Permanent Occupancy | | 4/6/1998 | 4/6/1998 | | DONE |
|
|
|
|
INSP - Final | 9/25/1997 | 9/26/1997 | 9/26/1997 | A | PASS |
Jim Sly
|
|
|
09/25/97 316 - Final Occupancy.
|
INSP-Final Inspection | 9/2/1997 | 9/2/1997 | 9/2/1997 | | PASS |
|
|
|
REINSP FOR FINAL OK FOR PERM OCC
|
INSP - Temporary occupancy | 8/28/1997 | 8/29/1997 | 9/2/1997 | A | PART |
Jim Sly
|
|
|
09/02/97 316 - Temp Occ.
|
INSP-Final Inspection | 8/28/1997 | 8/29/1997 | 8/29/1997 | A | NR |
Joe Tawney
|
|
|
08/29/97 406 - as early as possible NOT READY FOR INSP
|
INSP - Final | 8/21/1997 | 8/22/1997 | 8/22/1997 | A | FAIL |
Jim Sly
|
|
|
08/21/97 316 - C/N...Need handrail stage stairs, req. signatures...lette by Hello! on 08/21/97 at 14:03:57.
|
INSP-Final Inspection | 8/15/1997 | 8/18/1997 | 8/18/1997 | A | FAIL |
Joe Tawney
|
|
|
08/17/97 406 - 8:30 A.M. FINAL FAIL ALARM SYSTEM CURB STRIPING & LETTERING
|
INSP-Conference | 7/29/1997 | 7/29/1997 | 7/29/1997 | P | PASS |
Joe Tawney
|
|
|
/ / 406 - CONF ON ALARM SYSTEM REQUIRE LETTER TO DEACTIVATE DOOR HOLD DECISION MADE
|
INSP-Final Inspection | 7/15/1997 | 7/21/1997 | 7/21/1997 | A | FAIL |
Joe Tawney
|
|
|
07/21/97 406 - FINAL FAIL NO APPROVED ALARM SUBMITTAL DEFICIENTSIES NOTE EXT CAB NEED MALLETS
|
INSP - Carpentry | 6/18/1997 | 6/19/1997 | 6/19/1997 | A | PASS |
Jim Sly
|
|
|
06/18/97 316 - Corridor Penitrations ..W. & N.wings OK...Also Gym and Ki
|
INSP - Ceiling grid | 6/18/1997 | 6/19/1997 | 6/19/1997 | A | PASS |
Jim Sly
|
|
|
06/18/97 316 - All Ceiling grid OK...thruout...
|
INSP - Final | 6/19/1997 | 6/19/1997 | 6/19/1997 | | PART |
Joe Tawney
|
|
|
/ / 406 - TRIP TEST ON 2 DP SYSTEMS OK ON WATER TO END LINE TIMES
|
INSP-Sprinkler Rough-in/Hydro | 6/16/1997 | 6/18/1997 | 6/19/1997 | P | FAIL |
Joe Tawney
|
|
|
06/18/97 406 - SHELLY ###-#### TRIP TEST ON DP SYSTEMS FAIL
|
INSP - Ceiling grid | 6/17/1997 | 6/18/1997 | 6/18/1997 | A | NR |
Jim Sly
|
|
|
06/17/97 316 - CEILING AND CARPENTRY INSP. Cancel...Will do Thurs AM
|
INSP - Ceiling grid | 6/16/1997 | 6/17/1997 | 6/17/1997 | A | PASS |
Jim Sly
|
|
|
06/16/97 316 - South wing OK
|
INSP - Carpentry | 6/16/1997 | 6/16/1997 | 6/16/1997 | | PASS |
Jim Sly
|
|
|
/ / 316 - Firecaulk wall penitrations South wing ...OK
|
INSP - Ceiling grid | 6/13/1997 | 6/16/1997 | 6/16/1997 | P | PART |
Jim Sly
|
|
|
06/16/97 316 - CEILING CLOSE UP....OK D wing....East wing Only....
|
INSP - Ceiling grid | 6/3/1997 | 6/3/1997 | 6/3/1997 | | FAIL |
Jim Sly
|
|
|
/ / 316 - Inspection of grid East wing corridor and classrooms....stil engineering.
|
INSP - Wall cover | 6/3/1997 | 6/3/1997 | 6/3/1997 | | FAIL |
Jim Sly
|
|
|
/ / 316 - C/N...Seal all corridor penitrations /chpt 7..seal penitr ot
|
INSP - Ceiling grid | 5/29/1997 | 6/2/1997 | 6/2/1997 | A | FAIL |
Jim Sly
|
|
|
05/30/97 316 - Need engineering...
|
INSP-Final Inspection | 5/22/1997 | 5/27/1997 | 5/27/1997 | A | PART |
Joe Tawney
|
|
|
05/27/97 406 - OK ON PARTIAL HYDRO TEST 0F TWO DRY PIPE SYSTEMS. FDC ST
|
INSP - Final | 3/7/1997 | 3/7/1997 | 3/7/1997 | | CANC |
Jim Sly
|
|
|
03/07/97 316 - Wrong inspection sent ...Cancel
|
INSP - Framing/Rough-in | 2/19/1997 | 2/19/1997 | 2/19/1997 | | PASS |
Jim Sly
|
|
|
/ / 316 - All Sructural framing complete and OK pending approval and l Engineer.
|
INSP - Final | 2/12/1997 | 2/13/1997 | 2/18/1997 | A | PART |
Joe Tawney
|
|
|
JENNIFER ###-#### OK TO COVER SPKLRS IN KITCHEN AND GYMNASIUM AREAS
|
INSP - Framing/Rough-in | 2/13/1997 | 2/13/1997 | 2/13/1997 | | PART |
Jim Sly
|
|
|
/ / 316 - Inspection of installation of 1hr shafts for boiler rm. and
|
INSP - Framing/Rough-in | 2/11/1997 | 2/12/1997 | 2/12/1997 | A | CANC |
Jim Sly
|
|
|
02/12/97 316 - Cancel ...Will do 2/13/97
|
INSP - Framing/Rough-in | 1/23/1997 | 1/24/1997 | 1/24/1997 | P | FAIL |
Jim Sly
|
|
|
01/23/97 316 - C/N ...Backwards truss ..missed bearing multi-purpose roo
|
INSP - Roof | 1/9/1997 | 1/10/1997 | 1/10/1997 | P | PASS |
Jim Sly
|
|
|
01/10/97 316 - SHEATHING Multi-purpose Bldg. OK
|
INSP-Sprinkler Rough-in/Hydro | 1/10/1997 | 1/10/1997 | 1/10/1997 | P | PART |
Joe Tawney
|
|
|
STAN OR LINDA - ###-#### ROUGH IN OF ATTIC SPKLR SYSTEMS ADD HEAD FOR OBSTR OF DUCT PROVIDE PROTECTION IN SOFFIT ON EAST SIDE OK TO COVER GYM AREA NOT FINISHED
|
INSP - Energy code compliance | 1/7/1997 | 1/8/1997 | 1/8/1997 | P | PART |
Jim Sly
|
|
|
01/08/97 316 - East and West wings.
|
INSP - Framing/Rough-in | 1/7/1997 | 1/8/1997 | 1/8/1997 | P | PART |
Jim Sly
|
|
|
01/08/97 316 - West wing walls and Kitchen sheathing.
|
INSP - Framing/Rough-in | 12/24/1996 | 12/24/1996 | 12/24/1996 | | PART |
Jim Sly
|
|
|
/ / 316 - Inspection of ext. wall sheathing W. wing OK, Corridor for c OK, Interior lid for cover W. wing OK.
|
INSP - Framing/Rough-in | 12/12/1996 | 12/13/1996 | 12/13/1996 | A | PART |
Jim Sly
|
|
|
12/12/96 316 - SOUTH WING - AREA A for ceiling cover...OK
|
INSP - Carpentry | 12/5/1996 | 12/5/1996 | 12/5/1996 | | PASS |
Jim Sly
|
|
|
/ / 316 - East wing Draftstop OK.
|
INSP - Framing/Rough-in | 12/3/1996 | 12/3/1996 | 12/3/1996 | | PART |
Jim Sly
|
|
|
/ / 316 - Framing OK on East wing....Need to repair draftstop. Roof OK on West wing..
|
INSP - Framing/Rough-in | 11/27/1996 | 12/2/1996 | 12/2/1996 | P | NR |
Jim Sly
|
|
|
12/02/96 316 - Roof sheathing west wing (partial) and East wing frame...
|
INSP - Framing/Rough-in | 11/26/1996 | 11/27/1996 | 11/27/1996 | P | NR |
Jim Sly
|
|
|
11/27/96 316 - PARTIAL FRAMING Not Ready...Needs to patch holes in draft penitrations, wrap large electrical boxes with gyp, putty pack ect.
|
INSP - Roof | 11/19/1996 | 11/20/1996 | 11/19/1996 | P | PASS |
Jim Sly
|
|
|
11/19/96 316 - Roof sheathing...south side, West wing...OK.
|
INSP - Framing/Rough-in | 11/8/1996 | 11/12/1996 | 11/12/1996 | A | FAIL |
Jim Sly
|
|
|
11/11/96 316 - C/N for verification of detail for listed ceiling assembl
|
INSP - Wall cover | 11/4/1996 | 11/4/1996 | 11/4/1996 | | PART |
Jim Sly
|
|
|
/ / 316 - Roof sheathing nailing....south wing..OK.
|
INSP - Wall cover | 10/28/1996 | 10/28/1996 | 10/28/1996 | P | PART |
Jim Sly
|
|
|
10/28/96 316 - Roof sheathing nailing East wing (part) OK.
|
INSP - Wall cover | 10/21/1996 | 10/22/1996 | 10/22/1996 | A | PASS |
Jim Sly
|
|
|
10/21/96 316 - Inspection of ext ply and roof sheathing attachment...Eas
|
INSP - Conference | 9/19/1996 | 9/19/1996 | 9/19/1996 | | PASS |
Jim Sly
|
|
|
/ / 316 - Talked to J C Murray (Super) about progression of project.
|
INSP - Footings | 8/9/1996 | 8/9/1996 | 8/9/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 - FRMS-OK FORMS-REBAR 1st phase
|
INSP - Footings | 8/9/1996 | 8/9/1996 | 8/9/1996 | | PASS |
Jim Storey
|
|
|
/ / 301 - FRMS-OK FORMS-REBAR 1st phase
|
INSP - Footings | 8/7/1996 | 8/8/1996 | 8/8/1996 | A | PART |
Jim Storey
|
|
|
08/08/96 301 - LATE A.M. FRMS-OK FORMS-REBAR awing special insp on site pending report not comple set up.
|