INSP - Final | 11/30/1998 | 11/30/1998 | 11/30/1998 | A | PASS |
Carl Dependahl
|
|
|
fees paid per Linda H...card to Cathy.
|
Permanent Occupancy | | 11/30/1998 | 11/30/1998 | | DONE |
|
|
|
|
INSP - Final | 9/2/1998 | 9/2/1998 | 9/2/1998 | A | NR |
Carl Dependahl
|
|
|
has t/o; referred to Linda H. Also, will send fax copy c/o card as not all signed in office. keep c/n
|
INSP - Final | 8/31/1998 | 8/31/1998 | 8/31/1998 | P | PART |
Carl Dependahl
|
|
|
cert of value in...to be fee due'd per Linda H.
|
INSP - Final | 8/26/1998 | 8/26/1998 | 8/26/1998 | P | PART |
Carl Dependahl
|
|
|
greg. cert. of value submitted to Linda, firestop ok will chk w/ Linda re ok to issue c/o.
|
INSP - Final | 8/24/1998 | 8/25/1998 | 8/25/1998 | P | FAIL |
Carl Dependahl
|
|
|
2:00 pm Greg 1208 521 8520...need cert. of value, firestop(s) at boiler rm. will recall asap
|
INSP - Final | 8/24/1998 | 8/24/1998 | 8/24/1998 | A | FAIL |
Carl Dependahl
|
|
|
conf only; w/ Greg, proj mgr for Ormond..also need all fees paid per Linda H.
|
INSP-Final Inspection | 8/20/1998 | 8/21/1998 | 8/21/1998 | A | PASS |
Joe Tawney
|
|
|
08/21/98 406 - greg 208 521 8520 REINSP OK FOR PERM OCC
|
INSP - Final | 8/11/1998 | 8/11/1998 | 8/11/1998 | P | FAIL |
Carl Dependahl
|
|
|
need fire ok, complete install roll-up doors & actuators, hand rails,etc.
|
INSP-Final Inspection | 8/7/1998 | 8/7/1998 | 8/7/1998 | | FAIL |
Joe Tawney
|
|
|
08/07/98 406 - greg ###-#### REISP FAIL ROLL DOWN DOORS ELV HEAT DET SPKLR PROT STROBE CANDELLA
|
INSP - Final | 8/4/1998 | 8/4/1998 | 8/4/1998 | A | NR |
Carl Dependahl
|
|
|
conf w/ arch & busd ...work almost complete, will have cont call asap for final
|
INSP - Final | 7/30/1998 | 7/30/1998 | 7/30/1998 | A | FAIL |
Carl Dependahl
|
|
|
no insp; conf w/ Wendall B. & Scott,arch...roll-up doors didn't fit, back-ordered; keep c/n, need complete final l
|
INSP - Final | 5/21/1998 | 5/21/1998 | 5/21/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - REVIEWED LOCATION OF SMOKE DETECTORS AND HORN/STROBES SEVERA
|
INSP - Final | 5/15/1998 | 5/15/1998 | 5/15/1998 | A | PART |
Carl Dependahl
|
|
|
rec'd resubmittal for oversize penetration assemblies, will verify in field.
|
INSP - Final | 5/14/1998 | 5/14/1998 | 5/14/1998 | A | PART |
Carl Dependahl
|
|
|
c/n re: roll up doors, stair rails, firestops, temporary construction, doors and smoke seals; has signatures, ok for t/o... card to contractor. These items are to be done asap for final.
|
INSP - Final | 5/13/1998 | 5/13/1998 | 5/13/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR TEMP OCC
|
INSP - Final | 5/13/1998 | 5/13/1998 | 5/13/1998 | P | CANC |
Joe Tawney
|
|
|
05/13/98 406 - t/o ?? Cancel entered by inspector
|
INSP - Final | 5/13/1998 | 5/13/1998 | 5/13/1998 | P | FAIL |
Carl Dependahl
|
|
|
for t/o...still need fire, will re check later for ok (PROFIT)
|
INSP - Final | 5/12/1998 | 5/12/1998 | 5/12/1998 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - FINAL FAIL SPKLR SYSTEM AND ALARM SYSTEM ISSUES STILL UNRESO
|
INSP - Final | 5/7/1998 | 5/12/1998 | 5/12/1998 | P | FAIL |
Carl Dependahl
|
|
|
GYM AREA need fire ok
|
INSP - Final | 5/7/1998 | 5/11/1998 | 5/11/1998 | P | FAIL |
Carl Dependahl
|
|
|
FINAL FOR T/O...need all other sig's, fire ok. etc; keep struct c/n
|
INSP-Alarm Testing | 5/11/1998 | 5/11/1998 | 5/11/1998 | P | FAIL |
Joe Tawney
|
|
|
05/11/98 406 - CHRIS/###-#### - ALARM INSP. FINAL FAIL TESTING NOT COMPLETED UNABLE TO SEND SIGNALS OFF PREMISES
|
INSP-Sprinkler Rough-in/Hydro | 5/11/1998 | 5/11/1998 | 5/11/1998 | P | NR |
Joe Tawney
|
|
|
05/11/98 406 - GREG/ ###-#### - SPRINKLER INSP. SPKLR CONTRACTOR NOT ON SITE NOT ABLE TO LOOK AT SPKLRS DUE TO ALARM TES
|
INSP - Final | 5/7/1998 | 5/7/1998 | 5/7/1998 | P | FAIL |
Carl Dependahl
|
|
|
FOLLOW UP TO PROFIT MEETING...keep c/n
|
INSP - Final | 5/1/1998 | 5/5/1998 | 5/5/1998 | A | FAIL |
Carl Dependahl
|
|
|
profit pre final conf....need fire alarm plans submitted & approved,install rated doors, get other t/o's. complete c/n's...etc.
|
INSP - Final | 5/5/1998 | 5/5/1998 | 5/5/1998 | | PART |
Joe Tawney
|
|
|
05/05/98 406 - "PROFIT" PRE-FINAL CONFERENCE AT SCHOOL...CALL CARL D. 20 FLOYD...HE'S COMING, TOO. PRE FINAL CONF BIG ISSUE ALARM SYSTEM PLANS AND APPROVAL
|
INSP - Framing/Rough-in | 5/4/1998 | 5/4/1998 | 5/4/1998 | P | PART |
Carl Dependahl
|
|
|
no insp, conf w/ bldr, other insp's...for "Profit" meeting sched for 5-5-98
|
INSP - Final | 5/1/1998 | 5/5/1998 | 5/1/1998 | A | |
George Slane
|
|
|
GEORGE, THIS IS PROFIT PRE-FINAL CONF. I CHECKED W/ FLOYD, HE'S STILL AWAITING CORRECT ALARM SUBMITTAL
|
INSP - Framing/Rough-in | 4/27/1998 | 4/29/1998 | 4/29/1998 | P | PART |
Carl Dependahl
|
|
|
Scheduled by Hello!. Contact phone is [8537685]. clg grid b&c
|
INSP - Framing/Rough-in | 4/21/1998 | 4/21/1998 | 4/21/1998 | P | PASS |
Wes Worcester
|
|
|
04/21/98 342 - ceiling grid ok in hallways phone is [8537685].
|
INSP-Sprinkler Rough-in/Hydro | 4/15/1998 | 4/15/1998 | 4/15/1998 | | PART |
|
|
|
OK ON HYDRO TEST EXCEPT FDC PIPING OK ON ROUGH IN OF ENTIRE BLDG EXCEPT COVERAGE IN MAINT CHASES
|
INSP - Framing/Rough-in | 4/14/1998 | 4/14/1998 | 4/14/1998 | P | NR |
Carl Dependahl
|
|
|
NW Jr. High...keep c/n re 1hr lid, handrails, etc
|
INSP - Framing/Rough-in | 4/14/1998 | 4/13/1998 | 4/13/1998 | P | NR |
Carl Dependahl
|
|
|
no insp...conf. w/ supt. re previous c/n.
|
INSP - Framing/Rough-in | 4/8/1998 | 4/8/1998 | 4/8/1998 | P | FAIL |
Carl Dependahl
|
|
|
ceiling grid at locker room, kitchen, etc...c/n re firestops at lid & corridor wall at "B", handrails (brackets) thru-out, etc.
|
INSP - Framing/Rough-in | 3/31/1998 | 3/31/1998 | 3/31/1998 | P | PART |
Carl Dependahl
|
|
|
handrails, kitchen clg grid, locker room need consult w/ GS re handrails, brackets protrude .
|
INSP - Framing/Rough-in | 3/31/1998 | 3/31/1998 | 3/31/1998 | P | NR |
Carl Dependahl
|
|
|
CEILING GRID AREA A AND B, ###-####...need seismic braces all areas
|
INSP - Framing/Rough-in | 3/31/1998 | 3/27/1998 | 3/27/1998 | P | PART |
Carl Dependahl
|
|
|
not insp, conf w/ proj. mgr.
|
INSP - Framing/Rough-in | 3/27/1998 | 3/27/1998 | 3/27/1998 | P | NR |
Carl Dependahl
|
|
|
HAND RAILS \\JOE ###-####...not at site...5:00 pm
|
INSP - Framing/Rough-in | 3/24/1998 | 3/24/1998 | 3/24/1998 | P | NR |
Carl Dependahl
|
|
|
not insp, conf w/ greg, proj mgr...need eng's letter of acceptance of structure, etc prior to struct sign-off
|
INSP - Framing/Rough-in | 3/13/1998 | 3/16/1998 | 3/16/1998 | A | NR |
Carl Dependahl
|
|
|
YOU TALKED TO JOE ABOUT THIS ON FRIDAY ###-####...need firestop penetrations at 1hr lid mens, women's shower rms. ok to begin concrete board placement, will reinsp pm
|
INSP - Framing/Rough-in | 3/12/1998 | 3/11/1998 | 3/11/1998 | P | NR |
Carl Dependahl
|
|
|
REV'D PLANS W/ RUSS
|
INSP - Framing/Rough-in | 3/11/1998 | 3/10/1998 | 3/10/1998 | P | NR |
Carl Dependahl
|
|
|
conf. w/ russ re insp's at school...reviewed plan
|
INSP - Framing/Rough-in | 2/19/1998 | 2/19/1998 | 2/19/1998 | P | PART |
Carl Dependahl
|
|
|
part; ok to drop tiles in areas e,g,h...off corridor at classrooms
|
INSP - Framing/Rough-in | 2/19/1998 | 2/19/1998 | 2/19/1998 | P | FAIL |
Carl Dependahl
|
|
|
fire caulking and ceiling\area d g h\###-#### joe hanson keep c/n, need arch's detail for shafts, complete firestops at corr.walls in home ec. area, boiler room, kitchen & band area lids ok to continue
|
INSP - Framing/Rough-in | 2/17/1998 | 2/18/1998 | 2/18/1998 | P | CANC |
Wes Worcester
|
|
|
02/18/98 342 - CANCELLED ABD RESCHEDULED BY CONTRACTOR
|
INSP - Framing/Rough-in | 2/13/1998 | 2/13/1998 | 2/13/1998 | A | PART |
Carl Dependahl
|
|
|
H WING, NEED COMPLETE TOP OF WLL ASSY PER FIX DETAIL AT SOUTH SIDE E-W CORRIDOR AT 2ND FL...ROOMS OF N-S CORR. OK TODROP TILES. STILL NEED ARCH'S DETAIL FOR SHAFT FIX, KEEP C/N.
|
INSP - Framing/Rough-in | 2/11/1998 | 2/12/1998 | 2/12/1998 | P | PART |
Carl Dependahl
|
|
|
area h ###-#### STILL NEED ARCHS OK FOR SHAFTS...ROOMS OFF CORRIDOR OK TO SET TILE AT GRID
|
INSP - Framing/Rough-in | 2/11/1998 | 2/10/1998 | 2/10/1998 | P | PART |
Carl Dependahl
|
|
|
not frame, conf w/ arch scott & russ
|
INSP-Sprinkler Rough-in/Hydro | 2/9/1998 | 2/9/1998 | 2/9/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - PARTIAL ROUGH IN OF SPKLR SYSTEMS 2ND FLR AND PART OF 1ST FL
|
INSP - Carpentry | 2/4/1998 | 2/3/1998 | 2/3/1998 | A | FAIL |
Carl Dependahl
|
|
|
KEEP C/N...NEED DETAIL FOR SHAFTS AND STRUCT PENETRATIONS.
|
INSP - Framing/Rough-in | 2/2/1998 | 2/2/1998 | 2/2/1998 | P | FAIL |
Carl Dependahl
|
|
|
###-#### IF THIS DON'T WORK FOR THIS AFTER NOON. MORNING WOULD BE FINE...need complete firestops & framing
|
INSP - Framing/Rough-in | 1/29/1998 | 1/30/1998 | 1/30/1998 | A | PART |
Carl Dependahl
|
|
|
covering class room ceiling/ area e. ###-####...AREA E, 1ST FL; ROOMSIDE CORRIDOR WALLS OK TO INSTALL CLG TILES, NEED RECHK UTIL & ELEC ROOMS, 1HR NOT COMPLETED.
|
INSP - Conference | 1/30/1998 | 1/29/1998 | 1/29/1998 | P | PASS |
Carl Dependahl
|
|
|
W/ SUPT. RE INSTALL OF "TOP-OF-WALL" RESUBMITTED DETAIL; TOLD TO ADD FASTENERS PER SPEC.
|
INSP - Framing/Rough-in | 1/28/1998 | 1/28/1998 | 1/28/1998 | P | PART |
Carl Dependahl
|
|
|
CEILING GRID--FIRE LID--JOE AT ###-####...LOCKER RM AREAS, GRID OK TO GYP.
|
INSP - Conference | 1/22/1998 | 1/22/1998 | 1/22/1998 | P | PASS |
Carl Dependahl
|
|
|
sent fax letter to Scott at lombard-conrad: detail ok if fasteners detailed
|
INSP - Carpentry | 1/22/1998 | 1/21/1998 | 1/21/1998 | P | FAIL |
Carl Dependahl
|
|
|
chk firestopping above clg lines at area E; incomplete, need to submit detail for top of wall at occ sep areas & complete, recall when ready
|
INSP - Conference | 1/20/1998 | 1/21/1998 | 1/21/1998 | P | PASS |
Carl Dependahl
|
|
|
3:00 w/ arch; see if 408 can attend. MET W/ SCOTT, GREG & JOE AT SITE, GOT DETAIL FOR RATED WALL TOP, WILL REVIEW.
|
INSP - Conference | 1/20/1998 | 1/20/1998 | 1/20/1998 | A | PASS |
Carl Dependahl
|
|
|
W/ JOE & ARCH....WANT TO SET MEETING W/ RUSS & PROJ. MGR.
|
INSP - Conference | 1/20/1998 | 1/16/1998 | 1/16/1998 | P | PASS |
Carl Dependahl
|
|
|
W/ SUPT. RE: RESPONSE TO C/N'S FOR FIRESTOPS & "TESTED ASSY" OF RATED WALLS; WILL NEED TO MEET W/ ARCH.
|
INSP-Supply line flush | 1/16/1998 | 1/16/1998 | 1/16/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON UNDERGROUND FLUSH
|
INSP - Conference | 1/14/1998 | 1/13/1998 | 1/13/1998 | P | PASS |
Carl Dependahl
|
|
|
REC'D FIRESTOP SPECS, DISCUSSED W/ SUPT.
|
INSP - Framing/Rough-in | 1/12/1998 | 1/13/1998 | 1/13/1998 | P | PART |
Carl Dependahl
|
|
|
Joe ###-####...clg frame at area B, no access to mezzanine. verbal c/n re roof drains & other penetrations of 1 hr. lid. need detail & backing at hatches, breaks, etc. OK to begin gyp.
|
INSP - Conference | 1/7/1998 | 1/7/1998 | 1/7/1998 | P | PASS |
Carl Dependahl
|
|
|
W/ SUPT. RE SHAFT INSTALL
|
INSP - Conference | 1/6/1998 | 1/6/1998 | 1/6/1998 | A | PASS |
Carl Dependahl
|
|
|
W/ RUSS RE SHAFT DETAIL AND ARCH'S LETTER...TYPE 2 HOOD, SHAFT ONLY REQ'D AT STRUCT PENETRATIONS OF RATED CONST.
|
INSP - Conference | 12/30/1997 | 12/30/1997 | 12/30/1997 | A | PASS |
Carl Dependahl
|
|
|
W/ SUPT. RE C/N
|
INSP - Framing/Rough-in | 12/17/1997 | 12/18/1997 | 12/18/1997 | A | FAIL |
Carl Dependahl
|
|
|
AREA F AND B CEILING...need arch's detail and clarification re: kitch. duct/ hood type; top of wall closure at rated walls w/ tested assy reference.
|
INSP - Carpentry | 12/17/1997 | 12/17/1997 | 12/18/1997 | P | PART |
Carl Dependahl
|
|
|
12/18/97 340 - AREA F LID....PART
|
INSP - Conference | 12/16/1997 | 12/15/1997 | 12/15/1997 | P | PASS |
Carl Dependahl
|
|
|
W/ RUSS RE JR. HIGH PROJECTS; REVIEWED PLAN.
|
INSP - Framing/Rough-in | 12/11/1997 | 12/15/1997 | 12/15/1997 | P | FAIL |
Carl Dependahl
|
|
|
AREA G, 2ND FL...C/N, NEED VERIFY OTHER R/I'S, FIRESTOP OCC. SEPARATION; INSTALL FIRESTOPS THROUGHOUT,REMOVE NON-FRT WOOD AND WOOD PENETRATIONS. SHOW ALL CEILING FRAMING AT CORRIDOR, ETC.(SHAFTS???)
|
INSP - Conference | 12/15/1997 | 12/12/1997 | 12/12/1997 | P | PASS |
Carl Dependahl
|
|
|
W/ SUPT. RE CLG DETAIL
|
INSP - Conference | 12/10/1997 | 12/10/1997 | 12/10/1997 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - W/ BILL FULLER, PGR.###-#### RE SMOKE/FIRE DAMPERS AT CORRID
|
INSP - Conference | 12/8/1997 | 12/5/1997 | 12/5/1997 | A | PASS |
Carl Dependahl
|
|
|
W/ RUSS RE JR HIGH PROJECTS
|
INSP - Conference | 12/2/1997 | 12/2/1997 | 12/2/1997 | A | PASS |
Carl Dependahl
|
|
|
W/ RUSS RE SCHOOL PLAN/ MEETING W/ SUPT & PROJ. MGR.
|
INSP - Carpentry | 11/26/1997 | 11/26/1997 | 11/26/1997 | P | PART |
Carl Dependahl
|
|
|
AREA H LIDS...NEED GYP PER DETAIL AT CORR.
|
INSP - Framing/Rough-in | 11/26/1997 | 11/26/1997 | 11/26/1997 | P | FAIL |
Carl Dependahl
|
|
|
NEED COMPLETE FIRESTOPS, 1HR LID FASTENERS, ETC. INT ROOM PARTITIONS OK TO COVER AREA H&E.
|
INSP - Conference | 11/25/1997 | 11/25/1997 | 11/25/1997 | P | PASS |
Carl Dependahl
|
|
|
W/ BOB A. RE APPROVED VAPOR BARRIER MAT'L
|
INSP - Framing/Rough-in | 11/25/1997 | 11/25/1997 | 11/25/1997 | P | NR |
Carl Dependahl
|
|
|
AREA H; ALSO CHK CLG AT E...HAS C/N
|
INSP - Framing/Rough-in | 11/24/1997 | 11/24/1997 | 11/24/1997 | P | NR |
Carl Dependahl
|
|
|
area H
|
INSP - Carpentry | 11/21/1997 | 11/19/1997 | 11/19/1997 | P | FAIL |
Carl Dependahl
|
|
|
KEEP C/N RE: 1HR CORRIDOR LIDS. DISCUSSED ISSUE W/ RUSS...HE'S DOING SCHOOL AT COLUMBIA VILLAGE. CONTRACTOR HASN'T RESUBMITTED OR RECALLED INSP.
|
INSP - Miscellaneous | 11/18/1997 | 11/19/1997 | 11/19/1997 | A | PART |
Carl Dependahl
|
|
|
8 yards poured 11/18/97; MTI ONSITE
|
INSP - Miscellaneous | 11/13/1997 | 11/13/1997 | 11/13/1997 | P | PART |
Wes Worcester
|
|
|
11/13/97 342 - TUES= 8 YDS EXTERIOR AND INTERIOR WALLS WED= 8 YDS EXTERIOR AND INTERIOR WALLS RAN OUT OF TIME, WILL CK BK, SPE THURS= 8 YDS EXTERIOR AND INTERIOR WALLS INSPECTOR ON SITE
|
INSP - Foundation | 11/10/1997 | 11/12/1997 | 11/12/1997 | A | PART |
|
|
|
11/12/97 333 - 11/7- 5 YRDS INTERIOR AND EXTERIOR WALLS 11/10- 10 YRDS, DITO ok pending special insp report
|
INSP - Carpentry | 11/7/1997 | 11/7/1997 | 11/7/1997 | P | PART |
Carl Dependahl
|
|
|
11/07/97 340 - GROUT, MTI ONSITE; 1HR LID AT SEC. E&H. TOOK FROM 342. ne
|
INSP - Carpentry | 11/7/1997 | 11/7/1997 | 11/7/1997 | | PART |
Carl Dependahl
|
|
|
11/07/97 340 - GROUT, MTI ONSITE; 1HR LID AT SEC. E&H. TOOK FROM 342. ne
|
INSP - Miscellaneous | 11/6/1997 | 11/7/1997 | 11/7/1997 | A | CANC |
Wes Worcester
|
|
|
11/07/97 342 - GROUT REPORT=6YDS INTERIOR AND EXTERIOR WALLS
|
INSP - Miscellaneous | 11/6/1997 | 11/6/1997 | 11/6/1997 | P | CANC |
|
|
|
given to carl
|
INSP - Miscellaneous | 11/5/1997 | 11/5/1997 | 11/5/1997 | A | PART |
Carl Dependahl
|
|
|
8 YARDS OF INTERIOR AND EXTERIOR WALLS MTI ONSITE
|
INSP - Miscellaneous | 11/4/1997 | 11/5/1997 | 11/5/1997 | A | PART |
Carl Dependahl
|
|
|
GROUT REPORT//12 YDS INTERIOR AND EXTERIOR WALLS MTI ONSITE
|
INSP - Carpentry | 11/4/1997 | 11/4/1997 | 11/4/1997 | P | PART |
Carl Dependahl
|
|
|
GROUT, MTI ONSITE...
|
INSP - Foundation | 11/3/1997 | 11/4/1997 | 11/4/1997 | A | CANC |
|
|
|
11/04/97 333 - 11/03/97 GROUT REPORT 29 YDS INTERIOR AND EXTERIOR WALLS given to carl
|
INSP - Carpentry | 11/4/1997 | 11/3/1997 | 11/3/1997 | P | PART |
Carl Dependahl
|
|
|
MET W/ BRIAN PERRY, MTI SPEC INSP. & SUPT...NEED NEW 1HR LID DETAIL OR USE ORIGINAL, ICBO ES 1632.
|
INSP - Carpentry | 10/30/1997 | 10/30/1997 | 10/30/1997 | P | PASS |
Carl Dependahl
|
|
|
REVIEWING RESUBMITTAL FOR 1HR LID
|
INSP - Foundation | 10/30/1997 | 10/30/1997 | 10/30/1997 | P | CANC |
Wes Worcester
|
|
|
10/30/97 342 - GROUT REPORT FOR 10/30/97 16 YRDS INTERIOR AND EXTERIOR W
|
INSP - Framing/Rough-in | 10/31/1997 | 10/30/1997 | 10/30/1997 | P | FAIL |
Carl Dependahl
|
|
|
FRAMING OF 1HR LID AT UPPER CORRIDOR SEC. E & H NOT PER DETAIL SUBMITTED(UL P516) CN...MAY RETURN TO ORIG. PLAN BY ADDING TYPE G SCREWS 2-3" BACK FROM BUTT JOINTS PER ICBO ES # 1632. ALL SCREWS NOT TO BE INTO FURRING AT END JOINTS FOR THIS 2 LAYER ASS'Y.
|
INSP - Conference | 10/30/1997 | 10/29/1997 | 10/29/1997 | P | PASS |
Carl Dependahl
|
|
|
W/ GREG, ORMOND PROJ MGR...REC'D RESUBMITTAL FOR 1HR LID PER UL DESIGN P516(WHAT YEAR???)WILL ADVISE.
|
INSP - Miscellaneous | 10/30/1997 | 10/29/1997 | 10/29/1997 | A | PASS |
Wes Worcester
|
|
|
did 8 yards of interior and exterior
|
INSP - Foundation | 10/27/1997 | 10/28/1997 | 10/28/1997 | A | PART |
Wes Worcester
|
|
|
/ / 342 - poured w/spec insp on site as per super....now using wire po verticals and bond beam rebar was in place
|
INSP - Conference | 10/24/1997 | 10/24/1997 | 10/24/1997 | P | PASS |
Carl Dependahl
|
|
|
W/ ORMOND SUPT & PROJ MGR: CALLED ARCH RE 1HR LID DETAILS. MUST FOLLOW SPEC OR RESUBMIT.
|
INSP - Conference | 10/23/1997 | 10/23/1997 | 10/23/1997 | A | PASS |
Carl Dependahl
|
|
|
W/ JOE...RE FIRE ASSY. INSPS
|
INSP - Miscellaneous | 10/23/1997 | 10/23/1997 | 10/23/1997 | P | PART |
Carl Dependahl
|
|
|
GROUT REPORT 4.5 YDS INTERIOR AND EXTERIOR WALLS MTI ONSITE, REPORT PENDING
|
INSP - Wall cover | 10/23/1997 | 10/23/1997 | 10/23/1997 | P | PART |
Carl Dependahl
|
|
|
1st layer gyp at 1hr lid, E wing, 2nd fl. NEED TO FOLLOW SCHED. IN ICBO 1632 E FOR FACE LAYER.
|
INSP - Miscellaneous | 10/23/1997 | 10/22/1997 | 10/23/1997 | A | |
Alan Hauser
|
|
|
grout report 17 yards of interior and exterior
|
INSP - Carpentry | 10/22/1997 | 10/22/1997 | 10/22/1997 | P | PASS |
Carl Dependahl
|
|
|
W/ SUPT. & HOBSON. 2:30; CHK'D PLAN DETAIL, DAMPER LISTINGS & INSTALL INSTRUCTION...MET W/ BILL OF HOBSON FABRICATORS.
|
INSP - Foundation | 10/21/1997 | 10/22/1997 | 10/22/1997 | A | PART |
Carl Dependahl
|
|
|
GROUT REPORT FOR 10/21/97 12 YDS INTERIOR AND EXTERIOR WALLS MTI ONSITE, PENDING REPORT.
|
INSP - Carpentry | 10/21/1997 | 10/21/1997 | 10/21/1997 | P | PART |
Carl Dependahl
|
|
|
RE CLG FRAMING,DAMPERS; DISCUSSED PLANS W/ CHUCK TINDER, BUSD & MET W/ ORMOND AT SITE
|
INSP - Framing/Rough-in | 10/16/1997 | 10/20/1997 | 10/20/1997 | P | PART |
Carl Dependahl
|
|
|
sec E 2nd fl clg framing at corridor; need specs for ICBO es 1625 for 1hr lid...runners per plan; Need install specs for dampers ,chk w/ Hobson(hvac)
|
INSP - Miscellaneous | 10/20/1997 | 10/20/1997 | 10/20/1997 | P | PART |
Carl Dependahl
|
|
|
GROUT REPORT--FRI IS 16 YARDS EXTERIOR AND INTERIOR WALLS
|
INSP - Miscellaneous | 10/16/1997 | 10/17/1997 | 10/17/1997 | A | PART |
Carl Dependahl
|
|
|
PLACED 7 YARDS OF GROUT IN EXTERIOR AND INTERIOR WALLS
|
INSP - Conference | 10/17/1997 | 10/16/1997 | 10/16/1997 | P | PASS |
Carl Dependahl
|
|
|
W/ JOE, SUPT. FOR ORMOND...REQUESTED LISTING & INSTALL INSTRUCTION FOR SMOKE FIRE DAMPERS AT MASONRY WALLS...NEED DETAIL FROM HOBSON FAB. (MECH CONT.) HE WILL ARRANGE OR INFORM HOBSON.
|
INSP - Foundation | 10/15/1997 | 10/16/1997 | 10/16/1997 | A | CANC |
Alan Hauser
|
|
|
10/16/97 350 - REPORT FOR MIKELSON MASONARY FOR 10/15/97 7 YDS to be done by #340
|
INSP - Foundation | 10/15/1997 | 10/15/1997 | 10/15/1997 | P | PART |
Carl Dependahl
|
|
|
10-14 8 yrds interior and exterior walls
|
INSP - Footings | 10/13/1997 | 10/14/1997 | 10/14/1997 | A | PART |
Carl Dependahl
|
|
|
10-8 24 YARDS, 10-9 16 YDS, 10-10 8 YDS, 10-13 8 YDS, ALL INTERIOR AND EXTERIOR WALLS. GROUT REPORT FOR PETE MIKELSON MASONARY...MTI ONSITE,REPORT PENDING.
|
INSP - Foundation | 10/7/1997 | 10/8/1997 | 10/8/1997 | P | PART |
Carl Dependahl
|
|
|
10-6 24 YRDS INTERIOR AND EXTERIOR WALLS 10-7 24 YARDS INTERIOR AND EXTERIOR WALLS THIS IS GROUT REPORT FOR MIKELSON MASONRY
|
INSP - Foundation | 10/3/1997 | 10/1/1997 | 10/1/1997 | A | PASS |
Carl Dependahl
|
|
|
8 YARDS OF INTERIOR AND EXTERIOR WALLS\10-02-97 32 YARDS OF INTERIOR AND EXTERIOR WALLS THIS WAS CALLED IN AS A REPORT
|
INSP - Footings | 9/25/1997 | 9/25/1997 | 9/25/1997 | P | PART |
Carl Dependahl
|
|
|
09/25/97 340 - grouted on tuesday 15 yards wednesday 7 1/2 yards and thu
|
INSP - Carpentry | 9/24/1997 | 9/24/1997 | 9/24/1997 | P | PART |
Carl Dependahl
|
|
|
09/24/97 340 - WALKED SITE, SPOKE W/ BRIAN, MTI SPEC INSP.
|
INSP - Conference | 9/22/1997 | 9/23/1997 | 9/23/1997 | A | PART |
Carl Dependahl
|
|
|
09/23/97 340 - did 8 yards grout inside and out friday
|
INSP - Footings | 9/22/1997 | 9/23/1997 | 9/23/1997 | A | PART |
Carl Dependahl
|
|
|
09/23/97 340 - 12 YARDS OF GROUT EXTERIOR/INTERIOR. MTI ONSITE, REPORT P
|
INSP - Conference | 9/19/1997 | 9/19/1997 | 9/19/1997 | A | PASS |
Carl Dependahl
|
|
|
MET W/ NEW SPEC INSP(W/MTI)...PERRY BRIAN. DISCUSSED NONCONFORMING INSP REPORTS; MUST BE COMPILED AND ADDRESSED BY ENG.
|
INSP - Footings | 9/19/1997 | 9/19/1997 | 9/19/1997 | P | PART |
Carl Dependahl
|
|
|
09/19/97 340 - poured 14 yards 9/18/97 will call monday and let you know poured saturday. for interior and exterior. spec. inspector on job site.
|
INSP - Conference | 9/17/1997 | 9/17/1997 | 9/17/1997 | P | PASS |
Carl Dependahl
|
|
|
REQUESTED LISTING & INSTALL INSTRUCTION FOR DAMPERS AT 2 HR MASONRY WALL FROM JOE HANSEN, SUPT...TOLD HE NEEDS TO TELL HOBSON(MECH CONTRACTOR) TO GET INFO.
|
INSP - Footings | 9/17/1997 | 9/17/1997 | 9/17/1997 | P | PART |
Carl Dependahl
|
|
|
09/17/97 340 - POUR 15 YARDS OF GROUT INTER EXTER WALLS YESTERDAY AND TO
|
INSP - Footings | 9/15/1997 | 9/16/1997 | 9/16/1997 | A | PART |
Tom Arcoraci
|
|
|
15 yards exterior and interior SPECIAL INSPECTOR ONSITE
|
INSP - Carpentry | 9/12/1997 | 9/12/1997 | 9/12/1997 | P | PART |
Carl Dependahl
|
|
|
pouring/grout 12 yards interior and exterior today. spec. inspector on job. courtsey call. WALKED JOB W/ SCOTT. SUPT. NOT ONSITE, NEED SPRAY FIREPROOF SPEC'S & CHK W/ MTI.
|
INSP - Site Preparation | 9/11/1997 | 9/11/1997 | 9/11/1997 | P | PASS |
Carl Dependahl
|
|
|
20 YDS OF GROUT INTERIOR AND EXTERIOR WALLS
|
INSP - Carpentry | 9/9/1997 | 9/9/1997 | 9/9/1997 | P | PASS |
Carl Dependahl
|
|
|
09/09/97 340 -
|
INSP - Footings | 9/9/1997 | 9/9/1997 | 9/9/1997 | P | PART |
Carl Dependahl
|
|
|
09/09/97 340 - 24 yards exterior and interior
|
INSP - Conference | 9/5/1997 | 9/5/1997 | 9/5/1997 | A | PASS |
Wes Worcester
|
|
|
schedule precon at 1:30 -2pm w/fire, arch, 342 and 408
|
INSP - Conference | 9/5/1997 | 9/5/1997 | 9/5/1997 | P | PASS |
Carl Dependahl
|
|
|
09/05/97 340 - PRECON W/ SUPT, ETC. met wendall binghan, scotthansen, ar discussed insp's, eng's reports etc
|
INSP - Framing/Rough-in | 9/4/1997 | 9/5/1997 | 9/5/1997 | P | NR |
Carl Dependahl
|
|
|
09/05/97 340 - GROUTED INTERIOR/EXTERIOR 18 YARDS
|
INSP - Conference | 9/4/1997 | 9/4/1997 | 9/4/1997 | P | PASS |
Carl Dependahl
|
|
|
09/04/97 340 - W/JOE TAWNEY RE FIRE PROTECTION OF OPENINGS, DAMPERS, ETC
|
INSP - Foundation | 9/3/1997 | 9/4/1997 | 9/4/1997 | P | PART |
Carl Dependahl
|
|
|
09/04/97 340 - EXTERIOR AND INTERIOR WALLS
|
INSP-Sprinkler Rough-in/Hydro | 9/3/1997 | 9/4/1997 | 9/4/1997 | A | PART |
Joe Tawney
|
|
|
09/03/97 406 - NEED TO TALK TO BELL FULLER LOOKED AT FIRE SMOKE DAMPERS WITH MECH CONTRACTOR
|
INSP - Wall cover | 9/2/1997 | 9/3/1997 | 9/4/1997 | A | PART |
Carl Dependahl
|
|
|
09/03/97 340 - GROUTED, 12 YARDS 9/2/97 / WILL CALL 9/3/97/ AND LET YOU POURED TODAY. SPEC. INSPECTOR ON JOB SITE.
|
INSP - Masonry | 8/28/1997 | 8/29/1997 | 8/29/1997 | A | PART |
Wes Worcester
|
|
|
POURED GROUT
|
INSP - Conference | 8/28/1997 | 8/28/1997 | 8/28/1997 | A | PASS |
Wes Worcester
|
|
|
SEPT 5 AT 1:30 TO 2:00 ON SITE W/ARCHITECT AND CONTRACTOR
|
INSP - Conference | 8/28/1997 | 8/28/1997 | 8/28/1997 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - NW JR HIGH SCHOOL; W/ WES RE CONFERENCE SET FOR 9-5-97
|
INSP - Framing/Rough-in | 8/27/1997 | 8/28/1997 | 8/28/1997 | A | PART |
Wes Worcester
|
|
|
24yrs int. and ext. walls and gounding at 800 and will call in total yrage
|
INSP - Carpentry | 8/27/1997 | 8/27/1997 | 8/27/1997 | | PART |
Carl Dependahl
|
|
|
/ / 340 - WALKED W/ SUPT. THRU PARTITION FRAMING, STAIRS, FIRESTOPS
|
INSP - Masonry | 8/27/1997 | 8/27/1997 | 8/27/1997 | P | PART |
Carl Dependahl
|
|
|
08/27/97 340 - grouted 17 yards 10/26/97 6 to 12 yards today. spec. insp
|
INSP - Conference | 8/26/1997 | 8/26/1997 | 8/26/1997 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - w/ JOE, SUPT. FOR ORMOND RE PROCEDURE FOR INSPS
|
INSP - Framing/Rough-in | 8/26/1997 | 8/26/1997 | 8/26/1997 | P | NR |
Carl Dependahl
|
|
|
08/26/97 340 - sheet rocking metal studs. ###-#### joe hansen, please call him as he wasn't sure if you wanted to out on this inspection, he can explain the situation to you ok???
|
INSP - Masonry | 8/26/1997 | 8/26/1997 | 8/26/1997 | P | PART |
Carl Dependahl
|
|
|
08/26/97 340 - grouted 12 yards 8/25/ doing at least 5 yards today, spec site.
|
INSP - Conference | 8/22/1997 | 8/22/1997 | 8/22/1997 | P | PASS |
Carl Dependahl
|
|
|
08/22/97 340 - W/ WES RE HIS INSP & SPEC INSP OF MASONRY
|
INSP - Masonry | 8/21/1997 | 8/22/1997 | 8/22/1997 | A | CANC |
Wes Worcester
|
|
|
08/22/97 342 - DID 24 YARD 8/20/97 AND 30 YARDS OF GROUTING 8/21/97/SPEC given to Tom A
|
INSP - Masonry | 8/21/1997 | 8/21/1997 | 8/21/1997 | | PART |
Carl Dependahl
|
|
|
08/21/97 340 - poured; SPEC INSP ONSITE,PENDING REPORT
|
INSP - Masonry | 8/21/1997 | 8/21/1997 | 8/21/1997 | | PART |
Carl Dependahl
|
|
|
08/21/97 340 - poured; SPEC INSP ONSITE,PENDING REPORT
|
INSP - Masonry | 8/18/1997 | 8/19/1997 | 8/19/1997 | A | PART |
Carl Dependahl
|
|
|
GROUTING 6 YARDS 8:30 A.M. MIGHT DO ANOTHER TRUCK BUT WILL CALL SPEC. INSPECTOR ON SITE.
|
INSP - Masonry | 8/19/1997 | 8/19/1997 | 8/19/1997 | | PART |
Carl Dependahl
|
|
|
08/19/97 340 - GROUTING 6 YARDS 8:30 A.M. MIGHT DO ANOTHER TRUCK BUT WI INSPECTOR ON SITE.
|
INSP - Masonry | 8/18/1997 | 8/18/1997 | 8/18/1997 | P | PART |
Carl Dependahl
|
|
|
said he was grouting interior and exterior at 8:30 a.m. starting with 5 yards, courtsey call, special inspector on site.
|
INSP - Masonry | 8/18/1997 | 8/18/1997 | 8/18/1997 | | PART |
Carl Dependahl
|
|
|
/ / 340 - said he was grouting interior and exterior aQUESTED PLAN & C
|
INSP - Foundation | 8/7/1997 | 8/15/1997 | 8/15/1997 | A | PART |
Wes Worcester
|
|
|
08/15/97 342 - POURING AT 6:30 A.M 2ND FLOOR SLAB special inspector on s
|
INSP - Foundation | 8/7/1997 | 8/14/1997 | 8/14/1997 | A | PART |
Wes Worcester
|
|
|
08/14/97 342 - POURING 2ND FLOOR SLAB. 2ND FLOOR....poured w/speciaL INS
|
INSP - Masonry | 8/13/1997 | 8/14/1997 | 8/14/1997 | A | FAIL |
Wes Worcester
|
|
|
08/14/97 342 - 8:30 in the morning 12 yds of grout and he poured 18 toda place, no clips or web placement in place 1st lift next to locker room
|
INSP - Foundation | 8/7/1997 | 8/13/1997 | 8/13/1997 | A | PART |
Wes Worcester
|
|
|
08/13/97 342 - POURING AT 6:30 2ND FLOOR SLAB ...SPECIAL INSP ON SITE
|
INSP - Foundation | 8/13/1997 | 8/13/1997 | 8/13/1997 | | PART |
Wes Worcester
|
|
|
/ / 342 - SPEC INSP ON SITE
|
INSP - Masonry | 8/12/1997 | 8/13/1997 | 8/13/1997 | A | FAIL |
Wes Worcester
|
|
|
08/13/97 342 - 17 yards of grout poured 8-12-97 and more at 9am on 8-13. BAR 16" OC AND VERBALLY AGREED WITH BY ENG...NEED STAMPED DETAIL SIGNED
|
INSP - Foundation | 8/12/1997 | 8/12/1997 | 8/13/1997 | P | CANC |
Carl Dependahl
|
|
|
poured grout 24 yards 8/12/97 /pouring 11 today, these are interior and exterior walls, spec. inspector on site..given to 342
|
INSP - Conference | 8/11/1997 | 8/11/1997 | 8/11/1997 | | FAIL |
Wes Worcester
|
|
|
/ / 342 - special inspection log not current, left note to update and special inspector log.
|
INSP - Foundation | 8/7/1997 | 8/11/1997 | 8/11/1997 | A | PART |
Wes Worcester
|
|
|
08/11/97 342 - GOING TO POUR FLOOR SLAB THE REST ON GRADE AT 7:30 A.M.
|
INSP - Foundation | 8/11/1997 | 8/11/1997 | 8/11/1997 | P | PART |
Tom Arcoraci
|
|
|
POURED AT 9 A.M. INTERIOR AND EXTERIOR, 18 YARDS. DID 6 YARDS FRIDAY, SPEC INSPECTOR ON SITE. COURTSEY CALL
|
INSP - Wall cover | 8/6/1997 | 8/6/1997 | 8/6/1997 | P | PART |
Carl Dependahl
|
|
|
grouting walls wall 8 a.m. this morning. grouted 22 yds tuesday. spec. inspector on job. MET W/ INSPECTOR ONSITE
|
INSP - Wall cover | 8/5/1997 | 8/5/1997 | 8/5/1997 | P | PART |
Carl Dependahl
|
|
|
08/05/97 340 - message, going to pour(grouting) this a.m. at 10 a.m. yes 23 yards. courtsey call.
|
INSP - Foundation | 7/31/1997 | 7/31/1997 | 8/1/1997 | P | PART |
Carl Dependahl
|
|
|
07/31/97 340 - POURING GROUT 5-MAYBER 6 MORE 9:30 A.M. HAS A ON SITE INS CALL
|
INSP - Masonry | 7/30/1997 | 7/30/1997 | 7/30/1997 | P | PART |
Carl Dependahl
|
|
|
07/30/97 340 - Poured grout 11 yards yesterday and is pouring 5 more yar interior and exterior wall. PEND SPEC INSP REPORTS
|
INSP - Masonry | 7/28/1997 | 7/28/1997 | 7/28/1997 | P | PART |
Carl Dependahl
|
|
|
07/28/97 340 - 12 YARDS TODAY
|
INSP - Masonry | 7/25/1997 | 7/25/1997 | 7/25/1997 | P | PART |
Carl Dependahl
|
|
|
SPEC INSP ONSITE
|
INSP - Masonry | 7/24/1997 | 7/24/1997 | 7/24/1997 | P | PART |
Carl Dependahl
|
|
|
POURING GROUT 9:30 A.M. 6 TO 18 YARDS. SPEC. INSPECTOR ON SITE. ALSO HE SAID HE POURED 24 YARDS 7/23/97 TRIED TO CALL BUT COULDN'T GET THRU TO US. SPEC. INSPECTOR ON SITE.
|
INSP - Masonry | 7/22/1997 | 7/22/1997 | 7/22/1997 | P | PART |
Carl Dependahl
|
|
|
masonry grout interior walls, pouring about 12 yards today/ special inspector on site.
|
INSP - Masonry | 7/21/1997 | 7/21/1997 | 7/21/1997 | P | PART |
Carl Dependahl
|
|
|
special inspector on job site.
|
INSP - Footings | 7/14/1997 | 7/18/1997 | 7/18/1997 | A | PART |
Tom Arcoraci
|
|
|
INSIDE FOOTINGS spec inspec on site report pending
|
INSP - Masonry | 7/14/1997 | 7/18/1997 | 7/18/1997 | A | PART |
Tom Arcoraci
|
|
|
INSIDE spec inspec on site report pending
|
INSP - Masonry | 7/14/1997 | 7/17/1997 | 7/17/1997 | A | PART |
Tom Arcoraci
|
|
|
INSIDE spec inspec on site
|
INSP - Footings | 7/14/1997 | 7/16/1997 | 7/16/1997 | A | PART |
Tom Arcoraci
|
|
|
INSIDE FOOTINGS spec inspec on site
|
INSP - Masonry | 7/16/1997 | 7/16/1997 | 7/16/1997 | A | PART |
Carl Dependahl
|
|
|
GROUTING AT 9 A.M. 6 YARDS PROBABLY DO 16 YARDS INTERIOR WALLS. SPECIAL INSPECTOR ON JOB SITE FROM MPI.
|
INSP - Wall cover | 7/15/1997 | 7/16/1997 | 7/16/1997 | A | PART |
Tom Arcoraci
|
|
|
COURTSEY CALL 6 YARDS GOING TO 12 TO 18 YARD. STARTING AT 9 O'CLOCK spec inspec on site
|
INSP - Footings | 7/14/1997 | 7/15/1997 | 7/15/1997 | P | PART |
Carl Dependahl
|
|
|
INSIDE FOOTINGS, pend spec insp
|
INSP - Masonry | 7/14/1997 | 7/15/1997 | 7/15/1997 | A | part |
Tom Arcoraci
|
|
|
07/15/97 408 - 8:30 START GROUT
|
INSP - Masonry | 7/14/1997 | 7/14/1997 | 7/14/1997 | P | PART |
Carl Dependahl
|
|
|
2:00 pend spec insp
|
INSP - Footings | 7/7/1997 | 7/11/1997 | 7/11/1997 | P | PART |
Wes Worcester
|
|
|
special inspector on site earlier, no one on site in PM
|
INSP - Wall cover | 7/11/1997 | 7/11/1997 | 7/11/1997 | P | PART |
Wes Worcester
|
|
|
pouring 7 yards of grout at 9 o'clock. has a special inspector on job site... no one on site in PM
|
INSP - Footings | 7/7/1997 | 7/10/1997 | 7/10/1997 | P | PART |
Carl Dependahl
|
|
|
07/10/97 340 - PENDING SPEC INSP REPORT
|
INSP - Masonry | 7/9/1997 | 7/10/1997 | 7/10/1997 | A | PART |
Tom Arcoraci
|
|
|
07/10/97 408 - spec on site pend rpt
|
INSP - Footings | 7/7/1997 | 7/9/1997 | 7/9/1997 | P | PART |
Carl Dependahl
|
|
|
07/09/97 340 - PENDING SPEC INSP, CONTACTED CHRIS OF MTI
|
INSP - Masonry | 7/8/1997 | 7/9/1997 | 7/9/1997 | A | PART |
Carl Dependahl
|
|
|
07/09/97 340 - pouring grout on the morning pending spec insp
|
INSP - Masonry | 7/7/1997 | 7/8/1997 | 7/8/1997 | A | PART |
Wes Worcester
|
|
|
pouring grout at 8am special inspector on site
|
INSP - Masonry | 7/3/1997 | 7/3/1997 | 7/7/1997 | P | PART |
Carl Dependahl
|
|
|
07/07/97 340 - pouring 5 yards of grout, PEND SPEC INSP REPORT
|
INSP - Masonry | 7/2/1997 | 7/2/1997 | 7/2/1997 | P | PART |
Carl Dependahl
|
|
|
07/02/97 340 - POURING 6 YEARS 11 O'CLOCK TODAY
|
INSP - Foundation | 7/1/1997 | 7/1/1997 | 7/1/1997 | P | PART |
Carl Dependahl
|
|
|
07/01/97 340 - Pouring grout at 1:30 7 yards
|
INSP - Masonry | 6/30/1997 | 6/30/1997 | 6/30/1997 | A | PART |
Carl Dependahl
|
|
|
06/30/97 340 - pouring grout at 10:30; part, pending spec insp report
|
INSP - Footings | 6/24/1997 | 6/25/1997 | 6/25/1997 | A | PART |
Tom Arcoraci
|
|
|
POURING FOOTINGS AND SLABS AT 6:30 A.M. THIS WIL GO ON WEDNESDAY, THURSDAY & FRIDAY. SPECIAL INSPECTOR ON JOB.
|
INSP - Masonry | 6/25/1997 | 6/25/1997 | 6/25/1997 | P | PART |
Carl Dependahl
|
|
|
06/25/97 340 - GROUT - POURING 6 YARDS INTERIOR WALLS.
|
INSP - Footings | 6/23/1997 | 6/24/1997 | 6/24/1997 | P | PART |
Carl Dependahl
|
|
|
06/24/97 340 - pend spec insp
|
INSP - Masonry | 6/24/1997 | 6/24/1997 | 6/24/1997 | P | PART |
Carl Dependahl
|
|
|
06/24/97 340 - FYI:MASONRY GROUT & INTERIOR WALL - POURING AT 10:30 A.M. TODAY. SPECIAL INSPECTOR ON JOB.
|
INSP - Conference | 6/23/1997 | 6/23/1997 | 6/23/1997 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - TOLD CONT TO TRY TO HOLD DUST DOWN AS WEV'E HAD COMPLAINT; S
|
INSP - Masonry | 6/23/1997 | 6/23/1997 | 6/23/1997 | P | PART |
Carl Dependahl
|
|
|
06/23/97 340 - GROUT - 6 YARDS AT 10 A.M. ......PEND SPEC INSP
|
INSP - Footings | 6/17/1997 | 6/19/1997 | 6/19/1997 | A | PART |
Tom Arcoraci
|
|
|
|
INSP - Foundation | 6/17/1997 | 6/19/1997 | 6/19/1997 | A | PART |
Tom Arcoraci
|
|
|
FND. WALL
|
INSP - Masonry | 6/18/1997 | 6/19/1997 | 6/19/1997 | A | PART |
Tom Arcoraci
|
|
|
GROUT 6 YARDS POURING AROUND 10 A.M.
|
INSP - Masonry | 6/16/1997 | 6/17/1997 | 6/17/1997 | A | PART |
Tom Arcoraci
|
|
|
GROUTING AROUND 9 A.M....PENDING SPEC INSP RPT
|
INSP - Footings | 6/10/1997 | 6/13/1997 | 6/13/1997 | A | CANC |
Alan Hauser
|
|
|
06/13/97 350 - POURING 10:30 to be done by #340 ì
|
INSP - Footings | 6/10/1997 | 6/13/1997 | 6/13/1997 | P | PART |
|
|
|
06/13/97 333 - FTG -OK FOOTING
|
INSP - Masonry | 6/12/1997 | 6/13/1997 | 6/13/1997 | A | CANC |
Alan Hauser
|
|
|
06/13/97 350 - POURING AT 8 A.M. GROUT to be done by #340
|
INSP - Footings | 6/10/1997 | 6/12/1997 | 6/12/1997 | P | PART |
Carl Dependahl
|
|
|
/ / 340 - INTERIOR FOOTINGS AND FLOOR SLAB
|
INSP - Footings | 6/10/1997 | 6/12/1997 | 6/12/1997 | P | CANC |
Alan Hauser
|
|
|
06/12/97 350 - POUR AT 10:30 to be done by #340
|
INSP - Foundation | 6/11/1997 | 6/12/1997 | 6/12/1997 | P | PART |
Carl Dependahl
|
|
|
06/12/97 340 - grout...PENDING SPEC INSP REPORT
|
INSP - Footings | 6/10/1997 | 6/11/1997 | 6/11/1997 | A | PART |
Carl Dependahl
|
|
|
06/11/97 340 - 5 YARDS 9 A.M...pend s.i.
|
INSP - Footings | 6/10/1997 | 6/11/1997 | 6/11/1997 | P | PART |
Carl Dependahl
|
|
|
06/11/97 340 - POURING AT 1 O'CLOCK...pending spec insp.
|
INSP - Masonry | 6/9/1997 | 6/10/1997 | 6/10/1997 | P | PART |
Carl Dependahl
|
|
|
06/10/97 340 - GROUT POURING AT 8:30 A.M...pending spec insp report
|
INSP - Footings | 6/4/1997 | 6/6/1997 | 6/6/1997 | P | PART |
Carl Dependahl
|
|
|
06/06/97 340 - pending spec insp report
|
INSP - Footings | 6/4/1997 | 6/6/1997 | 6/5/1997 | A | CANC |
|
|
|
06/06/97 333 - given to Carl
|
INSP - Masonry | 6/5/1997 | 6/6/1997 | 6/5/1997 | A | CANC |
|
|
|
06/06/97 333 - given to Carl
|
INSP - Footings | 6/4/1997 | 6/5/1997 | 6/5/1997 | P | PART |
Carl Dependahl
|
|
|
06/05/97 340 - PENDING SPEC INSP REPORT
|
INSP - Footings | 6/4/1997 | 6/5/1997 | 6/5/1997 | P | PART |
Carl Dependahl
|
|
|
06/05/97 340 - NW JR HIGH, TRAN FROM 333 BY 340, PENDING SPEC INSP REPOR
|
INSP - Foundation | 6/4/1997 | 6/5/1997 | 6/5/1997 | A | PART |
Carl Dependahl
|
|
|
/ / 340 - FLOOR SLAB, NW JR HIGH; TRAN FROM 333 BY 340
|
INSP - Masonry | 6/2/1997 | 6/3/1997 | 6/3/1997 | P | PART |
Carl Dependahl
|
|
|
06/03/97 340 - grout - 9:30 am. they were scheduled to pour floor slab part, pending spec insp report
|
INSP - Footings | 6/2/1997 | 6/2/1997 | 6/2/1997 | P | PART |
Carl Dependahl
|
|
|
06/02/97 340 - interior footing ... PEND SPEC INSP REPORT
|
INSP - Foundation | 6/2/1997 | 6/2/1997 | 6/2/1997 | P | PART |
Carl Dependahl
|
|
|
06/02/97 340 - PEND SPEC INSP REPORT
|
INSP - Conference | 5/30/1997 | 5/30/1997 | 5/30/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - told and left notice that Carl D. is going to be doing the i would like to set up a meeting.
|
INSP - Masonry | 5/29/1997 | 5/30/1997 | 5/30/1997 | A | PART |
Alan Hauser
|
|
|
05/30/97 350 - THEY ARE GROUTING THE MASONRY..WANTED TO LET YOU KNOW went by told and left notice that carl d. is going to be doing the inspe and he would like to set up a meeting
|
INSP-Conference | 5/8/1997 | 5/8/1997 | 5/8/1997 | P | PART |
|
|
|
relocation of fdc and piv to side of building, advised to hydro test before covering, want hydraulic calcs on additional restriction due to long line length
|
INSP - Footings | 4/28/1997 | 4/28/1997 | 4/28/1997 | P | PASS |
Alan Hauser
|
|
|
04/28/97 350 - left notice that they don't need to call inspections for inspections, send copies of m.t.i. reports to city
|
INSP - Footings | 4/24/1997 | 4/25/1997 | 4/25/1997 | P | PASS |
Alan Hauser
|
|
|
04/25/97 350 - AFTER 1:30 rebar and ftns ok, front corner
|
INSP - Footings | 4/22/1997 | 4/23/1997 | 4/22/1997 | P | CANC |
|
|
|
04/23/97 333 - canceled by Dixi
|
INSP - Framing/Rough-in | 3/16/1998 | 3/16/1998 | 3/16/1997 | P | PART |
Carl Dependahl
|
|
|
4:00 w/ ormond & comm'l const re shafts, reinsp shower area lid SHAFTS OK IF ORIGINAL DETAIL FOLLOWED TO "REMOVE" (COVER) ALL MAJOR STRUCT. ELEMENTS...JOISTS, BEAMS, ETC. OK TO FIRE CAULK NON-CRITICAL ELEMENTS...ALL-THREAD, BRACES, ETC. OK TO COVER SHOWER COMPARTMENT AT MENS LOCKER ROOM
|