INSP - Final | 3/5/1997 | 3/5/1997 | 3/5/1997 | | PASS |
|
|
|
TERRY RECORDS SENT LETTER. BOB ARCHIBALD OK'D LETTER OF COMPLIANCE THIS DATE.
|
INSP - Letter of compliance | | | 3/5/1997 | | PASS |
|
|
|
ISSUED #12484 C OF C BY MJW AS PER 325 THIS DATE.
|
INSP - Final | 2/28/1997 | 2/28/1997 | 2/28/1997 | P | FAIL |
Alan Hauser
|
|
|
02/28/97 350 - no final, need letter from engineer signing off the lands
|
INSP - Final | 2/24/1997 | 2/24/1997 | 2/24/1997 | P | NR |
Alan Hauser
|
|
|
02/24/97 350 - not ready for final, still need letter from engineer on f from terry records
|
INSP - Conference | 11/22/1996 | 11/22/1996 | 11/22/1996 | A | PASS |
Wes Worcester
|
|
|
talked w/Sta-rite truss and they are placing brng blks ok
|
INSP - Energy code compliance | 11/22/1996 | 11/22/1996 | 11/22/1996 | A | PASS |
Wes Worcester
|
|
|
|
INSP - Framing/Rough-in | 11/21/1996 | 11/22/1996 | 11/22/1996 | A | PASS |
Wes Worcester
|
|
|
8 a.m. appointment
|
INSP - Framing/Rough-in | 11/20/1996 | 11/21/1996 | 11/21/1996 | A | PART |
Wes Worcester
|
|
|
8:30 A.M. APPOINTMENT several truss items in question..stair ldg ?
|
INSP - Framing/Rough-in | 11/20/1996 | 11/20/1996 | 11/20/1996 | P | NR |
Wes Worcester
|
|
|
will meet on site at 8:30 am w/plan and engineering
|
INSP - Framing/Rough-in | 11/18/1996 | 11/19/1996 | 11/19/1996 | A | NR |
|
|
|
11/19/96 333 - ENGR. IS SENDING YOU A LETTER - YIPEE!!!! OTH-OTHER AGENCIES NOT APPROVED placed cn
|
INSP - Conference | 11/7/1996 | 11/8/1996 | 11/8/1996 | A | PART |
Wes Worcester
|
|
|
9 A.M. APPOINTMENT engineer redoing calcs and changes to submit
|
INSP - Carpentry | 11/4/1996 | 11/4/1996 | 11/4/1996 | P | FAIL |
Wes Worcester
|
|
|
11/04/96 342 - SHEAR WALL not nailed off, not to plan and hold downs ins need engineering and engineered fix along with approved plan on site....
|
INSP - Carpentry | 10/30/1996 | 10/31/1996 | 10/31/1996 | A | NR |
Wes Worcester
|
|
|
10/31/96 342 - SHEAR WALL
|
INSP - Framing/Rough-in | 10/31/1996 | 10/31/1996 | 10/31/1996 | | FAIL |
Wes Worcester
|
|
|
/ / 342 - shr not nailed off
|
INSP - Conference | 10/24/1996 | 10/24/1996 | 10/24/1996 | P | NH |
Wes Worcester
|
|
|
|
INSP - Foundation | 9/3/1996 | 9/4/1996 | 9/4/1996 | P | PASS |
Wes Worcester
|
|
|
|
INSP - Conference | 8/30/1996 | 8/30/1996 | 8/30/1996 | A | PART |
Wes Worcester
|
|
|
mti on site for compaction effort
|
INSP - Conference | 8/30/1996 | 8/30/1996 | 8/30/1996 | A | FAIL |
Wes Worcester
|
|
|
need compaction effort report on fill
|
INSP - Footings | 8/29/1996 | 8/30/1996 | 8/30/1996 | A | NR |
Wes Worcester
|
|
|
EARLY - PLEASE!
|
INSP - Footings | 8/30/1996 | 8/30/1996 | 8/30/1996 | A | PART |
Wes Worcester
|
|
|
|