INSP - Final | 6/1/1998 | 6/1/1998 | 6/1/1998 | P | PASS |
Carl Dependahl
|
|
|
card to cont. ok for l/c
|
INSP - Framing/Rough-in | 6/1/1998 | 6/1/1998 | 6/1/1998 | P | PASS |
Carl Dependahl
|
|
|
c/n ok, mech ok per alan
|
INSP - Final | 5/20/1998 | 5/22/1998 | 5/22/1998 | P | FAIL |
Carl Dependahl
|
|
|
final/ ###-#### ALBERTSONS LATE PM ...need health signature, verify hood/w/Alan H
|
INSP - Framing/Rough-in | 4/24/1998 | 4/24/1998 | 4/24/1998 | P | PART |
Carl Dependahl
|
|
|
NO INSP, CONF W/ GIL OF ESI
|
INSP - Framing/Rough-in | 4/8/1998 | 4/8/1998 | 4/8/1998 | P | FAIL |
Carl Dependahl
|
|
|
4:00...show info for cooker...need hood?
|
INSP - Framing/Rough-in | 4/6/1998 | 4/7/1998 | 4/7/1998 | P | NR |
Carl Dependahl
|
|
|
albertsons\\###-#### gil with ESI...spoke w/ gill, need elec, plbg ok prior, will recall
|
INSP - Framing/Rough-in | 3/27/1998 | 3/27/1998 | 3/27/1998 | A | PART |
Carl Dependahl
|
|
|
suspended partitions at deli
|
INSP - Framing/Rough-in | 3/20/1998 | 3/20/1998 | 3/20/1998 | A | FAIL |
Carl Dependahl
|
|
|
conf w/ joe tawney, cont stated he'd signed off shaft. keep c/n will chk plan, etc.
|
INSP - Framing/Rough-in | 3/20/1998 | 3/19/1998 | 3/19/1998 | A | NR |
Carl Dependahl
|
|
|
need to chk shaft, cont.not onsite
|
INSP-Final Inspection | 3/16/1998 | 3/17/1998 | 3/17/1998 | A | PASS |
Joe Tawney
|
|
|
03/17/98 406 - bill ###-#### FINAL OK FOR CERT OF COMPLETION ì
|
INSP-Final Inspection | 3/13/1998 | 3/16/1998 | 3/13/1998 | A | CANC |
Joe Tawney
|
|
|
03/16/98 406 - 8:30 as per 406 bill ###-#### INSP CANCELLED BY CONTRACTOR
|
INSP-Sprinkler Rough-in/Hydro | 3/10/1998 | 3/12/1998 | 3/12/1998 | A | FAIL |
Joe Tawney
|
|
|
03/12/98 406 - bill ###-#### as per you will met at 8:00 am - fire suppr TEST OF ANSUL SYSTEM ON HOOD FAIL DID NOT SHUT OFF ALL ELECTRICAL
|
INSP - Framing/Rough-in | 3/4/1998 | 3/4/1998 | 3/4/1998 | P | PART |
Carl Dependahl
|
|
|
SUSPENDED PARTITION AT DELI OK PER RESUB DETAIL...NEED TO INSP HOOD SHAFT, WORK NOT DONE THAT AREA.
|
INSP - Wall cover | 2/19/1998 | 2/19/1998 | 2/19/1998 | P | PART |
Carl Dependahl
|
|
|
SUSPENDED WALL--GILL ###-####...OK TO COVER 1 SIDE ONLY, STILL NEED 1HR SHAFT; ARCH'S DETAIL TO BE FAXED & ONSITE
|
INSP - Framing/Rough-in | 2/19/1998 | 2/18/1998 | 2/18/1998 | A | NR |
Carl Dependahl
|
|
|
KEEP C/N, SPOKE W/ JIM OF PSI RE ASBESTOS REMOVAL: HAS MANIFEST....
|
INSP - Framing/Rough-in | 2/13/1998 | 2/13/1998 | 2/13/1998 | A | PART |
Carl Dependahl
|
|
|
REC'D PRELIMINARY REPORT FOR ASBESTOS VERIFICATION (REMOVAL) & DETAIL FOR SUSPENDED PARTITIONS, NEED ARCH'S OK. GAVE CONT. FIRE PLAN CHK REPORT, DISCUSSED INSP'S FOR HOOD & SHAFT. KEEP C/N
|
INSP - Framing/Rough-in | 2/13/1998 | 2/12/1998 | 2/12/1998 | P | PART |
Carl Dependahl
|
|
|
chk w.i.p. keep c/n. ok to continue...will need arch's ok
|
INSP - Framing/Rough-in | 2/12/1998 | 2/11/1998 | 2/11/1998 | P | PART |
Carl Dependahl
|
|
|
NOT FRAME INSP...CONF W/ CONTRACTOR, CREW WORKS NITES...TOLD OK TO CONTINUE WORK, 1-SIDE ONLY...CONTACT ARCH.
|
INSP - Framing/Rough-in | 2/11/1998 | 2/11/1998 | 2/11/1998 | P | FAIL |
Carl Dependahl
|
|
|
GILL-###-####...C/N: SUSPENDED PARTITIONS NOT PER DETAIL, NEED PROOF OF PROPER ASBESTOS ABATEMENT & REMOVAL PER SPECS. ARCH. TO OK AS BUILT OR??
|
INSP - Framing/Rough-in | 2/9/1998 | 2/9/1998 | 2/9/1998 | P | NR |
Carl Dependahl
|
|
|
VIDEO DEPT--CARD AT MANAGER TERMINAL--GILL ###-####...NEED PLAN, OTHER INSPS, LEFT NOTE, CALLED GILL, SPOKE W/ ALBERTSONS ...NO INSP DONE
|
INSP - Framing/Rough-in | 2/10/1998 | 2/6/1998 | 2/6/1998 | P | NR |
Carl Dependahl
|
|
|
STOPPED BY JOB, NO PERMIT POSTED, ETC, LEFT NOTE.
|