INSP - Final | 1/29/1998 | 1/29/1998 | 1/29/1998 | | PASS |
|
|
|
Final -
|
Permanent Occupancy | | 1/29/1998 | 1/29/1998 | | DONE |
|
|
|
|
INSP - Final | 1/27/1998 | 1/28/1998 | 1/28/1998 | P | PART |
|
|
|
01/28/98 333 - need to check on exit signs
|
INSP-Final Inspection | 1/26/1998 | 1/27/1998 | 1/27/1998 | A | PASS |
Rick Jackson
|
|
|
tested alarms - passed. building not fully smoke protected (owner provided letter acknowledging)
|
INSP-Final Inspection | 1/23/1998 | 1/26/1998 | 1/26/1998 | A | FAIL |
Rick Jackson
|
|
|
alarms not ready.
|
INSP-Final Inspection | 1/20/1998 | 1/22/1998 | 1/22/1998 | A | CANC |
Rick Jackson
|
|
|
01/22/98 409 - cancelled by Sundance contractor. scheduled for 1/26
|
INSP-Sprinkler Rough-in/Hydro | 1/20/1998 | 1/22/1998 | 1/22/1998 | A | CANC |
Rick Jackson
|
|
|
01/22/98 409 - ###-#### cancelled by Sundance Contractor. rescheduled for 1/26
|
INSP - Final | 10/16/1997 | 10/16/1997 | 10/16/1997 | P | FAIL |
Tom Arcoraci
|
|
|
correc left with superintendent on site all day per g. slane
|
INSP - Temporary occupancy | 10/16/1997 | 10/16/1997 | 10/16/1997 | P | PASS |
Tom Arcoraci
|
|
|
on site all day per g. slane
|
INSP-Final Inspection | 10/15/1997 | 10/16/1997 | 10/16/1997 | A | FAIL |
|
|
|
sundance requested 9:00 am. the fire alarm system was not complete, gave correction notice to Zicarro (sundance) need to test all pulls, smokes, tampers. need to check door lock releases. location of several detectors are incorrect, 2 missing. retest at 1pm, will notify owner of no occupancy if not ready.
|
INSP-Final Inspection | 10/16/1997 | 10/16/1997 | 10/16/1997 | P | PART |
|
|
|
corrections required, notice issued, approved for temp occupancy. alarm system requires
|
INSP-Final Inspection | 10/15/1997 | 10/15/1997 | 10/15/1997 | P | FAIL |
Rick Jackson
|
|
|
fire alarms not ready. will try again on 10/16/97 - 9:00am
|
INSP - Framing/Rough-in | 9/8/1997 | 9/9/1997 | 9/9/1997 | A | PASS |
|
|
|
09/09/97 333 - FIRE CAULKING at entry ok
|
INSP-Sprinkler Rough-in/Hydro | 9/3/1997 | 9/5/1997 | 9/5/1997 | P | PART |
Joe Tawney
|
|
|
09/05/97 406 - OK ON TEST OF PRE ACTION SYSTEM STROBES TOO HIGH & INTENS
|
INSP - Ceiling grid | 8/28/1997 | 8/29/1997 | 8/29/1997 | A | PASS |
|
|
|
08/29/97 333 - north and south wings and entry ok
|
INSP - Ceiling grid | 8/21/1997 | 8/21/1997 | 8/21/1997 | | NR |
|
|
|
08/21/97 333 - gate locked there at 4:45pm
|
INSP - Ceiling grid | 8/21/1997 | 8/21/1997 | 8/21/1997 | P | FAIL |
|
|
|
gate locked 4:45pm
|
INSP - Framing/Rough-in | 8/4/1997 | 8/4/1997 | 8/4/1997 | P | PASS |
|
|
|
08/04/97 333 - corridor ok
|
INSP-Sprinkler Rough-in/Hydro | 7/29/1997 | 7/30/1997 | 7/30/1997 | A | PASS |
|
|
|
call rick at ###-#### pager so you set up time.
|
INSP-Sprinkler Rough-in/Hydro | 7/22/1997 | 7/23/1997 | 7/23/1997 | A | PART |
|
|
|
OK TO COVER MAIN LOBBY AND SOUTH EAST OFFICE AREA
|
INSP - Framing/Rough-in | 7/15/1997 | 7/15/1997 | 7/15/1997 | P | FAIL |
|
|
|
07/15/97 333 - other trades not passed
|
INSP - Framing/Rough-in | 7/3/1997 | 7/3/1997 | 7/3/1997 | P | PASS |
|
|
|
07/03/97 333 - roof nailing ok
|
INSP-Sprinkler Rough-in/Hydro | 7/2/1997 | 7/3/1997 | 7/3/1997 | P | PART |
Joe Tawney
|
|
|
07/03/97 406 - SPKLR ROUGH IN OK TO COVER ART STORAGE AND ART VAULT
|
INSP - Framing/Rough-in | 6/27/1997 | 6/30/1997 | 6/30/1997 | A | PART |
|
|
|
06/30/97 333 - north half and south part
|
INSP-Sprinkler Rough-in/Hydro | 6/27/1997 | 6/30/1997 | 6/30/1997 | A | PART |
Joe Tawney
|
|
|
OK TO COVER IN CLASSROOM AREA AND A TO E AREA
|
INSP - Roof | 6/18/1997 | 6/19/1997 | 6/19/1997 | A | PASS |
|
|
|
06/19/97 333 - roof nailing ok
|
INSP - Roof | 6/17/1997 | 6/18/1997 | 6/18/1997 | A | FAIL |
|
|
|
06/18/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPL
|
INSP - Roof | 6/12/1997 | 6/13/1997 | 6/13/1997 | A | pass |
|
|
|
06/13/97 333 - SUB ROOF NAILING
|
INSP - Framing/Rough-in | 6/2/1997 | 6/2/1997 | 6/2/1997 | P | PASS |
|
|
|
06/03/97 333 - roof nailing ok
|
INSP - Wall cover | 5/29/1997 | 5/30/1997 | 5/29/1997 | A | PASS |
|
|
|
05/30/97 333 - FIRE TAPING 1 side 2hr walls ok
|
INSP - Wall cover | 5/23/1997 | 5/27/1997 | 5/26/1997 | A | PART |
|
|
|
05/27/97 333 - shaft wall 2hr wall ok
|
INSP - Framing/Rough-in | 5/14/1997 | 5/15/1997 | 5/14/1997 | A | PASS |
|
|
|
05/15/97 333 - FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 5/13/1997 | 5/13/1997 | 5/11/1997 | P | PART |
|
|
|
05/13/97 333 - ramp ok
|
INSP - Conference | 4/29/1997 | 4/30/1997 | 4/29/1997 | P | PASS |
|
|
|
04/30/97 333 - recieved inspection reports
|
INSP - Masonry | 4/22/1997 | 4/22/1997 | 4/21/1997 | P | PART |
|
|
|
04/22/97 333 - canceled by contractor
|