Permanent Occupancy | | 1/7/1998 | 1/7/1998 | | DONE |
|
|
|
|
INSP - Final | 1/6/1998 | 1/6/1998 | 1/6/1998 | | PASS |
|
|
|
Lacking P&Z approval otherwise ok.
|
INSP - Carpentry | 12/16/1997 | 12/16/1997 | 12/16/1997 | | PASS |
|
|
|
Landing & steps at front entry.
|
INSP - Conference | 9/17/1997 | 9/17/1997 | 9/17/1997 | P | PART |
Bob Archibald
|
|
|
Structural engineer, Dean, w/TJI faxed letter approving installation of TJI components in crawl space without proper clearance from earth.
|
INSP - Conference | 9/16/1997 | 9/16/1997 | 9/16/1997 | P | PEND |
Bob Archibald
|
|
|
Floor access cut. Framing is TJI construction and doesn't meet code for clearance from earth. Proposed mechanical ventilation approved for crawl space(to be installed and inspected at a later date).
|
INSP - Conference | 8/20/1997 | 8/19/1997 | 8/19/1997 | | PART |
|
|
|
Conference on correctiojn notice requirement #1. When vents are installed floor construction will be verified.
|
INSP - Conference | 7/26/1997 | 7/26/1997 | 7/26/1997 | | PART |
Wes Worcester
|
|
|
/ / 342 - talked at lenghth with Carl Westfall and will resolve "frame
|
INSP - Final | 7/24/1997 | 7/25/1997 | 7/26/1997 | A | PART |
Wes Worcester
|
|
|
07/25/97 342 - temp ok, c/n on site to finish several plan check items, also provide access to crawl. joists placed and covered w/o inspection
|
INSP - Final | 7/24/1997 | 7/24/1997 | 7/25/1997 | P | NR |
Wes Worcester
|
|
|
you said you would be there between 10 and 10:30 a.m.??? call ###-#### jeff, dick or carl....did not see an AM insp., no frame inspection, not to plan or plan check notes, going to see Carl W
|
INSP-Final Inspection | 7/24/1997 | 7/24/1997 | 7/24/1997 | P | PASS |
|
|
|
reinspect
|
INSP - Temporary occupancy | 7/22/1997 | 7/23/1997 | 7/23/1997 | A | NR |
Wes Worcester
|
|
|
fire has yet to sign off....? on frame and occupied 2nd floor
|
INSP-Final Inspection | 7/22/1997 | 7/23/1997 | 7/23/1997 | A | PART |
|
|
|
TEMP. OCCUPANCY, C/N ISSUED
|