INSP - Final | 9/8/1997 | 9/8/1997 | 9/8/1997 | P | PASS |
Tom Arcoraci
|
|
|
|
INSP - Final | 9/5/1997 | 9/8/1997 | 9/8/1997 | P | CANC |
Russ Owen
|
|
|
09/08/97 407 - transfer to Tom A.
|
INSP - Letter of compliance | 9/8/1997 | 9/8/1997 | 9/8/1997 | P | PASS |
Tom Arcoraci
|
|
|
13027
|
INSP - Framing/Rough-in | 8/12/1997 | 8/11/1997 | 8/11/1997 | P | PASS |
Russ Owen
|
|
|
re-insp 1 item.
|
INSP - Framing/Rough-in | 8/4/1997 | 8/5/1997 | 8/5/1997 | A | PART |
Russ Owen
|
|
|
08/05/97 407 - re-inspection ì
|
INSP - Energy code compliance | 7/23/1997 | 7/23/1997 | 7/23/1997 | P | PASS |
Russ Owen
|
|
|
07/23/97 407 -
|
INSP - Framing/Rough-in | 7/23/1997 | 7/23/1997 | 7/23/1997 | P | PART |
Russ Owen
|
|
|
07/23/97 407 - RE-INSPECTION ok to sheetrock all except for the garage fronts still need prior correc engineering at front talked with contractor 7/23/97 about this.
|
INSP - Framing/Rough-in | 7/14/1997 | 7/15/1997 | 7/15/1997 | A | FAIL |
Russ Owen
|
|
|
07/15/97 407 -
|
INSP - Footings | 6/3/1997 | 6/3/1997 | 6/3/1997 | P | PASS |
Russ Owen
|
|
|
06/03/97 407 - NO APPROVED PLAN ON SITE APPEARS TO BE OK. WORK IN PROGRESS. POURED BE FOR INSPECTION.
|