Permanent Occupancy | | 4/3/1997 | 4/3/1997 | | DONE |
|
|
|
|
INSP - Final | 4/2/1997 | 4/2/1997 | 4/2/1997 | | PASS |
|
|
|
Final
|
INSP - Final | 3/10/1997 | 3/11/1997 | 3/11/1997 | A | PASS |
Joe Tawney
|
|
|
03/11/97 406 - HE WANTED A FINAL ON FIRE CODE & ANSUL SYSTEM. JULIO - 37 FINAL OK FOR PERM OCC
|
INSP - Final | 3/11/1997 | 3/11/1997 | 3/11/1997 | | PART |
|
|
|
316 - Temp. only - pending bonding for landscaping
|
INSP - Carpentry | 3/7/1997 | 3/7/1997 | 3/7/1997 | | PASS |
Jim Sly
|
|
|
/ / 316 - Inspection of (2) 1hr shafts for hoods. OK
|
INSP - Ceiling grid | 3/6/1997 | 3/7/1997 | 3/7/1997 | P | PASS |
Jim Sly
|
|
|
03/07/97 16 - OK
|
INSP-Conference | 3/5/1997 | 3/5/1997 | 3/5/1997 | | PASS |
|
|
|
PRE FINAL CONF
|
INSP - Ceiling grid | 2/26/1997 | 2/27/1997 | 2/27/1997 | A | NR |
|
|
|
02/27/97 338 - not ready to inspect c/n issued for ceiling grid only
|
INSP - Carpentry | 2/12/1997 | 2/13/1997 | 2/13/1997 | P | PASS |
Jim Sly
|
|
|
02/13/97 316 - 1 HR. SHAFT
|
INSP - Framing/Rough-in | 2/10/1997 | 2/10/1997 | 2/10/1997 | P | PART |
Jim Sly
|
|
|
02/10/97 316 - Inspection of boxed out framed area in play room....OK
|
INSP - Framing/Rough-in | 2/5/1997 | 2/6/1997 | 2/6/1997 | A | PART |
Jim Sly
|
|
|
02/05/97 316 - C/N...Misc Carpentry
|
INSP - Framing/Rough-in | 2/3/1997 | 2/4/1997 | 2/4/1997 | A | PART |
Jim Sly
|
|
|
02/03/97 316 - Inspection of roof deck over play area...OK.
|
INSP - Carpentry | 1/29/1997 | 1/29/1997 | 1/29/1997 | | PART |
Jim Sly
|
|
|
/ / 316 - Ext gyp attachment...gyp shear.
|
INSP - Framing/Rough-in | 1/29/1997 | 1/29/1997 | 1/29/1997 | P | CANC |
Jim Sly
|
|
|
01/29/97 316 - Cancel....will do AM
|
INSP - Roof | 1/27/1997 | 1/28/1997 | 1/28/1997 | A | PASS |
Jim Sly
|
|
|
01/27/97 316 - ROOF SHEATHING OK
|
INSP - Roof | 1/27/1997 | 1/27/1997 | 1/27/1997 | | NR |
|
|
|
316 - Roof sheathing nailing...NR
|
INSP - Foundation | 1/8/1997 | 1/9/1997 | 1/9/1997 | | PART |
|
|
|
01/09/97 316 - North foundation OK pending special inspection approval.
|
INSP - Foundation | 1/8/1997 | 1/8/1997 | 1/8/1997 | | PART |
|
|
|
01/08/97 316 - fnd. wall North end OK pending special inspection approval.
|
INSP - Footings | 1/7/1997 | 1/7/1997 | 1/7/1997 | P | PART |
Jim Sly
|
|
|
01/07/97 316 - conc.scheduled for 2 p.m. OK Pending special inspection
|
INSP - Footings | 1/6/1997 | 1/6/1997 | 1/6/1997 | P | PART |
Jim Sly
|
|
|
01/06/97 316 - REBAR Found. S. W. area...OK pending special inspection
|
INSP-Conference | 1/6/1997 | 1/6/1997 | 1/6/1997 | | PASS |
Joe Tawney
|
|
|
/ / 406 - SPOKE WITH JULIO BERRELEZ OF K2 CONST ABOUT HYD REQ PRIOR TO COMB MATERIAL ON SITE HE WILL CONTACT WATER DEPT AND CALL ME WITH INST SCHED
|
INSP - Footings | 1/2/1997 | 1/3/1997 | 1/3/1997 | | PART |
|
|
|
01/03/97 316 - OK pending special inspection.
|
INSP - Foundation | 1/2/1997 | 1/3/1997 | 1/3/1997 | | PART |
|
|
|
01/03/97 316 - OK pending special inspection approval.
|
INSP - Footings | 12/30/1996 | 12/31/1996 | 12/31/1996 | | PART |
|
|
|
12/31/96 316 - South, West (square) and part of East footing OK pending OK.
|