INSP - Final | 11/20/1997 | 11/21/1997 | 11/21/1997 | A | PASS |
|
|
|
card signed for perm
|
Permanent Occupancy | | 11/21/1997 | 11/21/1997 | | DONE |
|
|
|
|
INSP - Conference | 9/22/1997 | 9/23/1997 | 9/23/1997 | A | PASS |
|
|
|
09/23/97 333 - dennis contact person
|
INSP - Conference | 8/25/1997 | 8/25/1997 | 8/25/1997 | | PASS |
|
|
|
/ / 333 - talked to Gus about finals
|
INSP-Final Inspection | 6/12/1997 | 6/16/1997 | 6/16/1997 | A | PASS |
|
|
|
perm occ ok, bollards and fe installed
|
INSP - Partial final | 6/12/1997 | 6/13/1997 | 6/13/1997 | A | FAIL |
|
|
|
06/13/97 333 - OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Partial final | 6/13/1997 | 6/13/1997 | 6/13/1997 | P | PART |
|
|
|
06/13/97 333 - card signed for temp
|
INSP - Partial final | 6/3/1997 | 6/3/1997 | 6/2/1997 | P | PART |
|
|
|
06/03/97 333 - BLD.#I PARTIAL FINAL FOR TEMPORARY. card signed for temp west half
|
INSP-Final Inspection | 5/30/1997 | 5/30/1997 | 5/30/1997 | P | PART |
|
|
|
temp, need bollards to protect gas mains, need fe's hung
|
INSP - Temporary occupancy | 5/29/1997 | 5/30/1997 | 5/29/1997 | A | FAIL |
|
|
|
05/30/97 333 - not ready
|
INSP - Framing/Rough-in | 4/29/1997 | 4/30/1997 | 4/29/1997 | A | FAIL |
|
|
|
04/30/97 333 - arround 10 if possible CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 4/4/1997 | 4/7/1997 | 4/6/1997 | A | FAIL |
|
|
|
04/07/97 333 - OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Framing/Rough-in | 3/31/1997 | 4/1/1997 | 3/31/1997 | A | PASS |
|
|
|
04/01/97 333 - FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 3/3/1997 | 3/4/1997 | 3/3/1997 | A | FAIL |
|
|
|
03/04/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 2/27/1997 | 2/28/1997 | 2/27/1997 | A | FAIL |
|
|
|
02/28/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 1/27/1997 | 1/28/1997 | 1/28/1997 | A | PART |
|
|
|
01/28/97 333 - FNL -OK FINAL ok to cover lids
|
INSP - Framing/Rough-in | 1/23/1997 | 1/24/1997 | 1/24/1997 | A | FAIL |
Jim Storey
|
|
|
01/24/97 301 - TRANS TO KIM.M
|
INSP - Framing/Rough-in | 1/24/1997 | 1/24/1997 | 1/24/1997 | | FAIL |
|
|
|
/ / 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Conference | 1/7/1997 | 1/7/1997 | 1/7/1997 | | PASS |
|
|
|
TALKED WITH STEVE WITH STAPLEY ABOUT ROOF NAILING AND TOLD HIM WHAT HAD HAPPENED AND I NEEDED A REPORT FROM HIM
|
INSP - Roof | 12/20/1996 | 12/23/1996 | 12/23/1996 | A | PASS |
|
|
|
12/23/96 333 - nailing ok AFTER ENGINEERS REPORT RECIEVED PARTIAL COVER WITH SNOW
|
INSP - Roof | 12/19/1996 | 12/20/1996 | 12/20/1996 | A | NR |
|
|
|
12/20/96 333 - not ready snow
|