Information based on query as of Monday, July 1, 2024.
Permit Information
Permit NumberBLD96-01936
StatusFinaled
Name RJ'S DINER
Site Address 3095 N LAKEHARBOR LN
Project NameRJ'S 50'S DINER
Customer Number 
ePlanReviewNo
Description
TO CONSTURCT A NEW 1990 SQ. FT., ONE STORY, WOOD FRAME WITH CONCRETE SLAB FLOOR RESTAURANT AND RELATED SITE IMPROVEMENTS. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED REQUIREMENT LIST. DR#22-96/CU#114-84(MOD)/PC#379-96/JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 6/11/19976/11/1997 DONE
Details
INSP - Final6/10/19976/10/19976/10/1997 PASS
DetailsJoe Tawney
/ / 406 - REINSP FOR FINAL OK FOR PERM OCC
INSP - Final6/10/19976/10/19976/10/1997PPASS
DetailsCarl Dependahl
06/10/97 340 - FINAL REINSPECT LATE P.M. ok, card to contractor
INSP - Final6/10/19976/10/19976/10/1997PPASS
DetailsCarl Dependahl
06/10/97 340 - FINAL REINSPECT
INSP - Final6/6/19976/9/19976/9/1997PNR
DetailsCarl Dependahl
06/09/97 340 - NR, NEED OTHER OK'S
INSP-Final Inspection6/6/19976/9/19976/9/1997ANR
DetailsJoe Tawney
06/09/97 406 - FINAL REINSPECT NOT READY EMERGENCY LIGHTS NOT INSTALLED
INSP-Final Inspection6/5/19976/6/19976/6/1997ACANC
DetailsJoe Tawney
06/06/97 406 - FINAL REINSPECTION 10 A.M. APPOINTMENT - HE SAID... INSPECTION CANCELLED RESCHEDULED FOR MONDAY 6/97
INSP-Final Inspection6/4/19976/5/19976/5/1997ANR
DetailsJoe Tawney
06/05/97 406 - TODD ###-#### FOR TIME NOT READY FOR FINAL INSP
INSP - Conference4/8/19974/8/19974/8/1997 PASS
DetailsCarl Dependahl
/ / 340 - W/ POND CONST, HAS ALL OTHER INSP'S; FRAME OK'D BY 350
INSP - Framing/Rough-in4/7/19974/7/19974/7/1997PPASS
DetailsAlan Hauser
04/07/97 350 - frame reinspect frame ok, ok to cover
INSP - Framing/Rough-in4/7/19974/7/19974/7/1997PNR
DetailsCarl Dependahl
04/07/97 340 - CEILING R/I...need other insp's?
INSP - Conference3/31/19973/31/19973/31/1997 PASS
DetailsCarl Dependahl
/ / 340 - w/ supt. re c/n of 3-28-97
INSP - Framing/Rough-in3/28/19973/28/19973/28/1997PFAIL
DetailsCarl Dependahl
03/28/97 340 - C/N, NEED SHAFT DETAILM, FIREBLOCKS, ANCHORS, OTHER R/IS;
INSP - Framing/Rough-in3/26/19973/26/19973/26/1997PPART
DetailsJim Sly
03/26/97 316 - Need all trade rough-in Insp. OK to insul pending R.I I
INSP - Framing/Rough-in3/19/19973/20/19973/20/1997AFAIL
DetailsCarl Dependahl
03/20/97 340 - PARTIAL ONLY, NEED SHAFT, FIREBLOCKS, OTHER R/I OK'S
INSP - Carpentry3/12/19973/12/19973/12/1997 PASS
DetailsAlan Hauser
/ / 350 - looked at roof nailing, nailed off exceeding the 6/12 o.c. r
INSP - Conference2/20/19972/20/19972/20/1997 PASS
DetailsAlan Hauser
/ / 350 - went over ftns. with contractor
INSP - Foundation2/18/19972/18/19972/18/1997PPASS
DetailsAlan Hauser
02/18/97 350 - ASAP fnd. walls and rebar as per plans, electrical ground in and tied off to
INSP - Footings2/14/19972/14/19972/14/1997PPASS
DetailsAlan Hauser
02/14/97 350 - ftns. ok, ok to pour as per plan