INSP - Framing/Rough-in | 9/26/1996 | 9/26/1996 | 10/1/1996 | A | NR |
Carl Dependahl
|
|
|
ASK FOR AL INITIAL INSP REQUEST NOT REC'D, WENT TO JOB TUES 10-1...NO AL... KEEP CN( ITEM ON CN LOOKS OK, BUT NEED TO ASK FOR AL...)
|
INSP - Framing/Rough-in | 8/30/1996 | 9/3/1996 | 9/3/1996 | A | CANC |
Carl Dependahl
|
|
|
08/30/96 340 - ROOF NEEDS INSPECTING - PLEASE LOOK FOR FOREMAN (GLENN) ON THE JOB. HE NEEDS TO COVER ASAP....
|
INSP - Framing/Rough-in | 9/3/1996 | 9/3/1996 | 9/3/1996 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - CORRECTIONS NOT MADE; NO ONE AT SITE, KEEP C/N
|
INSP - Roof | 9/3/1996 | 9/3/1996 | 9/3/1996 | | NR |
Carl Dependahl
|
|
|
/ / 340 - NO ACCESS TO ROOF...
|
INSP - Framing/Rough-in | 8/29/1996 | 8/30/1996 | 8/30/1996 | A | FAIL |
Carl Dependahl
|
|
|
08/30/96 340 - C/N
|
INSP - Framing/Rough-in | 8/14/1996 | 8/15/1996 | 8/15/1996 | A | PASS |
Jim Sly
|
|
|
08/15/96 316 -
|
INSP - Framing/Rough-in | 8/5/1996 | 8/5/1996 | 8/5/1996 | P | PASS |
Jim Storey
|
|
|
08/05/96 301 - EAST WALL NORTH END
|
INSP - Framing/Rough-in | 7/24/1996 | 7/25/1996 | 7/25/1996 | A | PASS |
Jim Storey
|
|
|
07/25/96 301 - WALLS FRAM-OK FRAMING WFR -OK WALL FRAMING
|
INSP - Framing/Rough-in | 7/22/1996 | 7/23/1996 | 7/23/1996 | A | PART |
Carl Dependahl
|
|
|
PARTIAL ONLY. need plan, framing at "parapet" looks ok
|
INSP - Conference | 7/19/1996 | 7/19/1996 | 7/19/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - ARCH TO BRING PLAN TO JOB, WILL CALL?
|
INSP - Carpentry | 7/16/1996 | 7/16/1996 | 7/16/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - CHK'D "PARAPET'DETAIL & ASS'Y...NEED PLAN FOR FURTHER INSP
|