INSP - Final | 1/5/1998 | 1/5/1998 | 1/5/1998 | P | PASS |
|
|
|
01/05/98 338 - c/n removed FNL -OK FINAL LCI-LETTER OF COMPLIANCE ISSUED 014294
|
INSP - Final | 1/2/1998 | 1/2/1998 | 1/2/1998 | P | NH |
Jim Sly
|
|
|
01/02/98 316 - No Access...left note.
|
INSP - Final | 12/31/1997 | 12/31/1997 | 12/31/1997 | P | FAIL |
|
|
|
12/31/97 338 - WORK NOT COMPLETE 330 PM
|
INSP - Final | 12/31/1997 | 12/31/1997 | 12/31/1997 | | FAIL |
|
|
|
/ / 338 - CORRECTIONS NOT COMPLETE
|
INSP - Final | 12/29/1997 | 12/30/1997 | 12/30/1997 | A | NR |
|
|
|
12/30/97 338 - verbal c/n
|
INSP - Framing/Rough-in | 9/5/1997 | 9/5/1997 | 9/5/1997 | P | PASS |
|
|
|
09/05/97 338 - c/n removed FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 9/4/1997 | 9/5/1997 | 9/4/1997 | A | FAIL |
|
|
|
09/04/97 338 - OK TO INSULATE ONLY C/N ISSUED
|
INSP - Wall cover | 8/14/1997 | 8/14/1997 | 8/14/1997 | P | PASS |
|
|
|
08/14/97 338 - nailing of the prop line 1-hour wall at the attic area ok
|
INSP - Footings | 7/14/1997 | 7/14/1997 | 7/14/1997 | P | PASS |
|
|
|
07/14/97 338 - FTG -OK FOOTING
|
INSP - Foundation | 7/14/1997 | 7/14/1997 | 7/14/1997 | | PASS |
|
|
|
/ / 338 - FDN -OK FOUNDATION ufer in place
|