INSP - Final | 6/9/1998 | 6/10/1998 | 6/10/1998 | P | PASS |
Jim Storey
|
|
|
06/10/98 301 - FNL -OK FINAL ok for lc routed
|
INSP - Final | 6/2/1998 | 6/2/1998 | 6/2/1998 | P | NR |
Jim Storey
|
|
|
06/02/98 301 - c/n pending
|
INSP - Final | 5/26/1998 | 5/26/1998 | 5/26/1998 | P | PART |
Jim Storey
|
|
|
05/26/98 301 - pending special insp. letter of completion. recall for si
|
INSP-Final Inspection | 4/7/1998 | 4/13/1998 | 4/13/1998 | A | PASS |
Rick Jackson
|
|
|
rob puckett ###-#### rescheduled from 4/09 occ approved
|
INSP - Framing/Rough-in | 10/31/1997 | 10/31/1997 | 10/31/1997 | | PASS |
Jim Storey
|
|
|
/ / 301 - FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 10/31/1997 | 10/31/1997 | 10/31/1997 | | PASS |
Jim Storey
|
|
|
/ / 301 - FRAM-OK FRAMING
|
INSP - Footings | 10/2/1997 | 10/2/1997 | 10/2/1997 | | FAIL |
Jim Storey
|
|
|
/ / 301 - ENGINEERING REQUIRED FOR PIPE IN FT.
|
INSP - Footings | 10/1/1997 | 10/2/1997 | 10/2/1997 | P | CANC |
Russ Owen
|
|
|
10/02/97 407 - Scheduled by Hello! on 10/01/97 at 17:29:01. this is transfered to jim s.
|