INSP - Final | 11/23/1998 | 11/24/1998 | 11/24/1998 | A | PASS |
Wes Worcester
|
|
|
11/24/98 342 - BRIAN ###-####
|
INSP - Framing/Rough-in | 8/13/1998 | 8/13/1998 | 8/13/1998 | P | CANC |
Wes Worcester
|
|
|
brian ###-####
|
INSP - Energy code compliance | 2/12/1998 | 2/11/1998 | 2/11/1998 | P | PASS |
Carl Dependahl
|
|
|
HI-R REMOVED AT CONCEALED SPACES; INSUL OK
|
INSP - Framing/Rough-in | 2/11/1998 | 2/11/1998 | 2/11/1998 | P | PASS |
Carl Dependahl
|
|
|
BRIAN ###-#### ENG'G OK
|
INSP - Framing/Rough-in | 2/9/1998 | 2/9/1998 | 2/9/1998 | P | FAIL |
Carl Dependahl
|
|
|
BRIAN ###-####...COMPLETE PER ENG'G & PREVIOUS C/N
|
INSP - Carpentry | 2/4/1998 | 2/4/1998 | 2/4/1998 | P | PASS |
Carl Dependahl
|
|
|
STRAPS TO BE INSTALLED AT SHEAR PANELS PER ENG'R...OK TO BEGIN INSULATION. KEEP C/N
|
INSP - Conference | 1/30/1998 | 1/30/1998 | 1/30/1998 | A | PASS |
Carl Dependahl
|
|
|
W/ FRAMER AT SITE, NEED ENG'G
|
INSP - Conference | 1/29/1998 | 1/29/1998 | 1/29/1998 | A | PASS |
Carl Dependahl
|
|
|
W/ BRIAN, NEED ENG'S RED LINE PLAN FOR INSP
|
INSP - Framing/Rough-in | 1/28/1998 | 1/29/1998 | 1/29/1998 | P | FAIL |
Carl Dependahl
|
|
|
brian ###-####...2ND C/N, NEED ENG'S PLAN OR RESUBMITTAL/ APPROVAL & COMPLETE ALL OTHER ITEMS. APPEARS TO REQ. INTERIOR SIDE SHEAR PANELS. NEED SPECIFIC LOCATIONS AND TALL WALL DESIGN.
|
INSP - Conference | 1/29/1998 | 1/28/1998 | 1/28/1998 | A | PASS |
Carl Dependahl
|
|
|
W/ FRAMER RE C/N; NEED ALL R/I'S, ENG'D REDLINE PLAN ONSITE, ALL FIREBLOCKS AND AIR SEAL IN PLACE ETC
|
INSP - Framing/Rough-in | 1/27/1998 | 1/27/1998 | 1/27/1998 | P | FAIL |
Carl Dependahl
|
|
|
brian ###-####; NEED HTG OK; REQUESTED ENG'D PLAN ONSITE; WROTE GENERIC CORRECTION, NOT COMPLETE FRAME INSP. NO AIR SEAL DONE.
|
INSP - Footings | 9/29/1997 | 9/30/1997 | 9/30/1997 | A | PART |
Carl Dependahl
|
|
|
part, footings only, bar not in place....looks ok
|