INSP - Conference | 9/12/1997 | 9/12/1997 | 9/12/1997 | | PASS |
Wes Worcester
|
|
|
/ / 342 - called Cathy and mechanical and bldg ok
|
INSP - Final | 9/12/1997 | 9/12/1997 | 9/12/1997 | P | PASS |
Wes Worcester
|
|
|
09/12/97 342 - 3-3:30 pm
|
Permanent Occupancy | | 9/12/1997 | 9/12/1997 | | DONE |
|
|
|
|
Permanent Occupancy | | 9/12/1997 | 9/12/1997 | | DONE |
|
|
|
|
INSP - Final | 9/4/1997 | 9/4/1997 | 9/4/1997 | A | FAIL |
Jack Frank
|
|
|
cor. and double permit fee due no permit for signs and neon signs not wired to NEC and not listed by testing lab jf
|
INSP - Final | 9/4/1997 | 9/4/1997 | 9/4/1997 | A | NR |
Wes Worcester
|
|
|
sign elect not signed off, ceiling grid and hood duct not open
|
INSP - Final | 9/3/1997 | 9/3/1997 | 9/3/1997 | P | NR |
Wes Worcester
|
|
|
elect still not done
|
INSP-Final Inspection | 8/29/1997 | 8/29/1997 | 8/29/1997 | P | PASS |
Rick Jackson
|
|
|
c/n items done, perm ok
|
INSP - Final | 8/22/1997 | 8/25/1997 | 8/25/1997 | A | NR |
Wes Worcester
|
|
|
still waiting on fire
|
INSP - Final | 8/25/1997 | 8/25/1997 | 8/25/1997 | P | PART |
Wes Worcester
|
|
|
|
INSP-Final Inspection | 8/25/1997 | 8/25/1997 | 8/25/1997 | A | FAIL |
|
|
|
hood, exit lights, emergency lights, fryer location all need corrections...need to paint curb
|
INSP-Final Inspection | 8/25/1997 | 8/25/1997 | 8/25/1997 | A | FAIL |
|
|
|
called before returning, wes said they were ready, arrived to find hood shutdowns still not operable, told to callwhen ready and that there would be a reinspection fee. have been there 4 times at contractors request.
|
INSP - Conference | 8/22/1997 | 8/22/1997 | 8/22/1997 | A | PASS |
Wes Worcester
|
|
|
Wes called to discuss problems w/other agencies
|
INSP - Conference | 8/22/1997 | 8/22/1997 | 8/22/1997 | | PASS |
Wes Worcester
|
|
|
/ / 342 - called by general and he will not be ready this pm
|
INSP - Temporary occupancy | 8/21/1997 | 8/22/1997 | 8/22/1997 | P | NR |
Wes Worcester
|
|
|
08/22/97 342 -
|
INSP-Final Inspection | 8/22/1997 | 8/22/1997 | 8/22/1997 | A | FAIL |
|
|
|
hoods not wired yet, exposed electrical conductors in many locations, not inspected. wes will call when ready
|
INSP - Ceiling grid | 8/20/1997 | 8/21/1997 | 8/21/1997 | P | CANC |
Wes Worcester
|
|
|
added in the field
|
INSP - Ceiling grid | 8/21/1997 | 8/21/1997 | 8/21/1997 | | NR |
Wes Worcester
|
|
|
08/21/97 342 - STILL WIRING
|
INSP - Conference | 8/21/1997 | 8/21/1997 | 8/21/1997 | | PART |
Wes Worcester
|
|
|
/ / 342 - LEAVE OPEN SEVERAL CEILING PANELS FOR TOMORROW'S INSPECTION
|
INSP - Wall cover | 8/21/1997 | 8/21/1997 | 8/21/1997 | | PART |
Wes Worcester
|
|
|
/ / 342 - 1ST LAYER OK ON WEST HOOD
|
INSP-Final Inspection | 8/20/1997 | 8/21/1997 | 8/21/1997 | P | FAIL |
|
|
|
wes ###-#### ###-####-cell- please call before going out 3pm...not ready 4:45pm retry, not ready
|
INSP - Carpentry | 8/20/1997 | 8/20/1997 | 8/20/1997 | P | PART |
Wes Worcester
|
|
|
placing another stud and layer of rock
|
INSP - Conference | 8/20/1997 | 8/20/1997 | 8/20/1997 | P | PART |
Wes Worcester
|
|
|
met w/Marlene @ plan ck re:1hr shaft const at Perkins
|
INSP - Conference | 8/20/1997 | 8/20/1997 | 8/20/1997 | | PASS |
Wes Worcester
|
|
|
/ / 342 - met w/Dave and Wes @ hood
|
INSP - Conference | 8/20/1997 | 8/20/1997 | 8/20/1997 | | PART |
Wes Worcester
|
|
|
/ / 342 - need detail from Bob
|
INSP - Conference | 8/20/1997 | 8/20/1997 | 8/20/1997 | | PART |
Wes Worcester
|
|
|
/ / 342 - called Bob, called by Wes at Perkins
|
INSP - Conference | 8/20/1997 | 8/20/1997 | 8/20/1997 | | FAIL |
Wes Worcester
|
|
|
/ / 342 - plan depicts two layers of gwb 5/8's w/3" air space adjacent shaft assy as a 1 hour assy???? Bob Garrison was plan checker
|
INSP - Wall cover | 8/19/1997 | 8/20/1997 | 8/20/1997 | A | PART |
Wes Worcester
|
|
|
08/20/97 342 -
|
INSP - Framing/Rough-in | 8/18/1997 | 8/18/1997 | 8/20/1997 | P | FAIL |
Wes Worcester
|
|
|
08/20/97 342 - PARTIAL HOODS IN KITCHEN EARLY P.M.
|
INSP - Conference | 8/15/1997 | 8/15/1997 | 8/15/1997 | P | FAIL |
Wes Worcester
|
|
|
08/15/97 342 -
|
INSP - Framing/Rough-in | 7/28/1997 | 7/29/1997 | 7/29/1997 | A | PART |
Wes Worcester
|
|
|
07/29/97 342 - still installing blocking at drag strut locations, still & detail for clarification of drag strut installation different from pla
|
INSP - Framing/Rough-in | 7/25/1997 | 7/28/1997 | 7/28/1997 | A | FAIL |
Wes Worcester
|
|
|
07/28/97 342 - hold downs not installed correctly, hangers not installed struts not to plan
|
INSP - Framing/Rough-in | 7/23/1997 | 7/24/1997 | 7/24/1997 | A | NR |
Wes Worcester
|
|
|
needs plumbing, finish installing hold downs, and fireblocking
|
INSP - Framing/Rough-in | 7/22/1997 | 7/22/1997 | 7/23/1997 | P | PART |
Wes Worcester
|
|
|
outside sheer wall nailing ok
|
INSP - Conference | 7/17/1997 | 7/17/1997 | 7/17/1997 | P | PART |
Wes Worcester
|
|
|
Will call to set up an appointment ck on removing lolly column at cantilever gluelam
|
INSP - Conference | 6/27/1997 | 6/27/1997 | 6/27/1997 | P | PASS |
|
|
|
06/27/97 333 - talked about framing
|
INSP - Foundation | 6/6/1997 | 6/6/1997 | 6/5/1997 | P | PASS |
|
|
|
06/06/97 333 - FDN -OK FOUNDATION
|
INSP - Footings | 6/3/1997 | 6/4/1997 | 6/4/1997 | P | PASS |
|
|
|
06/04/97 333 - footings ok pending spec insp report
|