Permanent Occupancy | | 5/20/1998 | 5/20/1998 | | DONE |
|
|
|
|
Permanent Occupancy | | 5/19/1998 | 5/19/1998 | | DONE |
|
|
|
|
INSP-Final Inspection | 5/14/1998 | 5/14/1998 | 5/14/1998 | P | FAIL |
Rick Jackson
|
|
|
FDC in wrong location. system monitored and tested okay. emergency lights okay
|
INSP-Final Inspection | 5/11/1998 | 5/13/1998 | 5/11/1998 | P | |
Rick Jackson
|
|
|
###-####
|
INSP - Framing/Rough-in | 5/7/1998 | 5/8/1998 | 5/8/1998 | A | PASS |
Jim Storey
|
|
|
05/08/98 301 - SCLG-OK SUSPENDED CEILING
|
INSP - Framing/Rough-in | 5/5/1998 | 5/6/1998 | 5/6/1998 | P | FAIL |
Jim Storey
|
|
|
05/06/98 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 3/31/1998 | 4/1/1998 | 4/1/1998 | P | PASS |
Jim Storey
|
|
|
04/01/98 301 - FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 3/18/1998 | 3/19/1998 | 3/19/1998 | A | NR |
Tom Arcoraci
|
|
|
03/19/98 408 - MEINEKE MUFFLER--MARK ###-#### need app plans and eng for changes
|
INSP - Framing/Rough-in | 3/9/1998 | 3/10/1998 | 3/10/1998 | A | PART |
Jim Storey
|
|
|
03/09/98 301 - MARK ###-#### MEINEKE MUFFLER WIP -WORK IN PROGRESS strap on joist for cantalever ok
|
INSP - Conference | 2/26/1998 | 2/26/1998 | 2/26/1998 | | PASS |
Jim Storey
|
|
|
/ / 301 - APPROVED RESUBMITTAL AND ARCHIVED DOCUMENT.
|
INSP - Miscellaneous | 1/27/1998 | 1/28/1998 | 1/28/1998 | P | PASS |
Jim Storey
|
|
|
01/28/98 301 - SPECIAL INSPECTION FOR STEEL DECK AND JOIST--PUDDLE WELD ###-#### WELDING INPROGESS DECK WELDS SPACING AND DIA OK PENDING SPECIAL INSP.UPO COMPLETION OF WELDING APROX 400 TODAY/ PENDING REPORT.
|
INSP - Miscellaneous | 1/7/1998 | 1/8/1998 | 1/8/1998 | P | PART |
Jim Storey
|
|
|
01/08/98 301 - pouring grout at 12:30 covered by special insp. pending report.
|
INSP - Miscellaneous | 1/6/1998 | 1/7/1998 | 1/7/1998 | A | CANC |
Jim Storey
|
|
|
01/06/98 301 - cancled by contractor
|
INSP - Miscellaneous | 1/2/1998 | 1/5/1998 | 1/5/1998 | P | PART |
Jim Storey
|
|
|
01/05/98 301 - POURING GROUT AT 1:00--MEINEKE MUFFLER covered by special insp. pending report
|
INSP - Framing/Rough-in | 12/30/1997 | 1/2/1998 | 1/2/1998 | A | PASS |
Russ Owen
|
|
|
01/02/98 407 - masonry contractor,said strata has approved the pour.spec
|
INSP - Foundation | 12/30/1997 | 12/30/1997 | 12/30/1997 | P | PART |
Jim Storey
|
|
|
12/30/97 301 - ouring grout at 1:30 Strata will be there pending report
|
INSP - Foundation | 12/2/1997 | 12/3/1997 | 12/3/1997 | P | PASS |
Jim Storey
|
|
|
12/03/97 301 - MEINEKE FDN -OK FOUNDATION
|
INSP - Footings | 12/1/1997 | 12/2/1997 | 12/2/1997 | A | PASS |
Jim Storey
|
|
|
12/02/97 301 - MEINEKE MUFFLER FRMS-OK FORMS-REBAR
|