INSP - Letter of compliance | | | 5/19/1997 | | PASS |
|
|
|
Letter of Compliance #12582 issued 5-14-97 to Office Max on the storage racks.
|
INSP - Final | 5/12/1997 | 5/13/1997 | 5/13/1997 | A | PASS |
Jim Storey
|
|
|
05/13/97 301 - said everything you wanted fixed is fixed now. FNL -OK FINAL
|
INSP - Letter of compliance | 5/13/1997 | 5/13/1997 | 5/13/1997 | | PASS |
Jim Storey
|
|
|
/ / 301 - LCI-LETTER OF COMPLIANCE ISSUED 12582#
|
INSP - Letter of compliance | 5/13/1997 | 5/13/1997 | 5/13/1997 | | PASS |
Jim Storey
|
|
|
/ / 301 - LCI-LETTER OF COMPLIANCE ISSUED 12582#
|
INSP - Final | 5/7/1997 | 5/8/1997 | 5/8/1997 | A | NR |
Jim Storey
|
|
|
05/08/97 301 - any day but friday is ok. CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP-Final Inspection | 5/7/1997 | 5/8/1997 | 5/8/1997 | A | PASS |
|
|
|
structural set to go out 5/8 a.m.
|
INSP - Carpentry | 3/14/1997 | 3/18/1997 | 3/18/1997 | A | PASS |
Jim Storey
|
|
|
03/18/97 301 - WIP -WORK IN PROGRESS
|
INSP - Final | 3/11/1997 | 3/11/1997 | 3/14/1997 | P | FAIL |
|
|
|
ask for shawn bloom c/n issued, high storage area has solid shelves, knox box not installed.
|
INSP - Final | 3/11/1997 | 3/11/1997 | 3/12/1997 | P | FAIL |
Jim Storey
|
|
|
03/12/97 301 - ask for shawn bloom CORR-CORREC-CALL FOR REINSP WHEN COMPLETED have engineer of record verri that rack system is as per design. letter required.
|
INSP - Final | 3/11/1997 | 3/11/1997 | 3/11/1997 | P | CANC |
|
|
|
duplicate inspection request
|