INSP - Final | 11/17/1998 | 11/18/1998 | 11/19/1998 | A | PASS |
Russ Owen
|
|
|
11/19/98 407 - Letter from structural engineer in regards to Special Ins
|
INSP - Final | 11/9/1998 | 11/9/1998 | 11/9/1998 | P | FAIL |
Russ Owen
|
|
|
Left a correction notice at the site next to job card,need to have 2 unresolved items addressed by engineer, noted on final letter from special inspection.
|
INSP - Framing/Rough-in | 10/30/1998 | 11/2/1998 | 11/2/1998 | A | FAIL |
|
|
|
11/02/98 333 - given to russ
|
INSP-Final Inspection | 10/30/1998 | 10/30/1998 | 11/2/1998 | P | PASS |
Tom Arcoraci
|
|
|
10/30/98 408 - blair ###-#### digital pager for fire insp
|
INSP-Final Inspection | 10/30/1998 | 10/30/1998 | 10/30/1998 | P | PASS |
Rick Jackson
|
|
|
occ approved
|
INSP - Final | 10/29/1998 | 10/29/1998 | 10/29/1998 | P | FAIL |
Russ Owen
|
|
|
need fire life safety also special inspection letter of acceptance.
|
INSP - Final | 10/29/1998 | 10/29/1998 | 10/29/1998 | P | PART |
Russ Owen
|
|
|
need fire life safety,special inspection close-out.
|
INSP-Final Inspection | 10/29/1998 | 10/29/1998 | 10/29/1998 | A | FAIL |
Rick Jackson
|
|
|
remove tape from heads, remove gas pipe from sprinkler piping, change head in generator room
|
INSP-Final Inspection | 9/14/1998 | 9/14/1998 | 9/14/1998 | A | FAIL |
Rick Jackson
|
|
|
generator venting, fill line at openings, not tested (15 min) on hour meter; address; extinguisher tags
|
INSP-Sprinkler Rough-in/Hydro | 9/11/1998 | 9/14/1998 | 9/14/1998 | A | PASS |
Rick Jackson
|
|
|
BLAIR ###-#### PAGER tested sprinkler system - okay
|
INSP - Final | 9/8/1998 | 9/9/1998 | 9/9/1998 | P | CANC |
Russ Owen
|
|
|
09/09/98 407 - blair ###-#### pager/CANCEL WILL RESCHEDULE PER BLAIR
|
INSP - Framing/Rough-in | 7/14/1998 | 7/15/1998 | 7/15/1998 | P | PART |
Russ Owen
|
|
|
07/15/98 407 - corrections in truck bay areas suspended support for the
|
INSP-Sprinkler Rough-in/Hydro | 7/14/1998 | 7/15/1998 | 7/15/1998 | P | PASS |
Rick Jackson
|
|
|
rick 893--0091 hydro okay (dry and wet systems)
|
INSP-Supply line flush | 7/2/1998 | 7/6/1998 | 7/6/1998 | A | PART |
Joe Tawney
|
|
|
07/06/98 406 - rick ###-#### OK ON UNDERGROUND FLUSH ì
|
INSP - Energy code compliance | 6/8/1998 | 6/9/1998 | 6/9/1998 | A | PART |
Russ Owen
|
|
|
06/09/98 407 - need some additional fire stoping.
|
INSP - Framing/Rough-in | 6/1/1998 | 6/2/1998 | 6/2/1998 | A | CANC |
Russ Owen
|
|
|
06/02/98 407 - trans to 301.
|
INSP - Energy code compliance | 6/1/1998 | 6/1/1998 | 6/1/1998 | P | PASS |
Russ Owen
|
|
|
06/01/98 407 - garage ok to sheetrock.
|
INSP-Sprinkler Rough-in/Hydro | 5/29/1998 | 6/1/1998 | 6/1/1998 | P | PART |
Rick Jackson
|
|
|
rick fry/ ###-#### dry system in living quarters only okay to cover.
|
INSP - Framing/Rough-in | 5/21/1998 | 5/22/1998 | 5/22/1998 | A | PART |
Russ Owen
|
|
|
05/22/98 407 - storage building only ok to insulate.
|
INSP - Framing/Rough-in | 5/18/1998 | 5/19/1998 | 5/19/1998 | A | PART |
Jim Storey
|
|
|
05/19/98 301 - ROOF NAILLING OK FOR COVER / TRUSS C/N POSTED FOR REPAIR
|
INSP - Framing/Rough-in | 5/8/1998 | 5/8/1998 | 5/8/1998 | P | PART |
Russ Owen
|
|
|
05/08/98 407 - partial inspection.nailing ok. will add a few more in som removed 8,s from hold downs and replace with 16's.
|
INSP - Foundation | 4/30/1998 | 5/1/1998 | 5/1/1998 | P | PASS |
Russ Owen
|
|
|
this should be the final pour at the truck bays.
|
INSP - Foundation | 4/29/1998 | 4/30/1998 | 4/30/1998 | A | PART |
Wes Worcester
|
|
|
04/30/98 342 - 10:30 AS PER 407-GROUT POURed... according to super speci earlier and Russ had looked at splices
|
INSP - Foundation | 4/27/1998 | 4/28/1998 | 4/29/1998 | P | PART |
Russ Owen
|
|
|
04/28/98 407 - pouring at time of inspection exposed sections look good.special insp on site said rest looked good.
|
INSP - Concrete | 4/24/1998 | 4/27/1998 | 4/27/1998 | A | PART |
Jim Storey
|
|
|
04/27/98 301 - first lift of massonary wall ok special insp on site pend
|
INSP - Concrete | 4/23/1998 | 4/24/1998 | 4/24/1998 | P | CANC |
Russ Owen
|
|
|
04/24/98 407 - contractor called to cancell.
|
INSP - Concrete | 4/2/1998 | 4/3/1998 | 4/3/1998 | A | PART |
Russ Owen
|
|
|
04/03/98 407 - walls ok. Also special inspector on site.
|
INSP - Concrete | 3/30/1998 | 3/31/1998 | 3/31/1998 | A | PART |
Russ Owen
|
|
|
03/31/98 407 - special inspection required ,I did inspection of other po
|
INSP - Foundation | 3/26/1998 | 3/27/1998 | 3/27/1998 | A | PART |
Russ Owen
|
|
|
03/27/98 407 - Inspected what was ready at the north side still a section at the rear that needs to be completed,Special inspector has not yet been to site,told contractor not pour untill special inspectors approval.
|