Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD96-03323
StatusFinaled
Name INDEPENDENT SCHOOL DISTRICT OF
Site Address 916 W WASHINGTON ST
Project NameHIGH SCHOOL
Customer Number 
ePlanReviewNo
Description
* BOISE HIGH SCHOOL * NEW TWO STORY 81,050 SQ. FT., TYPE II-1HR FULLY FIRE SPRINKLERED CLASS ROOM BUILDING. INCLUDES A MEDIA CENTER, CAFETERIA/SOCIAL CENTER, AUXILIARY GYMNASIUM, SCIENCE AND MATH CLASSROOMS AND OTHER SECONDARY SPACES. ALL WORK IS PER APPROVED PLANS AND ATTACHMENTS, PC 761-96, DR-106-93, CU-87-93 SPRINKLERS USED FOR AREA.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 8/18/19988/18/1998 DONE
Details
INSP - Final8/10/19988/10/19988/10/1998PPASS
Details
08/10/98 333 - struct ok for perm other signatures needed
INSP - Final8/7/19988/7/19988/7/1998 PART
Details
08/07/98 333 - cn placed signed for temp
INSP - Final8/6/19988/7/19988/7/1998AFAIL
Details
08/07/98 333 - cn placed
INSP-Final Inspection8/3/19988/3/19988/3/1998PPASS
DetailsRick Jackson
gary ###-#### occ approved
INSP-Final Inspection7/20/19987/20/19987/20/1998PFAIL
DetailsRick Jackson
requested for 1:30 door release and damper relay not working, extinguisher for kitchen, knox box, updated alarm plans for school
INSP - Final7/17/19987/17/19987/17/1998PNR
DetailsRick Jackson
gary ###-#### fire inspection couldn't test detectors for roll up fire doors - simplex not available
INSP - Final6/23/19986/23/19986/23/1998PFAIL
Details
06/23/98 333 - OTH-OTHER AGENCIES NOT APPROVED
INSP - Final6/22/19986/22/19986/22/1998 PART
Details
/ / 333 - GYM TEMP ONLY
INSP - Final6/18/19986/19/19986/19/1998AFAIL
Details
06/19/98 333 - not readt
INSP - Final6/18/19986/18/19986/18/1998 PART
Details
/ / 333 - REVIEWED REQ FOR TEMP
INSP-Final Inspection6/16/19986/19/19986/16/1998A
DetailsRick Jackson
FINAL ###-#### GARY
INSP-Final Inspection6/10/19986/15/19986/15/1998PPART
DetailsRick Jackson
final/ ###-#### not a final insp. sprinkler system hydro pass - still need to hydro the FDC.
INSP-Final Inspection6/10/19986/11/19986/12/1998PCANC
DetailsJoe Tawney
06/11/98 406 - 200 lb test/ ###-#### postponed to monday per Cathy at Shilo, F_V canceled
INSP-Sprinkler Rough-in/Hydro6/10/19986/12/19986/10/1998PCANC
DetailsRick Jackson
sprinkler system/ ###-####
INSP - Framing/Rough-in6/8/19986/8/19986/8/1998PFAIL
Details
06/08/98 333 - not ready
INSP - Framing/Rough-in5/19/19985/22/19985/22/1998AFAIL
Details
05/22/98 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Framing/Rough-in5/5/19985/5/19985/5/1998PPART
Details
05/05/98 333 - CEILINGS ON 1ST OK
INSP-Final Inspection4/23/19984/27/19984/27/1998APART
DetailsRick Jackson
###-#### jennifer hangers needed in 2nd floor classroom. 1st floor requires heads in high ceiling area with multiple soffits.
INSP - Framing/Rough-in4/2/19984/3/19984/3/1998APASS
Details
04/03/98 333 - FRAM-OK FRAMING
INSP - Framing/Rough-in3/23/19983/24/19983/24/1998APASS
Details
03/24/98 333 - alll but ceilings in corridors
INSP - Framing/Rough-in3/4/19983/6/19983/6/1998APASS
Details
03/06/98 333 - 1st floor###-####
INSP-Final Inspection3/4/19983/6/19983/6/1998APASS
DetailsRick Jackson
###-#### underground flush and rough-in of first floor, move head away from beam in riser room. 2nd floor installation in progress.
INSP - Framing/Rough-in3/4/19983/5/19983/5/1998APART
Details
03/05/98 333 - backing to be fire retardent ok to cover all on first flo
INSP - Framing/Rough-in2/9/19982/10/19982/10/1998APART
Details
02/10/98 333 - OTH-OTHER AGENCIES NOT APPROVED
INSP - Conference2/5/19982/5/19982/5/1998 PASS
Details
/ / 333 - resubmittal review
INSP - Miscellaneous1/7/19981/7/19981/7/1998PPART
Details
01/07/98 333 - CMU BLACK AND BRICK VENEER--METAL STUD WALLS--ROOF SYSTEM GYM--WEEKLY INSPECTION in progress
INSP - Miscellaneous11/13/199711/13/199711/13/1997PPASS
Details
11/13/97 333 - REPORT FROM HASEGAWA/ SCHEDULE FOR 11/14/97/ LAY CMU BLOC STRUCTURAL STEEL OR METAL DECKING, METAL STUD WALLS, START ROOF SYSTEM O ELECTRICAL, PLMB, AND HVAC R-IN. in progress
INSP - Miscellaneous11/5/199711/5/199711/5/1997APASS
Details
OCTOBER-CMU BLOCK AND CONCRETE SLABS. THREE QUARTERS OF THE GYM ROOF TRUSSES AND DECK WERE INSTALLED AND 25 PIECES OF STRUCTURAL STEEL AND 2ND FLOOR DECK INSTALLED. POUR 2ND FLOOR SLAB ON FIR 11-7-97..HASAGAWA ASSOC...DF
INSP - Foundation9/8/19979/12/19979/12/1997APASS
Details
CMU BLOCK PLACEMENT, CONCRETE FOOTINGS, SPEC INSPECTOR ON JOB SITE. ok pending special insp report
INSP - Foundation9/8/19979/11/19979/11/1997APASS
Details
09/11/97 333 - CMU BLOCK PLACEMENT CONCRETE FOOTINGS SLAB PLACEMENT.SPEC SITE pending special insp reports
INSP - Foundation9/8/19979/10/19979/10/1997APASS
Details
CMU BLOCK PLACEMENT, CONCRETE FOOTINGS, SPEC. INSPECTOR ON SITE. ok pending special insp report
INSP - Foundation9/8/19979/9/19979/9/1997APART
Details
09/09/97 333 - CMU BLOCK PLACEMENT CONCRETE FOOTINGS, SPEC. INSPECTOR ON ok pending special insp report
INSP - Foundation8/25/19978/29/19978/29/1997PPART
Details
08/29/97 333 - concrete footing and stem walls, at 2 p.m. spec. inspecto FDN -OK FOUNDATION
INSP - Foundation8/25/19978/27/19978/27/1997APASS
Details
08/27/97 333 - pouring footing and stem walls, at 10 a.m. spec. inspecto ok pending special insp reports
INSP - Foundation8/25/19978/26/19978/26/1997PPASS
Details
08/26/97 333 - pouring at 2:30 concrete footing and stem walls, spec. in MASN-REBAR OK
INSP - Foundation8/11/19978/15/19978/15/1997PPASS
Details
08/15/97 333 - LAY CMU BLOCK AND GROUT, SPEC. INSPECTOR ON SITE ok pending special insp reports
INSP - Foundation8/11/19978/14/19978/14/1997PPART
Details
08/14/97 333 - LAY CMU BLOCK AND GROUT, SPEC. INSPECTOR ON SITE pour ok pending special insp report
INSP - Wall cover8/11/19978/14/19978/14/1997PPART
Details
08/14/97 333 - CONCRETE STEM WALL POUR THURSDAY 2:30 ok pending special insp report
INSP - Foundation8/11/19978/13/19978/13/1997PPASS
Details
LAY CMU BLOCK AND GROUT SPEC. INSPECTOR ON SITE ok pending special insp reports
INSP - Wall cover8/11/19978/12/19978/12/1997PPASS
Details
08/12/97 333 - STEM WALL POUR/1:30 P.M. SPEC. INSPECTOR ON SITE Ok pending special inspection reports
INSP - Foundation8/11/19978/11/19978/11/1997PPART
Details
08/11/97 333 - LAY CMU BLOCK AND GROUT, SPEC. INSPECTOR ON SITE ok pending special inspection report 2nd pour
INSP - Foundation8/11/19978/11/19978/11/1997PPART
Details
08/11/97 333 - LAY CMU BLOCK AND GROUT SPEC INSPECTOR ON SITE ok pending special inspection report for first pour
INSP - Foundation7/22/19977/25/19977/25/1997PPART
Details
07/25/97 333 - pouring concrete at 2:30p.m. stem walls. special inspecto ok pending special insp reports
INSP - Foundation7/22/19977/24/19977/24/1997PPART
Details
07/24/97 333 - pouring at 2:30 p.m. stem walls special inspector on site ok pending special insp reports
INSP - Footings7/22/19977/23/19977/23/1997APASS
Details
07/23/97 333 - ok pending special insp
INSP - Foundation7/22/19977/23/19977/23/1997PPART
Details
07/23/97 333 - stem walls concrete pours at 2:30 special inspector on si pending special insp reports
INSP - Wall cover7/22/19977/23/19977/23/1997PPASS
Details
07/23/97 333 - ok pending specilal insp reports
INSP - Foundation7/17/19977/18/19977/18/1997PPART
Details
07/17/97 333 - 2:30 pouring FDN -OK FOUNDATION
INSP - Foundation7/17/19977/17/19977/17/1997PPART
Details
07/17/97 333 - ok pending special insp reports
INSP - Conference6/3/19976/3/19976/2/1997PPASS
Details
06/03/97 333 - SAID YOU TOLD HIM YOU WERE AVAILABLE THIS P.M. pre con