INSP - Final | 3/25/1998 | 3/26/1998 | 3/26/1998 | A | PASS |
|
|
|
03/26/98 338 - FNL -OK FINAL SIGNED THE FINAL PERM COL OF THE OCC REQ CA
|
INSP-Final Inspection | 3/24/1998 | 3/25/1998 | 3/25/1998 | A | PASS |
Joe Tawney
|
|
|
03/25/98 406 - ###-#### pager for Renny REINSP OK FOR CERT OF COMPLETION
|
INSP - Final | 3/20/1998 | 3/20/1998 | 3/20/1998 | P | PART |
|
|
|
03/20/98 338 - RENNY WILL CALL YOU AFTER JOE LEAVES--RENNY ###-####
|
INSP-Final Inspection | 3/20/1998 | 3/20/1998 | 3/20/1998 | P | PASS |
Joe Tawney
|
|
|
03/20/98 406 - RENNY ###-#### REINSP ON SHELL OK FOR TEMP BOLLARDS FOR GAS & ELECT PAINT CURBS
|
INSP-Final Inspection | 3/17/1998 | 3/19/1998 | 3/19/1998 | A | FAIL |
Joe Tawney
|
|
|
03/19/98 406 - WOULD LIKE AT 10:00--TRACEY ###-#### FINAL ON SHELL FAIL BLDG ADDRESS BOLLARDS FOR GAS & ELECT PAINT CURBS
|
INSP-Final Inspection | 3/13/1998 | 3/16/1998 | 3/16/1998 | A | NR |
Joe Tawney
|
|
|
03/16/98 406 - PLEASE MEET TRACY AT 11:00--###-#### FINAL ON SHELL NOT READY
|
INSP-Conference | 3/11/1998 | 3/11/1998 | 3/11/1998 | P | PASS |
Joe Tawney
|
|
|
03/12/98 406 - BOISE OFFICE EQUIPMENT--RENNE PAGER ###-#### CONF ON FIRE LANE CURB STRIPING
|
INSP-Supply line flush | 2/2/1998 | 2/2/1998 | 2/2/1998 | P | PART |
Joe Tawney
|
|
|
02/02/98 406 - 1:30-prior arrangement tracy ###-#### OK ON UNDERGROUND FLUSH AND ROUGH IN EXCEPT RISERS
|
INSP - Framing/Rough-in | 1/20/1998 | 1/20/1998 | 1/20/1998 | P | PASS |
|
|
|
01/20/98 338 - roof welding on the roof deck east from 1- line
|
INSP - Foundation | 12/19/1997 | 12/22/1997 | 12/22/1997 | A | PASS |
|
|
|
12/22/97 338 - BOISE EQUIPMENT tie in slabs at the perimeter
|
INSP - Footings | 12/2/1997 | 12/3/1997 | 12/4/1997 | P | PASS |
|
|
|
12/03/97 338 - FRMS-OK FORMS-REBAR
|
INSP - Footings | 11/17/1997 | 11/18/1997 | 11/18/1997 | A | PART |
|
|
|
11/18/97 333 - north and east walls and footings pending special insp re
|
INSP - Footings | 11/12/1997 | 11/13/1997 | 11/13/1997 | A | PASS |
|
|
|
Late morning, please made ok with sp insp approval
|
INSP - Miscellaneous | 10/28/1997 | 10/29/1997 | 10/29/1997 | A | PASS |
|
|
|
SLAB FLOOR--INSIDE BLDGMAD EOK WITH SP INSP APPROVAL
|
INSP - Footings | 10/22/1997 | 10/22/1997 | 10/22/1997 | P | PASS |
|
|
|
1/2 of the col footing pads are ok to pour with sp isp approval
|
INSP - Footings | 10/21/1997 | 10/21/1997 | 10/21/1997 | P | NR |
|
|
|
not ready r-bar not placed compaction failed
|