INSP - Letter of compliance | 12/17/1996 | 12/17/1996 | 12/17/1996 | | PASS |
|
|
|
/ / 333 - setter #12359
|
INSP - Letter of compliance | 12/17/1996 | 12/17/1996 | 12/17/1996 | | PASS |
|
|
|
/ / 333 - setter #12359
|
INSP - Final | 12/16/1996 | 12/16/1996 | 12/17/1996 | P | PASS |
|
|
|
12/16/96 333 - FNL -OK FINAL
|
INSP - Carpentry | 11/12/1996 | 11/12/1996 | 11/12/1996 | P | PASS |
Wes Worcester
|
|
|
|
INSP - Energy code compliance | 11/6/1996 | 11/6/1996 | 11/6/1996 | P | PASS |
Wes Worcester
|
|
|
11/06/96 342 - LATE PM
|
INSP - Framing/Rough-in | 11/6/1996 | 11/6/1996 | 11/6/1996 | | PART |
Wes Worcester
|
|
|
/ / 342 - still has to fix cut floor joist
|
INSP - Framing/Rough-in | 11/4/1996 | 11/5/1996 | 11/5/1996 | A | PART |
Wes Worcester
|
|
|
11/04/96 342 - brace gable uprights, fix cur tji floor joist
|
INSP - Framing/Rough-in | 10/31/1996 | 10/31/1996 | 10/31/1996 | P | FAIL |
|
|
|
mech r/i not completed
|
INSP - Framing/Rough-in | 10/29/1996 | 10/30/1996 | 10/30/1996 | P | FAIL |
|
|
|
left corr mech r/i not completed
|
INSP - Foundation | 9/17/1996 | 9/17/1996 | 9/17/1996 | P | FAIL |
|
|
|
09/17/96 400 - poured pior to insp
|