INSP - Grading Inspection | 11/10/1997 | | 11/10/1997 | | PASS |
Rita DeYoung
|
|
|
Final grading and revegetation complete. $500.00 bond can be released.
|
INSP - Final | 9/5/1997 | 9/5/1997 | 9/5/1997 | P | PASS |
Wes Worcester
|
|
|
|
INSP - Letter of compliance | 9/5/1997 | 9/5/1997 | 9/5/1997 | P | PASS |
Wes Worcester
|
|
|
c/c issued
|
INSP - Final | 9/3/1997 | 9/3/1997 | 9/3/1997 | P | FAIL |
Wes Worcester
|
|
|
need elect and bcec not done
|
INSP - Grading Inspection | 9/3/1997 | | 9/3/1997 | | BOND |
Rita DeYoung
|
|
|
Final grading completed but revegetation not. House can receive final Letter of Compliance upon receipt of $500.00 bond, as recommended by the engineer.
|
INSP - Final | 8/29/1997 | 8/29/1997 | 8/29/1997 | P | NR |
Wes Worcester
|
|
|
need public works
|
INSP - Final | 8/28/1997 | 8/29/1997 | 8/29/1997 | A | NR |
Wes Worcester
|
|
|
|
INSP - Conference | 8/29/1997 | 8/29/1997 | 8/19/1997 | P | PASS |
Wes Worcester
|
|
|
will have p/w and plumbing done this pm
|
INSP - Energy code compliance | 7/30/1997 | 7/30/1997 | 7/30/1997 | | PASS |
Wes Worcester
|
|
|
/ / 342 -
|
INSP - Framing/Rough-in | 7/29/1997 | 7/30/1997 | 7/30/1997 | A | PASS |
Wes Worcester
|
|
|
07/29/97 342 - 7:30 apt carry over from previous day
|
INSP - Carpentry | 7/28/1997 | 7/28/1997 | 7/28/1997 | | PART |
Wes Worcester
|
|
|
/ / 342 - finishing shear, truss eng, installing windows, pt lds, stai
|
INSP - Conference | 7/28/1997 | 7/28/1997 | 7/28/1997 | | PART |
Wes Worcester
|
|
|
/ / 342 - talked to builder, will meet framers on site
|
INSP - Framing/Rough-in | 7/28/1997 | 7/28/1997 | 7/28/1997 | P | NR |
Wes Worcester
|
|
|
07/28/97 342 - met framers on site, still finishing
|
INSP - Framing/Rough-in | 7/24/1997 | 7/24/1997 | 7/24/1997 | P | NR |
Wes Worcester
|
|
|
no plans, no engineering, BCEC penetration package not started, no windows etc
|
INSP - Conference | 6/26/1997 | 6/26/1997 | 6/26/1997 | P | PASS |
Wes Worcester
|
|
|
discussed soils report with Kim
|
INSP - Conference | 6/26/1997 | 6/26/1997 | 6/26/1997 | P | PASS |
Wes Worcester
|
|
|
discussed previous c/n with Tom
|
INSP - Conference | 6/26/1997 | 6/26/1997 | 6/26/1997 | P | PASS |
Wes Worcester
|
|
|
drainage and soils discussed with builder.
|
INSP - Foundation | 6/26/1997 | 6/26/1997 | 6/26/1997 | P | NR |
Wes Worcester
|
|
|
rebar and bds not tied in place...questions on fdn plan.
|
INSP - Wall cover | 6/26/1997 | 6/26/1997 | 6/26/1997 | P | FAIL |
Wes Worcester
|
|
|
rebar and bds not tied in place.
|
INSP - Footings | 6/23/1997 | 6/23/1997 | 6/23/1997 | P | PART |
Tom Arcoraci
|
|
|
tran to 408 by 340, rec'd letter needs app plan on site
|
INSP - Footings | 6/20/1997 | 6/20/1997 | 6/20/1997 | P | FAIL |
Tom Arcoraci
|
|
|
no plan on site rebar not tied in place am insp
|
INSP - Footings | 6/13/1997 | 6/13/1997 | 6/13/1997 | P | FAIL |
|
|
|
06/13/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Foundation | 6/26/1997 | 6/26/1997 | 6/26/1996 | P | PASS |
Wes Worcester
|
|
|
entry made 9/10/97 for previous pour
|