INSP - Conference | 10/3/1997 | 10/3/1997 | 10/3/1997 | A | PART |
Wes Worcester
|
|
|
left msg w/Kevin requesting report from Heidi re: slab pour already completed
|
INSP - Site Preparation | 10/3/1997 | 10/3/1997 | 10/3/1997 | A | PART |
Wes Worcester
|
|
|
ADDED BY 342 AS NO ONE AVAILABLE 10/02... poured w/special insp on site....report requested
|
INSP - Site Preparation | 10/1/1997 | 10/2/1997 | 10/2/1997 | P | NH |
Wes Worcester
|
|
|
SLAB--POURING FRI AM....EMPLOYEE IN TRAILER DID NOT KNOW @ POUR, DROVE AROUND PROJECT AND COULD NOT FIND ANYONE @ ANY SLAB @ SITE
|
INSP - Wall cover | 9/8/1997 | 9/9/1997 | 9/9/1997 | A | PART |
Carl Dependahl
|
|
|
09/09/97 340 - THEY ARE POURING AT 1:00 ...MTI, ENG. ONSITE.
|
INSP - Foundation | 9/2/1997 | 9/3/1997 | 9/3/1997 | P | PART |
Carl Dependahl
|
|
|
09/03/97 340 - EARLY P.M. IF POSSIBLE; MET W/ KEVIN ENGSTROM, P WKS. NEW CLOSURE FND FOR AERATION PIT AT N. SIDE. MTI ONSITE
|
INSP - Conference | 8/26/1997 | 8/26/1997 | 8/26/1997 | A | PASS |
Bob Archibald
|
|
|
Conference w/contractor regarding letter to Hogland regarding Wes.
|
INSP - Conference | 8/7/1997 | 8/7/1997 | 8/7/1997 | P | |
Carl Dependahl
|
|
|
IN BACK
|
INSP - Footings | 8/5/1997 | 8/6/1997 | 8/6/1997 | A | PART |
Carl Dependahl
|
|
|
REBAR
|
INSP - Masonry | 7/30/1997 | 7/30/1997 | 7/30/1997 | P | NR |
Carl Dependahl
|
|
|
07/30/97 340 - puoring concrete this afternoon...NR, GAVE TO TOM A. FOR
|
INSP - Footings | 7/22/1997 | 7/24/1997 | 7/24/1997 | P | PART |
Carl Dependahl
|
|
|
PREFER EARLY PM...SPEC INSP ONSITE. THIS IS 342'S JOB.
|
INSP - Footings | 7/17/1997 | 7/17/1997 | 7/18/1997 | P | NR |
Carl Dependahl
|
|
|
07/17/97 340 - re-bar; UNABLE TO CONTACT
|
INSP - Footings | 7/15/1997 | 7/16/1997 | 7/16/1997 | A | FAIL |
Wes Worcester
|
|
|
inadequate cover, wrong splice, not to plan, unsafe ladder & could not access cat walk for wall pour
|
INSP - Footings | 7/11/1997 | 7/11/1997 | 7/11/1997 | P | CANC |
Jim Sly
|
|
|
07/11/97 316 - Gave to Wes W.
|
INSP - Footings | 7/11/1997 | 7/11/1997 | 7/11/1997 | P | NR |
Wes Worcester
|
|
|
poured w/Gary on site.. still waiting for letter of spec insp authorization.. still bolting together forms.. super wanted me to visually inspect wall pour.. asked him to schedule conf... We were not the problem for late pours!!
|
INSP - Foundation | 7/11/1997 | 7/11/1997 | 7/11/1997 | P | PART |
Wes Worcester
|
|
|
2nd interior wall pour ok.. noted unsafe attachment of ladder to access top of forms.. will call safety 7/14
|
INSP - Conference | 7/10/1997 | 7/10/1997 | 7/10/1997 | P | CANC |
Carl Dependahl
|
|
|
07/10/97 340 - WES AND KIM WENT
|
INSP - Conference | 7/10/1997 | 7/10/1997 | 7/10/1997 | P | PART |
Wes Worcester
|
|
|
3:00 met w/Gary, Bob, and Heidi, w/Kim on site
|
INSP - Foundation | 7/10/1997 | 7/10/1997 | 7/10/1997 | P | FAIL |
Wes Worcester
|
|
|
inadequate cover, incorrect placement of rebar, do not cover 2nd wall....
|
INSP - Site Preparation | 7/10/1997 | 7/10/1997 | 7/10/1997 | A | PART |
Wes Worcester
|
|
|
ck on spec insp and rebar placement on fill, scheduled conf. w/eng plus public works and bldg dept
|
INSP - Conference | 7/10/1997 | 7/9/1997 | 7/10/1997 | A | PART |
Wes Worcester
|
|
|
called Trammel and they are in process of performing punch lists
|
INSP - Conference | 7/10/1997 | 7/9/1997 | 7/10/1997 | A | PART |
Wes Worcester
|
|
|
called turnkey and noted spec insp requirements
|
INSP - Conference | 7/10/1997 | 7/9/1997 | 7/10/1997 | A | PART |
Wes Worcester
|
|
|
called Gary Lund @ spec insp and need to get handled prior to pour
|
INSP - Conference | 7/9/1997 | 7/9/1997 | 7/9/1997 | P | PART |
Wes Worcester
|
|
|
left note to call on front door
|
INSP - Footings | 7/9/1997 | 7/9/1997 | 7/9/1997 | P | NR |
Wes Worcester
|
|
|
no one on site at 4:15 pm
|
INSP - Footings | 7/9/1997 | 7/9/1997 | 7/9/1997 | P | NR |
Carl Dependahl
|
|
|
07/09/97 340 - CANT FIND WORK SITE OR CONTRACTOR
|
INSP - Conference | 7/7/1997 | 7/7/1997 | 7/7/1997 | A | PART |
Wes Worcester
|
|
|
talked w/George and will meet w/Tim later
|
INSP - Site Preparation | 7/3/1997 | 7/3/1997 | 7/3/1997 | P | NR |
Wes Worcester
|
|
|
schedule conf w/all concerned
|
INSP - Conference | 6/27/1997 | 6/27/1997 | 6/30/1997 | A | PART |
Wes Worcester
|
|
|
discussed spec insp criteria w/admin
|
INSP - Conference | 6/27/1997 | 6/27/1997 | 6/27/1997 | A | FAIL |
Wes Worcester
|
|
|
could not get a hold of Gary or Trammels
|
INSP - Conference | 6/27/1997 | 6/27/1997 | 6/27/1997 | A | FAIL |
Wes Worcester
|
|
|
need special inspector qualification letter and authorization.
|
INSP - Conference | 6/27/1997 | 6/27/1997 | 6/27/1997 | P | PART |
Wes Worcester
|
|
|
need construction conference and special inspector letter
|
INSP - Footings | 6/26/1997 | 6/27/1997 | 6/27/1997 | A | NR |
Wes Worcester
|
|
|
no one at pour site and no response at p/w or job shack
|
INSP - Footings | 5/27/1997 | 5/27/1997 | 5/27/1997 | P | PART |
Carl Dependahl
|
|
|
05/27/97 340 - part, aeration basin, NW section
|
INSP - Footings | 5/15/1997 | 5/15/1997 | 5/15/1997 | P | NR |
Carl Dependahl
|
|
|
05/15/97 340 - UNABLE TO CONTACT....
|
INSP - Final | 5/8/1997 | 5/8/1997 | 5/8/1997 | | NR |
Jim Storey
|
|
|
/ / 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED OTH-OTHER AGENCIES NOT APPROVED fire
|
INSP - Footings | 4/28/1997 | 4/29/1997 | 4/29/1997 | A | CANC |
Alan Hauser
|
|
|
04/28/97 350 - didn't get there
|
INSP - Foundation | 4/24/1997 | 4/28/1997 | 4/28/1997 | A | CANC |
Alan Hauser
|
|
|
04/28/97 350 - FLATWORK didn't get there
|
INSP - Footings | 4/22/1997 | 4/22/1997 | 4/22/1997 | P | PASS |
Alan Hauser
|
|
|
04/22/97 350 - rebar for sump basin north side
|
INSP - Footings | 4/17/1997 | 4/18/1997 | 4/17/1997 | A | PASS |
|
|
|
04/18/97 333 - FTG -OK FOOTING
|
INSP - Foundation | 4/16/1997 | 4/17/1997 | 4/17/1997 | P | PASS |
Alan Hauser
|
|
|
04/17/97 350 - THEY ARE POURING AT 4:00 stem walls ok to pour
|
INSP - Footings | 4/15/1997 | 4/16/1997 | 4/16/1997 | P | PASS |
Alan Hauser
|
|
|
04/16/97 350 - early pm please u.v. basin ftns for control room
|
INSP - Footings | 4/3/1997 | 4/4/1997 | 4/4/1997 | A | PASS |
Alan Hauser
|
|
|
04/04/97 350 - REBAR rebar ok for stoop
|
INSP - Footings | 4/1/1997 | 4/2/1997 | 4/2/1997 | P | PASS |
Alan Hauser
|
|
|
04/02/97 350 - cantelevered sidewalks ok
|
INSP - Footings | 3/24/1997 | 3/25/1997 | 3/25/1997 | A | PART |
Carl Dependahl
|
|
|
03/25/97 340 - re-bar and footings...PART, CANT FIND JOEL H.(PUB WKS SPE WALLS AT NW OK
|
INSP - Footings | 3/12/1997 | 3/14/1997 | 3/14/1997 | P | PASS |
Alan Hauser
|
|
|
03/14/97 350 - POURING AROUND 2 PM rebar clearances ok, placed as per plan, signed sheet in office
|
INSP - Carpentry | 3/11/1997 | 3/11/1997 | 3/12/1997 | P | CANC |
Alan Hauser
|
|
|
03/11/97 350 - Slab pour at the Lander St. Treatment Plant, would like e possible. had to go to gas co. meeting, as per george slane
|