BLD-Final | 1/19/2000 | 1/20/2000 | 1/20/2000 | A | PASS |
|
|
|
Doors have been installed new exit stair 90 minut doors have been installed per approved plan l/c issued #18291 1/20/00 11:44:11 AM
|
INSP-Final Inspection | 5/11/1999 | 5/12/1999 | 5/12/1999 | P | PART |
Rick Jackson
|
|
|
after 1/ Dennis ###-#### tested smoke control fans - okay for monitoring supervisory
|
INSP-Final Inspection | 5/4/1999 | 5/4/1999 | 5/4/1999 | P | PART |
Rick Jackson
|
|
|
tested smoke evac system for the 8th, 4th and 3rd floors and all were okay
|
INSP-Conference | 4/21/1999 | 4/21/1999 | 4/21/1999 | P | PART |
Rick Jackson
|
|
|
set up smoke evac certification for 4/27 3:30 pm
|
INSP-Conference | 4/19/1999 | 4/19/1999 | 4/19/1999 | P | PART |
Rick Jackson
|
|
|
gave approval for smoke evac controls to electrical contractor and general contractor
|
INSP-Conference | 4/13/1999 | 4/13/1999 | 4/13/1999 | P | PART |
Rick Jackson
|
|
|
approved smoke evac changes for control in FCC
|
INSP-Conference | 4/1/1999 | 4/1/1999 | 4/1/1999 | P | PART |
Rick Jackson
|
|
|
requested diagram for smoke control in fire control room
|
INSP - Final | 3/26/1999 | 3/26/1999 | 3/26/1999 | P | |
|
|
|
|
INSP-Final Inspection | 3/26/1999 | 3/26/1999 | 3/26/1999 | P | PART |
Rick Jackson
|
|
|
smoke evac problems for high rise; knox box; NFPA 72;
|
INSP-Final Inspection | 3/25/1999 | 3/25/1999 | 3/25/1999 | A | FAIL |
Rick Jackson
|
|
|
c/n items not complete
|
INSP-Alarm Testing | 3/24/1999 | 3/24/1999 | 3/24/1999 | P | PART |
Rick Jackson
|
|
|
generator 2 hr test okay; alarms not programmed properly for notification; sprinkler alarms tested okay;
|
INSP-Alarm Testing | 3/19/1999 | 3/23/1999 | 3/23/1999 | A | FAIL |
Rick Jackson
|
|
|
###-#### BOB//FIRE ALARM INSPECT elevators not ready; smoke evac controls not supervised; strobe in lobby not right cd; fire phones have static; labels on panel not correct
|
INSP-Final Inspection | 3/22/1999 | 3/23/1999 | 3/23/1999 | A | FAIL |
Rick Jackson
|
|
|
###-#### SAM//FINAL FIRE core not complete; generator test; fan controls;
|
INSP - Framing/Rough-in | 3/22/1999 | 3/22/1999 | 3/22/1999 | A | PART |
|
|
|
03/22/99 338 - fire caulk made ok in the core area 2-8th
|
INSP - Framing/Rough-in | 3/16/1999 | 3/19/1999 | 3/19/1999 | P | PART |
|
|
|
03/19/99 338 - core pressurization testing 1.5 hrs o.t.
|
INSP-Final Inspection | 3/19/1999 | 3/19/1999 | 3/19/1999 | P | PART |
Rick Jackson
|
|
|
tested smoke evac system - retest several areas and after tenant spaces complete; door sweeps not on
|
INSP-Conference | 3/17/1999 | 3/17/1999 | 3/17/1999 | P | PART |
Rick Jackson
|
|
|
discussed smoke evac test; checked water tank vent
|
INSP-Conference | 3/3/1999 | 3/3/1999 | 3/3/1999 | P | PART |
Rick Jackson
|
|
|
profit meeting
|
INSP-Final Inspection | 3/1/1999 | 3/2/1999 | 3/2/1999 | A | PART |
Rick Jackson
|
|
|
03/02/99 409 - pump test will start at 10:00 pump test only - okay. will flow through test header and test standpipe
|
INSP-Conference | 3/1/1999 | 3/1/1999 | 3/1/1999 | P | PART |
Rick Jackson
|
|
|
left corrrection notice for items from FV's inspection
|
INSP-Conference | 2/25/1999 | 2/25/1999 | 2/25/1999 | A | PART |
Rick Jackson
|
|
|
requirements for shell with Bob (gen contractor and TVFP)
|
INSP-Conference | 2/16/1999 | 2/16/1999 | 2/16/1999 | P | PART |
Rick Jackson
|
|
|
conference for final occ requirements
|
INSP-Supply line flush | 2/4/1999 | 2/4/1999 | 2/4/1999 | P | PASS |
Rick Jackson
|
|
|
SAM ###-#### PAGER underground flush okay
|
INSP - Framing/Rough-in | 2/3/1999 | 2/3/1999 | 2/3/1999 | P | |
|
|
|
Scheduled by Hello!. Contact phone is [8591837].
|
INSP-Conference | 2/3/1999 | 2/3/1999 | 2/3/1999 | | PART |
Rick Jackson
|
|
|
/ / 409 - WALK THROUGH WITH PERRY AND CONTRACTOR
|
INSP - Framing/Rough-in | 1/15/1999 | 1/20/1999 | 1/20/1999 | P | FAIL |
Wes Worcester
|
|
|
01/20/99 342 - Scheduled by Hello!. Contact phone is [8591837]. Perry
|
INSP - Framing/Rough-in | 1/12/1999 | 1/13/1999 | 1/13/1999 | A | PART |
|
|
|
01/13/99 338 - MADEOK ON WALK THROUGH WITH "BOB" THE SUPER LOOKED AT THE
|
INSP - Framing/Rough-in | 1/5/1999 | 1/6/1999 | 1/6/1999 | A | FAIL |
Wes Worcester
|
|
|
01/06/99 342 - Scheduled by Hello!. NO CONTACT NUMBER, GIVEN TO KIM
|
INSP - Framing/Rough-in | 12/23/1998 | 12/28/1998 | 12/28/1998 | A | PART |
|
|
|
12/28/98 333 - core ok need shaft protection and beam protection at stai
|
INSP-Sprinkler Rough-in/Hydro | 12/15/1998 | 12/15/1998 | 12/15/1998 | P | PART |
Rick Jackson
|
|
|
checked sheetrocking per L Smith request - all type x
|
INSP-Sprinkler Rough-in/Hydro | 12/9/1998 | 12/10/1998 | 12/10/1998 | A | PART |
Rick Jackson
|
|
|
SAM BALL PAGER ###-#### R/I okay to cover 1st floor lobby and all bathrooms. head still needed in the small utility room off 2nd floor bathrooms
|
INSP - Framing/Rough-in | 11/24/1998 | 11/25/1998 | 11/25/1998 | A | PART |
|
|
|
11/25/98 333 - bath on 12and 3
|
INSP - Framing/Rough-in | 11/13/1998 | 11/16/1998 | 11/16/1998 | A | FAIL |
|
|
|
11/16/98 333 - conference on framing
|
INSP - Framing/Rough-in | 9/21/1998 | 9/21/1998 | 9/21/1998 | P | PART |
|
|
|
first floor in progress
|
INSP - Framing/Rough-in | 9/1/1998 | 9/1/1998 | 9/1/1998 | P | PART |
|
|
|
09/01/98 333 - resubmittal on firestopping approved
|
INSP - Framing/Rough-in | 8/18/1998 | 8/19/1998 | 8/19/1998 | P | PART |
|
|
|
08/19/98 333 - review proposed 4hr wall detail
|
INSP - Framing/Rough-in | 8/3/1998 | 8/4/1998 | 8/4/1998 | P | PART |
|
|
|
08/04/98 333 - firestopping and assemblies
|
INSP - Foundation | 7/28/1998 | 7/29/1998 | 7/29/1998 | A | PASS |
|
|
|
07/30/98 333 - FDN -OK FOUNDATION
|
INSP - Foundation | 7/3/1998 | 7/3/1998 | 7/3/1998 | P | |
|
|
|
Scheduled by Hello!. Contact phone is [8591837].
|
INSP - Foundation | 6/22/1998 | 6/22/1998 | 6/22/1998 | | PART |
|
|
|
/ / 333 - GRADE BEAMS ON SOUTH WALL OK PEND SPECIAL INSP REPORT
|
INSP - Foundation | 6/10/1998 | 6/10/1998 | 6/10/1998 | P | PART |
|
|
|
06/10/98 333 - grade beams north side
|
INSP - Foundation | 6/9/1998 | 6/9/1998 | 6/9/1998 | | PART |
|
|
|
/ / 333 - GRADE BEAMS IN PROGRESS
|
INSP - Foundation | 6/8/1998 | 6/8/1998 | 6/8/1998 | | PART |
|
|
|
/ / 333 - GRADE BEAMS IN PROGRESS
|
INSP - Foundation | 6/3/1998 | 6/3/1998 | 6/3/1998 | P | PART |
|
|
|
06/03/98 333 - fdn east wall ok
|
INSP - Foundation | 5/27/1998 | 5/27/1998 | 5/27/1998 | | PART |
|
|
|
/ / 333 - FDN WALLS OK
|
INSP - Foundation | 5/26/1998 | 5/26/1998 | 5/26/1998 | | PART |
|
|
|
/ / 333 - CASON CAPS OK
|
INSP - Foundation | 5/19/1998 | 5/19/1998 | 5/19/1998 | | PART |
|
|
|
/ / 333 - CASONS SOUTH ESAT SIDE OK
|
INSP - Foundation | 5/15/1998 | 5/15/1998 | 5/15/1998 | | PART |
|
|
|
/ / 333 - caps ok
|
INSP - Foundation | 5/13/1998 | 5/13/1998 | 5/13/1998 | | PART |
|
|
|
/ / 333 - PIER CAPS ON NORTH SIDE OK PEND SPEC INSP REPORTS
|
INSP - Foundation | 5/12/1998 | 5/12/1998 | 5/12/1998 | A | PART |
|
|
|
05/12/98 333 - west wall ok
|
INSP - Foundation | 5/7/1998 | 5/7/1998 | 5/7/1998 | A | PART |
|
|
|
05/07/98 333 - west fdn ok pending special insp reports
|
INSP - Foundation | 5/4/1998 | 5/4/1998 | 5/4/1998 | | PART |
|
|
|
05/04/98 333 - ok pending special insp reports
|
INSP - Foundation | 4/29/1998 | 4/30/1998 | 4/30/1998 | A | PART |
|
|
|
04/30/98 333 - ok pending special insp reports
|
INSP - Foundation | 4/27/1998 | 4/27/1998 | 4/27/1998 | | PART |
|
|
|
/ / 333 - OK PENDING SPECIAL INSP REPORTS
|
INSP - Foundation | 4/19/1998 | 4/20/1998 | 4/20/1998 | A | PART |
|
|
|
04/20/98 333 - pending special insp reports
|
INSP - Concrete | 4/16/1998 | 4/16/1998 | 4/16/1998 | | PART |
|
|
|
04/16/98 333 - pre con meeting
|
INSP - Foundation | 4/15/1998 | 4/15/1998 | 4/15/1998 | | PART |
|
|
|
/ / 333 - OK PENDING SPECIAL INSP REPORT
|
INSP - Conference | 4/13/1998 | 4/13/1998 | 4/13/1998 | | PASS |
|
|
|
/ / 333 - pre con meeting
|
INSP - Foundation | 4/10/1998 | 4/10/1998 | 4/10/1998 | P | PART |
|
|
|
ok pend special insp report
|
INSP - Foundation | 4/8/1998 | 4/8/1998 | 4/8/1998 | P | PART |
|
|
|
ok pending special insp report
|
INSP - Foundation | 4/8/1998 | 4/8/1998 | 4/8/1998 | | PART |
|
|
|
04/08/98 333 - ok pend spec insp report###-####
|
INSP - Foundation | 4/6/1998 | 4/7/1998 | 4/7/1998 | A | PART |
|
|
|
04/07/98 333 - ok pend spec insp report
|
INSP - Foundation | 4/1/1998 | 4/2/1998 | 4/2/1998 | P | PART |
|
|
|
04/02/98 333 - CASONS OK PENDING SPEC INSP REPORT
|
INSP - Foundation | 3/31/1998 | 4/1/1998 | 4/1/1998 | P | PART |
|
|
|
04/01/98 333 - pending special insp report
|
INSP - Foundation | 3/30/1998 | 3/31/1998 | 3/31/1998 | A | PART |
|
|
|
03/31/98 333 - ksons ok pend spec ins report
|
INSP - Foundation | 3/30/1998 | 3/30/1998 | 3/30/1998 | P | PART |
|
|
|
03/30/98 333 - FOOTING ok pend spes insp report
|
INSP - Foundation | 3/17/1998 | 3/17/1998 | 3/17/1998 | | PART |
|
|
|
/ / 333 - PRECON W / BOB T AND MTI
|