INSP - Final | 6/4/1997 | 6/5/1997 | 6/5/1997 | A | PASS |
Alan Hauser
|
|
|
06/05/97 350 - Final Occupancy final ok
|
INSP - Letter of compliance | 6/5/1997 | 6/5/1997 | 6/5/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - c/c #13356
|
INSP - Letter of compliance | 6/5/1997 | 6/5/1997 | 6/5/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - c/c #13356
|
INSP - Energy code compliance | 5/1/1997 | 5/1/1997 | 5/1/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - insulation ok, ok to cover
|
INSP - Framing/Rough-in | 5/1/1997 | 5/1/1997 | 5/1/1997 | P | PASS |
Alan Hauser
|
|
|
05/01/97 350 - frame reinspect frame ok
|
INSP - Framing/Rough-in | 4/29/1997 | 4/30/1997 | 4/30/1997 | A | PASS |
Alan Hauser
|
|
|
04/29/97 350 - frame ok, ok to insulate
|
INSP - Foundation | 4/2/1997 | 4/2/1997 | 4/2/1997 | P | PART |
Carl Dependahl
|
|
|
04/02/97 340 - TAKE FOR ALAN, PORED W/O INSP LOOKS OK, NO PLAN. 350 AREA
|
INSP - Footings | 3/31/1997 | 4/1/1997 | 4/1/1997 | P | PASS |
Alan Hauser
|
|
|
04/01/97 350 - ftns. poured, setbacks ok
|