INSP - Final | 8/10/1998 | 8/11/1998 | 8/11/1998 | A | PASS |
Wes Worcester
|
|
|
08/11/98 342 - 9AM DOUG ###-####
|
INSP - Energy code compliance | 2/11/1998 | 2/12/1998 | 2/12/1998 | P | PASS |
Wes Worcester
|
|
|
02/12/98 342 - DOUG ###-#### ì
|
INSP - Framing/Rough-in | 2/6/1998 | 2/6/1998 | 2/6/1998 | P | NR |
Wes Worcester
|
|
|
02/06/98 342 - DOUG--###-####
|
INSP - Framing/Rough-in | 2/3/1998 | 2/4/1998 | 2/4/1998 | A | FAIL |
Wes Worcester
|
|
|
02/04/98 342 - doug ###-#### ì
|
INSP - Conference | 10/31/1997 | 10/31/1997 | 10/31/1997 | | PASS |
Wes Worcester
|
|
|
/ / 342 - discussed placement of bar as they tried to finish
|
INSP - Footings | 10/31/1997 | 10/31/1997 | 10/31/1997 | | PASS |
Wes Worcester
|
|
|
/ / 342 - dug out hole
|
INSP - Footings | 10/31/1997 | 10/31/1997 | 10/31/1997 | | PASS |
Wes Worcester
|
|
|
/ / 342 - 2nd trip
|
INSP - Footings | 10/30/1997 | 10/31/1997 | 10/31/1997 | A | FAIL |
Wes Worcester
|
|
|
10/31/97 342 - insufficient cover in one ftg
|
INSP - Wall cover | 10/31/1997 | 10/31/1997 | 10/31/1997 | P | NR |
Wes Worcester
|
|
|
10/31/97 342 - POURING AROUND 2:OO/ PIER WALLS,
|
INSP - Footings | 10/29/1997 | 10/30/1997 | 10/30/1997 | A | NR |
Wes Worcester
|
|
|
10/29/97 342 - no rebar on site
|
INSP - Foundation | 10/22/1997 | 10/22/1997 | 10/22/1997 | | PASS |
Wes Worcester
|
|
|
/ / 342 -
|
INSP - Wall cover | 10/21/1997 | 10/21/1997 | 10/22/1997 | P | PASS |
Wes Worcester
|
|
|
10/21/97 342 - AROUND 1:30 PLEASE
|
INSP - Wall cover | 10/20/1997 | 10/20/1997 | 10/20/1997 | P | CANC |
Wes Worcester
|
|
|
RESCHEDULED FOR TUES AM
|
INSP - Conference | 10/17/1997 | 10/17/1997 | 10/17/1997 | | PASS |
Wes Worcester
|
|
|
/ / 342 - met w/Shawn and Doug on site....epoxy sets as per engineers
|
INSP - Footings | 10/17/1997 | 10/17/1997 | 10/17/1997 | | PASS |
Wes Worcester
|
|
|
/ / 342 -
|
INSP - Footings | 10/17/1997 | 10/17/1997 | 10/17/1997 | P | PART |
Wes Worcester
|
|
|
10/17/97 342 -
|
INSP - Footings | 10/16/1997 | 10/16/1997 | 10/16/1997 | P | NR |
Wes Worcester
|
|
|
10/16/97 342 - LETTER FROM ENGINEER IS SUPPOSED TO BE FAXED TODAY
|
INSP - Footings | 10/15/1997 | 10/15/1997 | 10/15/1997 | A | FAIL |
Wes Worcester
|
|
|
poured w/o inspection, need engineering and stamped details and stamped approval per engineered ftg/fdn req'd
|
INSP - Footings | 10/6/1997 | 10/7/1997 | 10/7/1997 | A | PART |
Wes Worcester
|
|
|
thickened ftgs ok
|