Permanent Occupancy | | 12/21/1996 | 12/21/1996 | | DONE |
|
|
|
|
INSP - Final | 10/16/1996 | 10/17/1996 | 10/17/1996 | P | PASS |
Wes Worcester
|
|
|
10/17/96 342 - 1:30 APPT.
|
INSP - Final | 10/15/1996 | 10/16/1996 | 10/16/1996 | P | PART |
Jim Storey
|
|
|
10/16/96 301 - TRANS TO WES.
|
INSP - Final | 10/15/1996 | 10/16/1996 | 10/16/1996 | A | PASS |
|
|
|
10/16/96 405 - 2ND & 7TH FLOORS
|
INSP - Final | 9/18/1996 | 9/19/1996 | 9/19/1996 | A | FAIL |
Jim Storey
|
|
|
09/18/96 301 - PLAZA 4 BLDG. 2ND & 7TH FLOORS CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Final | 9/12/1996 | 9/13/1996 | 9/13/1996 | P | NH |
Wes Worcester
|
|
|
NO RESPONSE FROM CONTRACTOR FOR ACCESS
|
INSP - Final | 9/11/1996 | 9/12/1996 | 9/12/1996 | P | PASS |
|
|
|
09/12/96 405 - 2ND FLOOR perm occ approved
|
INSP - Final | 8/30/1996 | 9/3/1996 | 9/3/1996 | A | PART |
|
|
|
09/03/96 405 - BLDG. 4 2ND FLR. SPRINLERS. ok to cover need hydro
|
INSP - Framing/Rough-in | 8/29/1996 | 8/30/1996 | 8/30/1996 | A | NR |
Wes Worcester
|
|
|
J Storey looked at and I met on site to go over verbal corrections
|