14/1996 | 10/14/1996 | A | PASS |
Alan Hauser
|
|
|
10/14/96 350 - FND.REBAR IN FRONT 3 STORY COLUNN, FRONT PLANTER BOX WALL FOR COLUMNS CENTER BUILDING AND BY ELEVATOR SHAFT
|
INSP - Footings | 10/9/1996 | 10/10/1996 | 10/10/1996 | A | NR |
Wes Worcester
|
|
|
|
INSP - Foundation | 10/8/1996 | 10/9/1996 | 10/9/1996 | P | NH |
Wes Worcester
|
|
|
FND. COLUMN - SINGLE COLUMN gate locked .... special inspector on site
|
INSP - Foundation | 10/4/1996 | 10/7/1996 | 10/7/1996 | P | PASS |
Wes Worcester
|
|
|
FND. REBAR EARLY P.M.
|
INSP - Foundation | 10/3/1996 | 10/3/1996 | 10/3/1996 | P | PART |
Wes Worcester
|
|
|
REBAR POURING AT 2PM. 4th cplumn ok, special inspector on site
|
INSP - Foundation | 10/2/1996 | 10/2/1996 | 10/2/1996 | P | PART |
Wes Worcester
|
|
|
rebar - stem walls & columns....
|
INSP - Footings | 10/1/1996 | 10/1/1996 | 10/1/1996 | P | NR |
Wes Worcester
|
|
|
REBAR NOT READY, SPECIAL INSP TO BE ON SITE
|
INSP - Foundation | 10/1/1996 | 10/1/1996 | 10/1/1996 | A | PART |
Wes Worcester
|
|
|
2 DOUBLE MATS OK, SPECIAL INSP TO BE ON SITE
|
INSP - Foundation | 9/30/1996 | 9/30/1996 | 9/30/1996 | P | PART |
Wes Worcester
|
|
|
REBAR -COLUMN special inspector on site...what I could see was ok
|
INSP - Foundation | 9/25/1996 | 9/26/1996 | 9/26/1996 | A | PART |
Wes Worcester
|
|
|
FND. w/special insp on site, portion I looked at was well done
|
INSP - Foundation | 9/23/1996 | 9/24/1996 | 9/24/1996 | A | PART |
Wes Worcester
|
|
|
COLUMNS 9 - 9:30 APPOINTMENT
|
INSP - Foundation | 9/19/1996 | 9/20/1996 | 9/20/1996 | A | PASS |
Alan Hauser
|
|
|
09/20/96 350 - FND. REBAR IN HILLSIDE WALL TWO MATS IN 8" WALL, HAVE SPE WANTED TO LOOK AT WALL.
|
INSP - Conference | 9/10/1996 | 9/10/1996 | 9/10/1996 | | PASS |
|
|
|
/ / 405 - pre-con conference.....reviewed hydrant locations
|
INSP - Conference | 9/9/1996 | 9/9/1996 | 9/9/1996 | P | PART |
Wes Worcester
|
|
|
met w/MTI
|
INSP - Conference | 9/6/1996 | 9/9/1996 | 9/9/1996 | P | PART |
Wes Worcester
|
|
|
PRE-CONST.CONF. RON L. ###-#### - needs engineering for wet set and epoxy set of dowels...TI pending
|
INSP - Footings | 9/9/1996 | 9/9/1996 | 9/9/1996 | P | NR |
Wes Worcester
|
|
|
|
INSP - Site Preparation | 9/9/1996 | 9/9/1996 | 9/9/1996 | P | PART |
Wes Worcester
|
|
|
ck on soils....Strata on site
|
INSP - Footings | 9/3/1996 | 9/4/1996 | 9/4/1996 | P | FAIL |
Wes Worcester
|
|
|
pouring w/o inspection, have not rec'd scope of work letter
|
INSP - Footings | 8/30/1996 | 9/3/1996 | 9/3/1996 | A | PASS |
|
|
|
09/03/96 333 - NORTH WALL FOOTING OK TO POUR PENDING SPECIAL INSPECTION
|