Permit Information
Permit NumberBLD96-02179
StatusFinaled
Name FACILITIES AND OPERATIONS
Site Address 400 FORT
Project NameSCHOOL
Customer Number 
ePlanReviewNo
Description
NEW BUILDING FACILITIES FOR FACILITIES AND OPERATIONS COMPOUND, BOISE, ID PHASE II PC #452-96 WAREHOUSE AND MAINTENANCE BUILDING PER PLANS ON FILE THAT WERE REVIEWED AND APPROVED BY THE IDAHO DEPARTMENT OF LABOR AND INDUSTRIAL STANDARDS. DAR
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final11/20/199711/21/199711/21/1997APASS
Details
card signed for perm
Permanent Occupancy 11/21/199711/21/1997 DONE
Details
INSP - Conference9/22/19979/23/19979/23/1997APASS
Details
09/23/97 333 - dennis contact person
INSP - Conference8/25/19978/25/19978/25/1997 PASS
Details
/ / 333 - talked to Gus about finals
INSP-Final Inspection6/12/19976/16/19976/16/1997APASS
Details
perm occ ok, bollards and fe installed
INSP - Partial final6/12/19976/13/19976/13/1997AFAIL
Details
06/13/97 333 - OTH-OTHER AGENCIES NOT APPROVED
INSP - Partial final6/13/19976/13/19976/13/1997PPART
Details
06/13/97 333 - card signed for temp
INSP - Partial final6/3/19976/3/19976/2/1997PPART
Details
06/03/97 333 - BLD.#I PARTIAL FINAL FOR TEMPORARY. card signed for temp west half
INSP-Final Inspection5/30/19975/30/19975/30/1997PPART
Details
temp, need bollards to protect gas mains, need fe's hung
INSP - Temporary occupancy5/29/19975/30/19975/29/1997AFAIL
Details
05/30/97 333 - not ready
INSP - Framing/Rough-in4/29/19974/30/19974/29/1997AFAIL
Details
04/30/97 333 - arround 10 if possible CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Framing/Rough-in4/4/19974/7/19974/6/1997AFAIL
Details
04/07/97 333 - OTH-OTHER AGENCIES NOT APPROVED
INSP - Framing/Rough-in3/31/19974/1/19973/31/1997APASS
Details
04/01/97 333 - FRAM-OK FRAMING
INSP - Framing/Rough-in3/3/19973/4/19973/3/1997AFAIL
Details
03/04/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Framing/Rough-in2/27/19972/28/19972/27/1997AFAIL
Details
02/28/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Framing/Rough-in1/27/19971/28/19971/28/1997APART
Details
01/28/97 333 - FNL -OK FINAL ok to cover lids
INSP - Framing/Rough-in1/23/19971/24/19971/24/1997AFAIL
DetailsJim Storey
01/24/97 301 - TRANS TO KIM.M
INSP - Framing/Rough-in1/24/19971/24/19971/24/1997 FAIL
Details
/ / 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Conference1/7/19971/7/19971/7/1997 PASS
TALKED WITH STEVE WITH STAPLEY ABOUT ROOF NAILING AND TOLD HIM WHAT HAD HAPPENED AND I NEEDED A REPORT FROM HIM
INSP - Roof12/20/199612/23/199612/23/1996APASS
Details
12/23/96 333 - nailing ok AFTER ENGINEERS REPORT RECIEVED PARTIAL COVER WITH SNOW
INSP - Roof12/19/199612/20/199612/20/1996ANR
Details
12/20/96 333 - not ready snow