Permanent Occupancy | | 7/31/1997 | 7/31/1997 | | DONE |
|
|
|
|
INSP - Final | 7/18/1997 | 7/18/1997 | 7/18/1997 | P | PASS |
|
|
|
07/18/97 333 - signed card for occ. for kim as per kim-all signatures ar
|
INSP - Final | 9/18/1996 | 9/18/1996 | 9/18/1996 | | PASS |
|
|
|
/ / 405 - final occ approved, reviewed phase II requirements
|
INSP - Framing/Rough-in | 8/29/1996 | 8/30/1996 | 8/30/1996 | P | PASS |
Wes Worcester
|
|
|
|
INSP - Final | 8/29/1996 | 8/29/1996 | 8/29/1996 | | PART |
|
|
|
/ / 405 - checked hood, alarms, sprinkler, exits, emer lighting c/n issued....temp occupancy approved
|
INSP - Framing/Rough-in | 8/29/1996 | 8/29/1996 | 8/29/1996 | P | PART |
Wes Worcester
|
|
|
APPT.BETWEEN 4 & 4:30 P.M.
|
INSP - Conference | 8/26/1996 | 8/26/1996 | 8/26/1996 | A | PASS |
Wes Worcester
|
|
|
met w/dick (plans ck) and owner/contractor at city desk
|
INSP - Final | 8/23/1996 | 8/26/1996 | 8/26/1996 | A | NR |
Wes Worcester
|
|
|
still working w/fire and elect and plumbing
|
INSP - Carpentry | 8/23/1996 | 8/23/1996 | 8/23/1996 | A | PASS |
Wes Worcester
|
|
|
that that was done in correct
|
INSP - Conference | 8/23/1996 | 8/23/1996 | 8/23/1996 | A | PART |
Wes Worcester
|
|
|
met w/owner and contractor
|
INSP - Conference | 8/23/1996 | 8/23/1996 | 8/23/1996 | | PASS |
|
|
|
/ / 405 - walkthrough w/cont and owner on requirements...planning alar 8/28
|
INSP - Framing/Rough-in | 8/23/1996 | 8/23/1996 | 8/23/1996 | A | NR |
Wes Worcester
|
|
|
still working on shaft assy
|
INSP - Framing/Rough-in | 8/22/1996 | 8/23/1996 | 8/23/1996 | A | PART |
Wes Worcester
|
|
|
|
INSP - Carpentry | 8/19/1996 | 8/19/1996 | 8/19/1996 | P | PASS |
Wes Worcester
|
|
|
|
INSP - Conference | 8/19/1996 | 8/19/1996 | 8/19/1996 | P | PART |
Wes Worcester
|
|
|
need plan ck notes
|
INSP - Framing/Rough-in | 8/19/1996 | 8/19/1996 | 8/19/1996 | P | PART |
Wes Worcester
|
|
|
|
INSP - Roof | 8/19/1996 | 8/19/1996 | 8/19/1996 | P | NR |
Wes Worcester
|
|
|
blocking between bci's w/hvac unit above
|
INSP - Carpentry | 8/5/1996 | 8/5/1996 | 8/5/1996 | P | FAIL |
Wes Worcester
|
|
|
has deviated from approved plan... contacting architect for changes and engineer for calcs
|
INSP - Conference | 8/5/1996 | 8/5/1996 | 8/5/1996 | P | FAIL |
Wes Worcester
|
|
|
need calcs for hvac on roof and fix for spliced I joists at bearing point
|
INSP - Framing/Rough-in | 8/5/1996 | 8/5/1996 | 8/5/1996 | P | NR |
Wes Worcester
|
|
|
still working on framing
|