INSP - Final | 5/23/1997 | 5/27/1997 | 5/27/1997 | A | CANC |
Carl Dependahl
|
|
|
05/27/97 340 - prev final by 350
|
INSP - Final | 5/23/1997 | 5/23/1997 | 5/23/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - final, letter on glazing, exterior sheathing protected until finished.
|
INSP - Letter of compliance | 5/23/1997 | 5/23/1997 | 5/23/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - c/c #13358
|
INSP - Letter of compliance | 5/23/1997 | 5/23/1997 | 5/23/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - c/c #13358
|
INSP - Grading Inspection | 5/23/1997 | | 5/23/1997 | | PASS |
Rita DeYoung
|
|
|
Received engineers certification of grading and drainage. I inspected grading and approved. Roof drains were not connected but engineers letter says that they have been done. Building department inspector is to verify that roof drains have been connected.
|
INSP - Energy code compliance | 4/2/1997 | 4/2/1997 | 4/2/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - insulation ok, ok to cover
|
INSP - Framing/Rough-in | 4/1/1997 | 4/2/1997 | 4/2/1997 | P | PASS |
Alan Hauser
|
|
|
04/02/97 350 - frame ok
|
INSP - Framing/Rough-in | 3/28/1997 | 4/1/1997 | 4/1/1997 | P | PASS |
Alan Hauser
|
|
|
04/01/97 350 - frame ok, ok to insulate
|
INSP - Footings | 2/21/1997 | 2/24/1997 | 2/24/1997 | A | PASS |
Alan Hauser
|
|
|
02/24/97 350 - ftns. as per plan, setbacks on this hillside lot staked o
|