Permit Information
Permit NumberBLD96-01376
StatusFinaled
Name HEALTHWISE INC.
Site Address 2601 N BOGUS BASIN RD
Project NameHEALTHWISE-SHELL
Customer Number 
ePlanReviewNo
Description
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final8/11/19978/13/19978/13/1997APART
DetailsWes Worcester
08/13/97 342 - fire dept did not pass
INSP - Final7/23/19977/23/19977/23/1997PPASS
DetailsWes Worcester
still has to do some fire issues
INSP-Final Inspection7/16/19977/18/19977/18/1997PNR
Details
SHELL FINAL, ALARMS NOT READY TO TEST, NOT REQ'D FOR SHELL sprinklers not monitored yet
INSP - Framing/Rough-in4/4/19974/4/19974/4/1997PPART
DetailsCarl Dependahl
04/04/97 340 - NE CORNER 1ST FL OK, KEEP CN RE 2HR WALLS
INSP - Framing/Rough-in3/31/19973/31/19973/30/1997PPASS
Details
03/31/97 333 - south west half of 2nd floor
INSP - Framing/Rough-in3/24/19973/25/19973/25/1997APART
DetailsCarl Dependahl
03/25/97 340 - C/N RE PENETRATIONS OF SHAFT & 2HR WALL (HORIZ EXIT) BRAC OK TO COVER BATH AREA. NEED FIRE SPRINKLER R/I
INSP - Framing/Rough-in3/21/19973/21/19973/21/1997PPASS
Details
west end 3rd floor
INSP - Framing/Rough-in3/14/19973/17/19973/16/1997APART
Details
03/17/97 333 - stair detail ok to cover
INSP - Framing/Rough-in3/12/19973/13/19973/12/1997APASS
Details
03/13/97 333 - FRAM-OK FRAMING third floor west
INSP - Framing/Rough-in2/18/19972/19/19972/18/1997APART
Details
02/19/97 333 - exterior walls 3rd floor 1side only on second floor third floor north wing (east)
INSP - Framing/Rough-in1/21/19971/22/19971/22/1997PPART
DetailsAlan Hauser
01/22/97 350 - partial inspection on exterior soffit and north stair tow jim sly
INSP - Framing/Rough-in1/21/19971/22/19971/22/1997PPART
DetailsJim Sly
01/21/97 316 - Inspection of Ext. walls...North 1/2f of E. wall and Nort story and parapet same walls..C/N on north wall stair tower...continuous membrane.
INSP - Framing/Rough-in1/21/19971/21/19971/21/1997PCANC
DetailsJim Sly
01/21/97 316 - Cancel...Reschedule for 1/22/97
INSP - Footings1/8/19971/9/19971/9/1997APASS
DetailsWes Worcester
INSP - Foundation1/9/19971/9/19971/9/1997PPASS
DetailsWes Worcester
retaining wall rebar at blk out moved for more cover
INSP - Footings1/2/19971/3/19971/3/1997APART
DetailsWes Worcester
special inspector on site
INSP - Masonry12/18/199612/19/199612/18/1996APART
DetailsWes Worcester
CONCRETE STAIRS special inspector on site will recheck on Friday
INSP - Conference12/9/199612/9/199612/9/1996APASS
DetailsWes Worcester
discussed 2 hr construction
INSP - Masonry12/5/199612/6/199612/6/1996APASS
DetailsWes Worcester
COLUMNS REBAR & RETAINING WALL
INSP - Masonry12/3/199612/4/199612/4/1996PPASS
DetailsWes Worcester
REBAR-CONCRETE COLUMNS. SPECIAL INSPECTOR WILL BE ON JOB. THEY ARE POURING IN A.M. GEORGE SAID OK.
INSP - Masonry11/25/199611/27/199611/27/1996PPART
DetailsWes Worcester
WIRE MESH FOR FLOOR SLAB 1st floor deck mesh. spec insp on site
INSP - Masonry11/25/199611/26/199611/26/1996APASS
DetailsWes Worcester
LATE AM
INSP - Masonry11/21/199611/22/199611/22/1996APASS
DetailsWes Worcester
COLUMN REBAR ok and special inspector on site
INSP - Masonry11/19/199611/20/199611/20/1996PPART
DetailsWes Worcester
COLUMNS POUR
INSP - Foundation11/14/199611/15/199611/15/1996APART
DetailsWes Worcester
FND.REBAR
INSP - Foundation11/6/199611/7/199611/7/1996PPASS
DetailsWes Worcester
11/06/96 342 - early pm. TURNED ANCHOR BOLTS FOR CLEARANCE
INSP - Foundation11/6/199611/6/199611/6/1996PPART
DetailsWes Worcester
11/06/96 342 -
INSP - Carpentry11/5/199611/5/199611/5/1996PPASS
DetailsWes Worcester
11/05/96 342 - REBAR COLUMNS EARLY A.M.
INSP - Carpentry11/4/199611/4/199611/4/1996PPASS
DetailsWes Worcester
11/04/96 342 - columns
INSP - Footings10/31/199611/1/199611/1/1996APASS
DetailsWes Worcester
11/01/96 342 - REBAR
INSP - Foundation10/31/199610/31/199610/31/1996PPASS
DetailsWes Worcester
10/31/96 342 - EARLY PM. REBAR
INSP - Footings10/30/199610/30/199610/30/1996PPASS
DetailsWes Worcester
10/30/96 342 -
INSP - Footings10/25/199610/25/199610/29/1996PPASS
DetailsWes Worcester
10/29/96 342 - REBAR - EARLY P.M.
INSP - Foundation10/28/199610/28/199610/28/1996PPASS
DetailsWes Worcester
10/28/96 342 - FND. REBAR
INSP - Foundation10/23/199610/24/199610/24/1996APASS
DetailsWes Worcester
FND. REBAR
INSP - Foundation10/21/199610/22/199610/22/1996APART
DetailsWes Worcester
REBAR ok for column, not ready for wall or ftg
INSP - Framing/Rough-in10/21/199610/21/199610/21/1996PPASS
DetailsAlan Hauser
10/21/96 350 - RE-BAR OK IN WEST 3 STRY COLUMN AND BACK PLANTER AND SHOR
INSP - Foundation10/17/199610/17/199610/17/1996PPASS
DetailsWes Worcester
REBAR FOR LAST TALL COLUMN FOR THIS PHASE
INSP - Foundation10/16/199610/16/199610/16/1996PNH
DetailsWes Worcester
10/16/96 342 - FND. REBAR ...locked gate, however general called and spe site.
INSP - Footings10/15/199610/15/199610/15/1996PPART
DetailsWes Worcester
10/15/96 342 - 1:30-2 PM
INSP - Foundation10/11/199610/14/199610/14/1996APASS
DetailsAlan Hauser
10/14/96 350 - FND.REBAR IN FRONT 3 STORY COLUNN, FRONT PLANTER BOX WALL FOR COLUMNS CENTER BUILDING AND BY ELEVATOR SHAFT
INSP - Footings10/9/199610/10/199610/10/1996ANR
DetailsWes Worcester
INSP - Foundation10/8/199610/9/199610/9/1996PNH
DetailsWes Worcester
FND. COLUMN - SINGLE COLUMN gate locked .... special inspector on site
INSP - Foundation10/4/199610/7/199610/7/1996PPASS
DetailsWes Worcester
FND. REBAR EARLY P.M.
INSP - Foundation10/3/199610/3/199610/3/1996PPART
DetailsWes Worcester
REBAR POURING AT 2PM. 4th cplumn ok, special inspector on site
INSP - Foundation10/2/199610/2/199610/2/1996PPART
DetailsWes Worcester
rebar - stem walls & columns....
INSP - Footings10/1/199610/1/199610/1/1996PNR
DetailsWes Worcester
REBAR NOT READY, SPECIAL INSP TO BE ON SITE
INSP - Foundation10/1/199610/1/199610/1/1996APART
DetailsWes Worcester
2 DOUBLE MATS OK, SPECIAL INSP TO BE ON SITE
INSP - Foundation9/30/19969/30/19969/30/1996PPART
DetailsWes Worcester
REBAR -COLUMN special inspector on site...what I could see was ok
INSP - Foundation9/25/19969/26/19969/26/1996APART
DetailsWes Worcester
FND. w/special insp on site, portion I looked at was well done
INSP - Foundation9/23/19969/24/19969/24/1996APART
DetailsWes Worcester
COLUMNS 9 - 9:30 APPOINTMENT
INSP - Foundation9/19/19969/20/19969/20/1996APASS
DetailsAlan Hauser
09/20/96 350 - FND. REBAR IN HILLSIDE WALL TWO MATS IN 8" WALL, HAVE SPE WANTED TO LOOK AT WALL.
INSP - Conference9/10/19969/10/19969/10/1996 PASS
Details
/ / 405 - pre-con conference.....reviewed hydrant locations
INSP - Conference9/9/19969/9/19969/9/1996PPART
DetailsWes Worcester
met w/MTI
INSP - Conference9/6/19969/9/19969/9/1996PPART
DetailsWes Worcester
PRE-CONST.CONF. RON L. ###-#### - needs engineering for wet set and epoxy set of dowels...TI pending
INSP - Footings9/9/19969/9/19969/9/1996PNR
DetailsWes Worcester
INSP - Site Preparation9/9/19969/9/19969/9/1996PPART
DetailsWes Worcester
ck on soils....Strata on site
INSP - Footings9/3/19969/4/19969/4/1996PFAIL
DetailsWes Worcester
pouring w/o inspection, have not rec'd scope of work letter
INSP - Footings8/30/19969/3/19969/3/1996APASS
Details
09/03/96 333 - NORTH WALL FOOTING OK TO POUR PENDING SPECIAL INSPECTION