INSP - Final | 11/24/1997 | 11/24/1997 | 11/24/1997 | P | PASS |
Carl Dependahl
|
|
|
REINSP OK
|
INSP - Letter of compliance | 11/25/1997 | 11/24/1997 | 11/24/1997 | P | PASS |
Carl Dependahl
|
|
|
LC 015098
|
INSP - Final | 11/20/1997 | 11/21/1997 | 11/21/1997 | P | FAIL |
Tom Arcoraci
|
|
|
|
INSP - Energy code compliance | 11/3/1997 | 11/3/1997 | 11/3/1997 | P | PART |
Carl Dependahl
|
|
|
CHK VAPOR BARRIER AT FINAL
|
INSP - Framing/Rough-in | 11/3/1997 | 11/3/1997 | 11/3/1997 | P | PASS |
Carl Dependahl
|
|
|
REINSPECTION CN OK
|
INSP - Framing/Rough-in | 10/27/1997 | 10/27/1997 | 10/27/1997 | P | FAIL |
Carl Dependahl
|
|
|
C/N...SUPPORT TRUSS AT GAR, PATCH GYP AT 1HR, COMPLETE GAS TEST. OK TO INSUL.
|
INSP - Carpentry | 5/7/1997 | 5/8/1997 | 5/8/1997 | A | PASS |
Jim Sly
|
|
|
05/07/97 316 - Gave to Alan H.
|
INSP - Framing/Rough-in | 4/29/1997 | 4/29/1997 | 4/29/1997 | P | PASS |
Alan Hauser
|
|
|
04/29/97 350 - SUB-FLOOR underfloor ok
|
INSP - Footings | 4/21/1997 | 4/22/1997 | 4/22/1997 | A | PASS |
Alan Hauser
|
|
|
04/22/97 350 - ftns ok
|
INSP - Foundation | 4/9/1997 | 4/10/1997 | 4/10/1997 | A | PASS |
Alan Hauser
|
|
|
04/10/97 350 - stem walls ok
|
INSP - Footings | 4/4/1997 | 4/7/1997 | 4/7/1997 | A | PASS |
Alan Hauser
|
|
|
04/07/97 350 - ftns. ok
|