INSP - Final | 7/11/1997 | 7/11/1997 | 7/11/1997 | P | NR |
Russ Owen
|
|
|
07/11/97 407 - need plumbing and electrical.
|
INSP - Final | 7/10/1997 | 7/10/1997 | 7/10/1997 | P | NR |
Russ Owen
|
|
|
07/10/97 407 - need plumbing and electrical final.
|
INSP - Carpentry | 6/16/1997 | 6/16/1997 | 6/16/1997 | P | PASS |
Russ Owen
|
|
|
06/16/97 407 - STAIRS
|
INSP - Framing/Rough-in | 6/13/1997 | 6/13/1997 | 6/13/1997 | P | NR |
Russ Owen
|
|
|
06/13/97 407 - FRAME REINSPECT NOT READY.
|
INSP - Energy code compliance | 6/12/1997 | 6/12/1997 | 6/12/1997 | P | PART |
Russ Owen
|
|
|
NEED THE FRAMING CORRECTIONS COMPLETED BEFORE SHEETROCK.
|
INSP - Energy code compliance | 6/11/1997 | 6/11/1997 | 6/11/1997 | P | FAIL |
Russ Owen
|
|
|
NEED VAPOR BARRIER ABOVE STAIRS.
|
INSP - Framing/Rough-in | 6/9/1997 | 6/10/1997 | 6/10/1997 | A | FAIL |
Russ Owen
|
|
|
06/10/97 407 - FRAME REINSPECT see corrections on site. first inspection had no plans.
|
INSP - Framing/Rough-in | 6/5/1997 | 6/5/1997 | 6/5/1997 | P | NR |
Russ Owen
|
|
|
06/05/97 407 - need approved plans,plumbing not approved .
|
INSP - Footings | 5/8/1997 | 5/8/1997 | 5/8/1997 | P | PASS |
Jim Storey
|
|
|
05/08/97 301 - EAR-EARLY START POURED WITHOUT INSPECTION set bach ok
|