INSP - Final | 10/29/1997 | 10/29/1997 | 10/29/1997 | P | PASS |
|
|
|
SIGNED THE OCC REQ CARD FINAL PERM COLUMN
|
Permanent Occupancy | | 10/29/1997 | 10/29/1997 | | DONE |
|
|
|
|
Permanent Occupancy | | 10/29/1997 | 10/29/1997 | | DONE |
|
|
|
|
INSP-Final Inspection | 10/24/1997 | 10/27/1997 | 10/27/1997 | A | PASS |
Joe Tawney
|
|
|
10/27/97 406 - SCHEDULED FOR 8:30 REINSP FOR FINAL OK FOR PERM OCC
|
INSP-Final Inspection | 10/8/1997 | 10/9/1997 | 10/9/1997 | A | FAIL |
Joe Tawney
|
|
|
10/09/97 406 - FINAL FAIL ALARM SYSTEM SPKLR HEAD FIRE EXT
|
INSP-Sprinkler Rough-in/Hydro | 10/2/1997 | 10/2/1997 | 10/2/1997 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON HYDRO TEST FOR DPV SPKLR SYSTEM
|
INSP-Supply line flush | 9/5/1997 | 9/5/1997 | 9/5/1997 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON UNDERGROUND FLUSH
|
INSP-Supply line flush | 9/5/1997 | 9/5/1997 | 9/5/1997 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON UNDERGROUND FLUSH
|
INSP - Framing/Rough-in | 9/3/1997 | 9/4/1997 | 9/4/1997 | A | PASS |
|
|
|
09/04/97 338 - CEILING
|
INSP - Framing/Rough-in | 8/28/1997 | 8/29/1997 | 8/29/1997 | A | PART |
|
|
|
08/29/97 338 - AFTER 10:00-METAL STUD VERBAL CORRECTIONS i NEED ASSEMBLI PENETRATIONS OF THE 1-HOUR CEILING ASSY IN THE MEC ROOM
|
INSP - Framing/Rough-in | 8/26/1997 | 8/27/1997 | 8/28/1997 | A | PASS |
|
|
|
08/27/97 338 - steel stud framing ceiling frame ok
|
INSP - Framing/Rough-in | 8/11/1997 | 8/11/1997 | 8/11/1997 | P | PASS |
|
|
|
08/11/97 338 - OTH-OTHER AGENCIES NOT APPROVED ok to cover after heating signoff
|
INSP-Sprinkler Rough-in/Hydro | 8/8/1997 | 8/8/1997 | 8/8/1997 | | PART |
|
|
|
OK ON HYDRO TEST OF UNDERGROUND FDC
|
INSP-Sprinkler Rough-in/Hydro | 7/29/1997 | 7/30/1997 | 7/30/1997 | A | PART |
Joe Tawney
|
|
|
07/30/97 406 - SPKLR ROUGH IN OK TO COVER ONE DP SYSTEM
|
INSP - Framing/Rough-in | 7/14/1997 | 7/14/1997 | 7/14/1997 | | NR |
|
|
|
/ / 338 - reinspection from 07-14-97 OTH-OTHER AGENCIES NOT APPROVED
|
INSP - Framing/Rough-in | 7/14/1997 | 7/14/1997 | 7/14/1997 | P | NH |
|
|
|
07/14/97 338 - 6:pm out of time
|
INSP - Framing/Rough-in | 7/10/1997 | 7/11/1997 | 7/11/1997 | A | PART |
Jim Storey
|
|
|
07/11/97 301 - FRAMING ROOF CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Masonry | 6/27/1997 | 6/27/1997 | 6/27/1997 | P | PASS |
|
|
|
06/27/97 338 - made ok with sp insp blessingF.Y.I. SPECIAL INSPECTOR ON AT 11 A.M.
|
INSP - Masonry | 6/25/1997 | 6/26/1997 | 6/26/1997 | A | PASS |
|
|
|
06/26/97 338 - GROUTING 9:30 AM made ok with sp insp ok
|
INSP - Masonry | 6/24/1997 | 6/25/1997 | 6/25/1997 | A | PASS |
|
|
|
06/25/97 338 - GROUT POURING GROUT AT 8 A.M.made ok MASN-REBAR OK
|
INSP - Site Preparation | 6/20/1997 | 6/23/1997 | 6/23/1997 | A | PASS |
|
|
|
06/23/97 338 - I didn't know what to put this under so he is pouring gro know if you needed to stop by!AJC made ok with sp insp approval
|
INSP - Masonry | 6/19/1997 | 6/19/1997 | 6/19/1997 | P | PASS |
|
|
|
06/19/97 338 - masonry grout - pumping at 8 a.m. forgot to call Wed. MASN-REBAR OK ON JOB. made ok with sp insp approval r-bar is placed
|
INSP - Foundation | 5/20/1997 | 5/20/1997 | 5/19/1997 | P | PASS |
|
|
|
05/20/97 333 - stem walls 2 o'clock pouring
|
INSP - Footings | 5/19/1997 | 5/19/1997 | 5/19/1997 | P | PASS |
|
|
|
05/20/97 333 - FTG -OK FOOTING
|
INSP - Footings | 5/16/1997 | 5/16/1997 | 5/16/1997 | P | PASS |
|
|
|
05/16/97 338 - madeok ok to cut off the verts to pour the slab per the a insp for the drill and epoxy of the extensions after the slab
|
INSP - Foundation | 5/2/1997 | 5/2/1997 | 5/2/1997 | P | PART |
Carl Dependahl
|
|
|
05/02/97 340 - FDN INSUL INPLACE; PENDING SPEC INSP REPORT, LOOKS OK
|
INSP - Foundation | 4/30/1997 | 4/30/1997 | 4/30/1997 | P | CANC |
Carl Dependahl
|
|
|
FOUNDATION STEM WALL. POURING AT 3 P.M./CANCELED INSPECTION, TO MUDDY.
|
INSP - Footings | 4/28/1997 | 4/29/1997 | 4/29/1997 | P | PART |
Carl Dependahl
|
|
|
04/29/97 340 - IF THEY HAVE TIME WILL DO STEM WALL ALSO...MTI ONSITE, PE
|
INSP - Conference | 4/28/1997 | 4/28/1997 | 4/28/1997 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - HAD QUICK PRE-CON W/ DALE, ONSITE SUPT. & TROY, MTI SPEC INS
|
INSP - Footings | 4/28/1997 | 4/28/1997 | 4/28/1997 | P | PASS |
Carl Dependahl
|
|
|
04/28/97 340 - POURING AT 3 P.M. FORM & STEEL OK
|