INSP - Final | 11/20/1997 | 11/20/1997 | 11/21/1997 | P | PASS |
Wes Worcester
|
|
|
11/21/97 342 -
|
INSP - Final | 11/14/1997 | 11/17/1997 | 11/17/1997 | A | NR |
Wes Worcester
|
|
|
11/17/97 342 -
|
INSP - Grading Inspection | 11/18/1997 | | 11/17/1997 | | PASS |
Rita DeYoung
|
|
|
Met with Roger Smith(engineer) onsite. Landscaping 90% complete. Approved final grading.
|
INSP - Framing/Rough-in | 9/3/1997 | 9/4/1997 | 9/4/1997 | P | PASS |
Wes Worcester
|
|
|
|
INSP - Energy code compliance | 9/2/1997 | 9/3/1997 | 9/3/1997 | A | PASS |
Wes Worcester
|
|
|
|
INSP - Framing/Rough-in | 9/2/1997 | 9/3/1997 | 9/3/1997 | A | PART |
Wes Worcester
|
|
|
10:30 am on site....ok except eng for hold downs
|
INSP - Energy code compliance | 8/29/1997 | 9/2/1997 | 9/2/1997 | P | NR |
Wes Worcester
|
|
|
not finished
|
INSP - Framing/Rough-in | 8/29/1997 | 9/2/1997 | 9/2/1997 | P | NR |
Wes Worcester
|
|
|
REINSPECTION c/n blew away, no eng on site
|
INSP - Framing/Rough-in | 8/28/1997 | 8/28/1997 | 8/28/1997 | P | FAIL |
Wes Worcester
|
|
|
THEY WILL SUPPLY YOU WITH ENGINEERING REPORT REGARDING SHEAR PANEL INSPECTION AND WINDOW CHANGES....truss eng, garage hold downs etc
|
INSP - Conference | 8/22/1997 | 8/22/1997 | 8/22/1997 | | PASS |
Wes Worcester
|
|
|
/ / 342 - called Bob re Ryan homes and 2799 Woodview
|
INSP - Framing/Rough-in | 8/21/1997 | 8/22/1997 | 8/22/1997 | A | NR |
Wes Worcester
|
|
|
08/22/97 342 - plumbing has failed, shr walls covered
|
INSP - Footings | 6/10/1997 | 6/11/1997 | 6/11/1997 | P | PASS |
|
|
|
06/11/97 333 - POURING AROUND 3 P.M. footing ok
|