INSP - Final | 7/3/1997 | 7/3/1997 | 7/3/1997 | A | PASS |
Bob Archibald
|
|
|
|
INSP - Letter of compliance | 7/3/1997 | 7/3/1997 | 7/3/1997 | A | PASS |
Bob Archibald
|
|
|
letter 13890
|
INSP - Final | 7/1/1997 | 7/1/1997 | 7/1/1997 | P | PART |
Jim Storey
|
|
|
07/01/97 301 - Sent bid to contractor to cut weeds. reinspection ok pending mech insp.
|
INSP - Final | 6/30/1997 | 6/30/1997 | 6/30/1997 | P | NR |
Jim Storey
|
|
|
06/30/97 301 - OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Energy code compliance | 5/21/1997 | 5/22/1997 | 5/22/1997 | A | PART |
Jim Storey
|
|
|
05/22/97 301 - UNIT ABOVE AND GARAGE FRAM-OK FRAMING OTH-OTHER AGENCIES NOT APPROVEDELE
|
INSP - Footings | 4/23/1997 | 4/23/1997 | 4/23/1997 | P | PASS |
Jim Storey
|
|
|
04/23/97 301 - FTG -OK FOOTING
|
INSP - Energy code compliance | 4/3/1997 | 4/3/1997 | 4/3/1997 | P | PASS |
Jim Storey
|
|
|
insulation ok bearing at stair per tji engineering .25 short
|
INSP - Framing/Rough-in | 4/1/1997 | 4/2/1997 | 4/2/1997 | P | PASS |
Jim Storey
|
|
|
framing ok
|
INSP - Footings | 2/7/1997 | 2/7/1997 | 2/7/1997 | | PASS |
Jim Storey
|
|
|
02/07/97 301 - FDN -OK FOUNDATION
|