INSP - Final | 11/25/1998 | 11/25/1998 | 11/25/1998 | P | PASS |
Jim Storey
|
|
|
11/25/98 301 - FNL -OK FINAL
|
Permanent Occupancy | | 11/25/1998 | 11/25/1998 | | DONE |
|
|
|
|
INSP-Final Inspection | 11/18/1998 | 11/19/1998 | 11/19/1998 | A | PASS |
Rick Jackson
|
|
|
DAVE...###-#### BURNS BROS occ approved
|
INSP-Sprinkler Rough-in/Hydro | 11/16/1998 | 11/16/1998 | 11/16/1998 | A | PART |
Rick Jackson
|
|
|
checked old FDC at Commerce and Broadway - still there; will have to be removed, new wallmount FDC at main building
|
INSP - Foundation | 10/7/1998 | 10/7/1998 | 10/7/1998 | | PART |
Jim Storey
|
|
|
/ / 301 - achrived specail insp report for concrete and grade compackt
|
INSP - Final | 9/16/1998 | 9/17/1998 | 9/17/1998 | A | PART |
Jim Storey
|
|
|
09/17/98 301 - temp final ok for phase two per plan.
|
INSP - Final | 8/28/1998 | 8/31/1998 | 8/31/1998 | P | PART |
Jim Storey
|
|
|
08/31/98 301 - first thing am bru ###-#### shower corridor only ok for temp.
|
INSP-Final Inspection | 8/31/1998 | 8/31/1998 | 8/31/1998 | A | PART |
Rick Jackson
|
|
|
JOEL ###-#### occ approved for corridor and shower area only in addition to phase 1 approved earlier. taco bell and office area not complete
|
INSP - Framing/Rough-in | 8/26/1998 | 8/26/1998 | 8/27/1998 | P | PART |
Jim Storey
|
|
|
08/26/98 301 - ceiling grid/bru ###-#### SCLG-OK SUSPENDED CEILING PRNDING MECH SIGN OFF OF ROUGH IN
|
INSP-Conference | 8/11/1998 | 8/11/1998 | 8/11/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - CONF WITH JOEL ON LOCATION OF EMERG SHUT OFF SWITCHES SUGGES SWITCHS
|
INSP-Sprinkler Rough-in/Hydro | 8/5/1998 | 8/6/1998 | 8/6/1998 | A | PART |
Rick Jackson
|
|
|
BRU ###-#### heads still needed in the shower/corridor area and other areas. they want to open the showers by 8/15 and will have all areas covered with heads and alarms
|
INSP - Foundation | 7/30/1998 | 7/31/1998 | 7/31/1998 | A | PART |
Jim Storey
|
|
|
07/31/98 301 - BRU ###-#### CORR-CORREC-CALL FOR REINSP WHEN COMPLETED one 20 min jamb ass. mest be to work in wall assembly.
|
INSP - Foundation | 7/24/1998 | 7/24/1998 | 7/24/1998 | P | PASS |
Jim Storey
|
|
|
07/24/98 301 - VINEAR WALL BLOCKS BRU ###-#### resubmital received and approved 301 anchors in place and approved as be can be observed.
|
INSP - Framing/Rough-in | 7/8/1998 | 7/14/1998 | 7/14/1998 | P | FAIL |
Jim Storey
|
|
|
07/14/98 301 - bru/ ###-#### CORR-CORREC-CALL FOR REINSP WHEN COMPLETED ì
|
INSP - Wall cover | 7/1/1998 | 7/1/1998 | 7/1/1998 | | PART |
Jim Storey
|
|
|
/ / 301 - sheer wall sheathing exterior ok
|
INSP - Framing/Rough-in | 3/26/1998 | 3/27/1998 | 3/27/1998 | P | PART |
|
|
|
03/27/98 333 - card signed for temp Jim to check remaining items on cn
|
INSP-Final Inspection | 3/25/1998 | 3/27/1998 | 3/27/1998 | A | PART |
Rick Jackson
|
|
|
THIS IS A FOR A TEMP OCC ON THE 1ST PHASE-BRU-###-#### generator room venting, fill pipe, recheck appliances under hood, c/n issued.
|
INSP - Framing/Rough-in | 3/20/1998 | 3/23/1998 | 3/23/1998 | A | PASS |
Jim Storey
|
|
|
03/23/98 301 - fire tunnel patch ok ceilling grid ok to cover all pre fi
|
INSP-Final Inspection | 3/20/1998 | 3/23/1998 | 3/23/1998 | A | NR |
Rick Jackson
|
|
|
final on the hoods in the kitchen bob ###-#### exhaust fans not installed, fire panel not complete
|
INSP - Framing/Rough-in | 3/19/1998 | 3/20/1998 | 3/20/1998 | P | CANC |
Jim Storey
|
|
|
03/20/98 301 - MEET WITH BRU FOR A PRE-FINAL CONFERENCE ###-####
|
INSP - Framing/Rough-in | 3/16/1998 | 3/16/1998 | 3/16/1998 | P | PART |
Jim Storey
|
|
|
03/16/98 301 - grid inspection ceiling bru ###-#### CORR-CORREC-CALL FOR REINSP WHEN COMPLETED for coridor only all but kitc area ok for tile drop.
|
INSP - Framing/Rough-in | 3/10/1998 | 3/11/1998 | 3/11/1998 | P | PASS |
Jim Storey
|
|
|
03/11/98 301 - ceilling of dishwasher room ok fo cover
|
INSP - Framing/Rough-in | 2/18/1998 | 2/19/1998 | 2/20/1998 | P | FAIL |
Jim Storey
|
|
|
02/19/98 301 - BURNS BROS--CEILING GRID--BRU ###-####
|
INSP-Supply line flush | 2/3/1998 | 2/3/1998 | 2/3/1998 | A | PASS |
Rick Jackson
|
|
|
underground flush - okay
|
INSP-Supply line flush | 2/3/1998 | 2/3/1998 | 2/3/1998 | A | PASS |
Rick Jackson
|
|
|
underground flush okay
|
INSP - Framing/Rough-in | 1/5/1998 | 1/6/1998 | 1/6/1998 | A | PASS |
Jim Storey
|
|
|
01/05/98 301 - burns Bros. FRAM-OK FRAMING GWB -OK SHEETROCK NAILING
|
INSP - Wall cover | 12/16/1997 | 12/16/1997 | 12/16/1997 | P | FAIL |
Jim Storey
|
|
|
12/16/97 301 - OTH-OTHER AGENCIES NOT APPROVED ele, plmb. coridor walls to be pre rock partitions perpendickler w/5/8 gyp/
|
INSP - Framing/Rough-in | 12/3/1997 | 12/3/1997 | 12/3/1997 | P | PART |
Jim Storey
|
|
|
12/03/97 301 - conf. ok 1 hr.const w/sprinkler subsitution defined
|
INSP - Roof | 12/1/1997 | 12/1/1997 | 12/1/1997 | P | PASS |
Jim Storey
|
|
|
12/01/97 301 - ROOF NAILING AT BURNS BROS sheer and roof cover ok
|
INSP - Framing/Rough-in | 11/17/1997 | 11/18/1997 | 11/18/1997 | A | PASS |
Jim Storey
|
|
|
11/18/97 301 - SHEER WALL AT 10:00 GWB -OK SHEETROCK NAILING
|
INSP - Framing/Rough-in | 11/13/1997 | 11/14/1997 | 11/14/1997 | A | CANC |
Jim Storey
|
|
|
11/14/97 301 - doubled up insp. due to hello systeim not working causing
|
INSP - Framing/Rough-in | 11/12/1997 | 11/13/1997 | 11/13/1997 | A | PART |
Jim Storey
|
|
|
11/13/97 301 - Scheduled by Hello! on 11/12/97 at 10:51:08. GEN -GENERAL INSPECTION recall for sheer
|
INSP - Conference | 10/14/1997 | 10/14/1997 | 10/14/1997 | | PASS |
Jim Storey
|
|
|
/ / 301 - resubmital approved
|
INSP - Footings | 9/29/1997 | 9/30/1997 | 9/30/1997 | A | PART |
Jim Storey
|
|
|
09/30/97 301 - covered by special insp.report pending41:15.
|
INSP - Foundation | 9/25/1997 | 9/26/1997 | 9/26/1997 | A | PART |
Jim Storey
|
|
|
09/26/97 301 - Scheduled by Hello! on 09/25/97 at 16:22:15. FRMS-OK FORMS-REBAR special insp to be on site at time of placment.
|
INSP - Footings | 9/24/1997 | 9/25/1997 | 9/25/1997 | A | PART |
Jim Storey
|
|
|
09/25/97 301 - covered by special insp. pending report.
|
INSP - Footings | 9/22/1997 | 9/22/1997 | 9/22/1997 | P | CANC |
Jim Storey
|
|
|
09/22/97 301 - contractor called said he would call back if he was going
|
INSP - Foundation | 9/16/1997 | 9/17/1997 | 9/17/1997 | A | PART |
Jim Storey
|
|
|
Scheduled by Hello! on 09/16/97 at 17:20:26.spec insp per 301
|
INSP - Foundation | 9/15/1997 | 9/16/1997 | 9/16/1997 | A | PART |
Jim Storey
|
|
|
09/16/97 301 - Scheduled by Hello! on 09/15/97 at 13:51:30. WIP -WORK IN PROGRESS special insp. pending report
|
INSP - Foundation | 9/12/1997 | 9/12/1997 | 9/15/1997 | P | PART |
Jim Storey
|
|
|
09/15/97 301 - covered by special insp.
|
INSP - Foundation | 9/9/1997 | 9/10/1997 | 9/10/1997 | P | PART |
Jim Storey
|
|
|
09/10/97 301 - work in progess rfi for achor bolt22 not on aproved plan
|
INSP - Footings | 9/9/1997 | 9/9/1997 | 9/9/1997 | P | FAIL |
Jim Storey
|
|
|
09/09/97 301 - covered w/o special insp. engineer of record to approve o
|