Information based on query as of Monday, July 1, 2024.
Permit Information
Permit NumberBLD97-00763
StatusExpired
Name HEWLETT-PACKARD COMPANY
Site Address 9700 W BETHEL CT
Project NameHP #25
Customer Number46B11152
ePlanReviewNo
Description
HEWLETT PACKARD T.I.S. ADDITION * TO CONSTRUCT A 26,950 SQ. FT., II-N FULLY FIRE SPRINKLERED "SHELL ONLY" ADDITION WITH EIFS EXTERIOR FINISH TO AN EXISTING DATA CENTER. OTHER WORK INCLUDES ALL RELATED SITE WORK AND PAVING PER DR#20-97/9700, PC97-164 AND APPROVED PLANS AND ATTACHMENTS.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final1/2/19981/2/19981/2/1998 PART
Details
/ / 338 - SIGNED THE TEMP COL
INSP - Final1/2/19981/2/19981/2/1998 PART
Details
/ / 338 - SIGNED THE TEMP COL
INSP - Final12/31/199712/31/199712/31/1997 PASS
DetailsJoe Tawney
/ / 406 - FINAL OK FOR CERT OF COMPL
INSP - Framing/Rough-in11/18/199711/19/199711/19/1997ACANC
Details
sent to 333
INSP - Framing/Rough-in11/19/199711/19/199711/19/1997 PART
Details
/ / 333 - bathrooms ok will recall for firestoping at corridor walls a
INSP - Framing/Rough-in11/4/199711/5/199711/6/1997APART
DetailsJim Storey
11/05/97 301 - ceiling in computor rm. ok for cover all but at 2 hr occ. for fire stopping detial for through pentrations and clean room wall gyp part of the 2 hr assembly. isue fire stopping product required on both s of sleave penatrat
INSP - Framing/Rough-in9/8/19979/9/19979/9/1997APASS
Details
09/09/97 338 - HP #25 c/n issued made ok to cover
INSP - Conference8/27/19978/27/19978/28/1997PPASS
Details
08/27/97 338 - made ok for the new tunnel corridor sys at the entry area
INSP - Conference8/6/19978/6/19978/6/1997PPASS
Details
08/06/97 338 -
INSP - Conference8/1/19978/4/19978/4/1997ACANC
DetailsRuss Owen
08/04/97 407 - CONF. WITH YOU ON REMODEL JOB THEY ARE DOING, HE SAID YOU A.M. ??????????/PAT will call perry on phone just has a question about the kitchen remodel i other buuilding.
INSP - Foundation8/1/19978/4/19978/4/1997A
DetailsRuss Owen
POUR AT 10 A.M. SPECIAL INSPECTOR ON SITE.
INSP - Footings7/30/19977/30/19977/30/1997PPASS
Details
07/30/97 338 - pouring a concrete footings made ok with sp insp approval
INSP - Foundation7/21/19977/22/19977/21/1997APASS
Details
07/22/97 338 - SPECIAL INSPECTOR ON SITE RE-BAR made ok with sp insp ble
INSP - Footings7/16/19977/17/19977/17/1997PPASS
Details
07/17/97 338 - made ok with sp insp blessing
INSP - Masonry7/10/19977/11/19977/11/1997APART
DetailsTom Arcoraci
REFORCING BOND BEAM WALLS spec inspec on site
INSP - Masonry7/7/19977/8/19977/8/1997APASS
Details
07/08/97 338 - BUILDING #25 MASN-REBAR OK sp insp ok
INSP - Masonry7/1/19977/2/19977/2/1997APASS
Details
07/02/97 338 - MAS. RE-BAR r-bar placed ok to go with sp insp ok
INSP - Foundation6/30/19977/1/19977/1/1997APASS
Details
07/01/97 338 - made ok with sp insp approval
INSP - Masonry6/27/19976/30/19976/30/1997APASS
Details
06/30/97 338 - pouring concrete block walls made ok with sp insp approva
INSP - Masonry6/24/19976/25/19976/25/1997APASS
Details
06/25/97 338 - MASONRY BLK. MASN-REBAR OK WITH SP INSP APPROVAL
INSP - Footings6/19/19976/20/19976/20/1997APASS
DetailsTom Arcoraci
early am Buck ###-#### made ok w\spec app
INSP - Foundation6/12/19976/13/19976/13/1997APASS
Details
06/13/97 338 - made ok with sp insp approval
INSP - Foundation6/6/19976/9/19976/9/1997PPASS
Details
06/09/97 338 - FND. WALL. EARLY PM. made ok with the sp insp blessing
INSP - Conference6/5/19976/5/19976/5/1997 PASS
Details
/ / 338 - conf witht he supper on the rain delays
INSP - Footings6/5/19976/5/19976/5/1997PPASS
Details
06/05/97 338 - made ok with sp insp approval
INSP - Foundation6/5/19976/5/19976/5/1997PPASS
Details
06/05/97 338 - made ok with sp insp approval
INSP - Footings6/3/19976/4/19976/4/1997PNR
Details
06/04/97 338 - FOOTING REBAR ì
INSP - Footings5/30/19976/2/19976/2/1997APASS
Details
06/02/97 338 - ok with the sp insp blessing
INSP - Footings5/29/19975/30/19975/30/1997ACANC
Details
05/30/97 338 - contr postponed till monday