Permit Information
Permit NumberBLD96-02127
StatusFinaled
Name B B R CONSTRUCITON
Site Address 1403 S DIVISION AVE Unit: A
Project NameBODINE TOWNHOMES
Customer Number 
ePlanReviewNo
Description
To construct a new 1506sf two story single family TOWNHOME on zero lot line with a DETACHED 440sf two car garage and approximatly 159sf of concrete patio per approved plans and attached requirement/condition list. (First Floor=721sf) (Second Floor=785sf) ACHD # 96-0658. Plan Check #628. prp
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final7/16/19977/18/19977/18/1997APASS
DetailsJim Storey
07/18/97 301 - FNL -OK FINAL built as per the plan.
INSP - Letter of compliance7/18/19977/18/19977/18/1997 PASS
DetailsJim Storey
/ / 301 - LCI-LETTER OF COMPLIANCE ISSUED 12617
INSP - Letter of compliance7/18/19977/18/19977/18/1997 PASS
DetailsJim Storey
/ / 301 - LCI-LETTER OF COMPLIANCE ISSUED 12617
INSP - Final7/11/19977/11/19977/14/1997PFAIL
DetailsJim Storey
07/14/97 301 - UP TO SIDE WALK LOOK TO RIGHT BIG TREE EYE LEVEL THERES A CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Framing/Rough-in1/10/19971/13/19971/13/1997APASS
DetailsJim Storey
01/13/97 301 - I THINK YOU WERE SUPPOSE TO DO THIS TODAY...(FRIDAY PM).. FRAM-OK FRAMING
INSP - Carpentry1/6/19971/7/19971/7/1997PPASS
DetailsJim Storey
01/07/97 301 - FIREWALL nail ok
INSP - Energy code compliance12/9/199612/9/199612/9/1996PPASS
DetailsJim Storey
12/09/96 301 - LATE PM INSL-OK INSULATION-ENERGY CODE
INSP - Framing/Rough-in12/5/199612/6/199612/6/1996APASS
DetailsJim Storey
12/05/96 301 - FRAM-OK FRAMING
INSP - Framing/Rough-in11/26/199611/26/199611/26/1996PFAIL
DetailsJim Storey
11/26/96 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Carpentry11/25/199611/25/199611/25/1996APART
DetailsWes Worcester
plan ck notes on approved plan are not to construction in lieu of a parapet criteria......
INSP - Conference11/26/199611/25/199611/25/1996
MET WITH WES WORCESTER, JIM STOREY AND BOB ARCHIBALD, AND MR DOUG BODINE. WE REVIEWD THE CONSTRUCTION AND THE APPROVED SET OF PLANS. AFTER REVIEWING WHAT HAD TAKEN PLACE VERSES THE PLAN SIT IS CONCLUDED THAT THE CONTRACTOR HAD BUILT PER HIS APPROVED SET OF PLANS AND THAT IS WHAT WOULD BE APPROVED. GS. 11-26-96 BOB GARRISSON AND I MET WITH MR BODINE ON SITE AND PICKED UP THE APPROVED SET OF PLANS WHICH IS IN CONFLICT WITH THE PLAN REVIEW NOTES AND WHAT THE PLAN REVIEWER RED LINED ON THE PLAN. MR GARRISSON WAS TO RESOVE THE ISSUE WITH HIS PLAN REVIEWER. THIS ISSUE IS CLOSED.
INSP - Conference11/22/199611/22/199611/22/1996 NH
no answer on phone number ###-#### attempted twice
INSP - Conference11/18/199611/19/199611/19/1996APASS
DetailsJim Storey
11/19/96 301 - WIP -WORK IN PROGRESS
INSP - Carpentry11/13/199611/13/199611/13/1996PFAIL
DetailsWes Worcester
c/n left re:1 hr construction in lieu of a parapet
INSP - Carpentry10/25/199610/28/199610/28/1996APASS
DetailsJim Storey
10/25/96 301 - COMMON WALL GWB -OK SHEETROCK NAILING
INSP - Carpentry10/16/199610/17/199610/17/1996APART
DetailsWes Worcester
10/17/96 342 - COMMON WALL. 8:30 APPOINTMENT
INSP - Conference10/17/199610/17/199610/17/1996 PART
DetailsWes Worcester
/ / 342 - need meeting with bldr, tji, (resubmittal)? and framer...Cal