INSP - Letter of compliance | | | 3/14/1997 | | PASS |
|
|
|
ISSUED #12497 C OF C BY MJW THIS DATE.
|
INSP - Final | 2/18/1997 | 2/19/1997 | 2/19/1997 | A | PASS |
Carl Dependahl
|
|
|
02/19/97 340 - BLDG 4 MIDDLE, SO. AREA. CARD TO HP MGR
|
INSP - Final | 2/11/1997 | 2/12/1997 | 2/12/1997 | A | PASS |
Joe Tawney
|
|
|
FINAL OK FOR CERT OF COMPL
|
INSP - Carpentry | 1/30/1997 | 1/30/1997 | 1/30/1997 | | PART |
Carl Dependahl
|
|
|
/ / 340 - BLDG 4 MIDDLE; RAISED FLOOR AT SOUTH PART...NEED FINALS
|
INSP - Final | 10/16/1996 | 10/24/1996 | 10/24/1996 | A | FAIL |
Carl Dependahl
|
|
|
10/23/96 340 - MAIN FLR. IMP. YOU CAN FIND PAUL JOHNSON AT COLUMN I - 7. ###-####...C/N,SIGNED FOR T/O. CARD TO CONTRACTOR
|
INSP - Conference | 10/23/1996 | 10/23/1996 | 10/23/1996 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - FLOOR SYSTEM, BLDG 4. DISCUSSED INSP PROCESS W/ PROJ. MGR.
|
INSP - Final | 10/16/1996 | 10/23/1996 | 10/23/1996 | P | PASS |
Joe Tawney
|
|
|
10/23/96 406 - MAIN FLR. IMP. BLDG.4. PAUL JOHNSON - ###-####. PAUL CAN FNL -OK FINAL
|