INSP - Final | 7/27/1998 | 7/27/1998 | 7/27/1998 | A | PASS |
Jim Storey
|
|
|
okay as per mike strasser/final occ given
|
Permanent Occupancy | | 7/27/1998 | 7/27/1998 | | DONE |
|
|
|
|
INSP-Final Inspection | 3/19/1998 | 3/19/1998 | 3/19/1998 | P | PASS |
Rick Jackson
|
|
|
JIM ###-#### all items corrected. occ approved
|
INSP - Final | 3/17/1998 | 3/18/1998 | 3/18/1998 | A | PASS |
Jim Storey
|
|
|
JIM SAID YOU WOULD MEET HIM TUES AT 2:00-HE WAITED UNTIL 3:30--HAD TO LEAVE--HE WILL BE THERE AT 7:00 WED AM--###-#### ok for temp pending others
|
INSP - Final | 3/17/1998 | 3/17/1998 | 3/17/1998 | P | NH |
Jim Storey
|
|
|
03/17/98 301 - jim ###-#### missed jim unable to contact him on the phone. no acess to the bldg. mov
|
INSP - Final | 3/13/1998 | 3/16/1998 | 3/16/1998 | P | FAIL |
Jim Storey
|
|
|
03/16/98 301 - jim ###-#### CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP-Final Inspection | 3/16/1998 | 3/16/1998 | 3/16/1998 | A | PART |
Rick Jackson
|
|
|
temp occ approved. smoke detector for door moved to 5 ft, retest emergency/exit lights
|
INSP-Conference | 3/2/1998 | 3/3/1998 | 3/3/1998 | P | PART |
Rick Jackson
|
|
|
JIM ###-####--OUR LADY OF THE ROSARY discussed final occ requirements
|
INSP - Framing/Rough-in | 2/9/1998 | 2/10/1998 | 2/10/1998 | A | PASS |
Jim Storey
|
|
|
02/10/98 301 - CEILING GRID--JIM ###-####--LADY OF THE ROSARY SCLG-OK SUSPENDED CEILING
|
INSP - Framing/Rough-in | 2/2/1998 | 2/2/1998 | 2/2/1998 | P | PASS |
Jim Storey
|
|
|
02/02/98 301 - SHEET ROCK SCREWING--JIM AT ###-#### GWB -OK SHEETROCK NAILING celling
|
INSP - Miscellaneous | 1/7/1998 | 1/8/1998 | 1/8/1998 | P | PASS |
Jim Storey
|
|
|
01/08/98 301 - FIRE CAULK INSPECTION s1 occ ok on a3 side
|
INSP - Miscellaneous | 12/24/1997 | 12/29/1997 | 12/29/1997 | A | CANC |
Jim Storey
|
|
|
12/29/97 301 - CATHOLIC CHURCH ONE HOUR FIREWALL AND FIRE CAULKING INSPECTION/ LATE AM WOULD BE FINE. ( WANTS APT. AT 11:03) cancled by stub,s
|
INSP-Final Inspection | 12/19/1997 | 12/19/1997 | 12/19/1997 | P | PASS |
Rick Jackson
|
|
|
hydro of sprinkler system. still need underground flush and hydro.
|
INSP - Framing/Rough-in | 12/17/1997 | 12/18/1997 | 12/18/1997 | A | PART |
Jim Storey
|
|
|
12/18/97 301 - ONE HOUR WALL occ east corner ok one side.
|
INSP - Framing/Rough-in | 10/27/1997 | 10/27/1997 | 10/27/1997 | P | PASS |
Jim Storey
|
|
|
10/27/97 301 - COLUMN grout ok
|
INSP - Conference | 10/21/1997 | 10/22/1997 | 10/22/1997 | A | PART |
Jim Storey
|
|
|
10/22/97 301 - steel detailer and engineer need to address the refab of they will not empead in to the separation wall.
|
INSP - Conference | 7/22/1997 | 7/24/1997 | 7/24/1997 | A | PASS |
Jim Storey
|
|
|
07/24/97 301 - pre job conf. ì
|
INSP - Footings | 7/22/1997 | 7/22/1997 | 7/23/1997 | P | PART |
Jim Storey
|
|
|
07/23/97 301 - SEE LETTER FOR CONDITIONS. added insp. noted.
|
INSP - Footings | 7/22/1997 | 7/22/1997 | 7/22/1997 | | PART |
Jim Storey
|
|
|
/ / 301 - placed with special insp. report pending field report ok.
|