INSP - Final | 9/30/1996 | 10/1/1996 | 10/1/1996 | A | PASS |
Alan Hauser
|
|
|
10/01/96 350 - FINAL OK
|
INSP - Letter of compliance | 10/1/1996 | 10/1/1996 | 10/1/1996 | | PASS |
Alan Hauser
|
|
|
/ / 350 - C/C #11633
|
INSP - Letter of compliance | 10/1/1996 | 10/1/1996 | 10/1/1996 | | PASS |
Alan Hauser
|
|
|
/ / 350 - C/C #11633
|
INSP - Final | 9/30/1996 | 9/30/1996 | 9/30/1996 | P | FAIL |
Alan Hauser
|
|
|
09/30/96 350 - EARLY P.M. NO FINAL CORRECTIONS
|
INSP - Energy code compliance | 8/30/1996 | 8/30/1996 | 8/30/1996 | P | FAIL |
Jim Sly
|
|
|
08/30/96 316 - NR
|
INSP - Energy code compliance | 8/30/1996 | 8/30/1996 | 8/30/1996 | | PASS |
Jim Sly
|
|
|
/ / 316 -
|
INSP - Framing/Rough-in | 8/30/1996 | 8/30/1996 | 8/30/1996 | P | FAIL |
Jim Sly
|
|
|
08/30/96 316 - REINSPECTION C/N...finish corrections..
|
INSP - Framing/Rough-in | 8/30/1996 | 8/30/1996 | 8/30/1996 | | PASS |
Jim Sly
|
|
|
/ / 316 - C/N removed
|
INSP - Framing/Rough-in | 8/29/1996 | 8/29/1996 | 8/29/1996 | P | PASS |
Alan Hauser
|
|
|
08/29/96 350 - OK TO INSULATE AFTER PLBG APPROVED I GOT THERE AHEAD OF P CORRECTIONS TO CHECK ON E.C. INSPECTION
|
INSP - Footings | 8/7/1996 | 8/8/1996 | 8/8/1996 | A | PASS |
Alan Hauser
|
|
|
08/08/96 350 - FTNS OK SET BACKS OK 5'1/2" ON WEST SIDE FRONT CORNER
|