Permit Information
Permit NumberBLD97-02769
StatusExpired
Name BOISE CITY FIRE DEPARTMENT
Site Address 3240 STATE HWY 21
Project NameFIRE STATION #12
Customer Number 
ePlanReviewNo
Description
BOISE CITY FIRE STATION #12 * TO CONSTRUCT A NEW 1-STORY 7,437 SQ. FT.,TYPE V-N WOOD FRAMED, FULLY FIRE SPRRINKLERED FIRE STATION. OTHER WORK INCLUDES A 720 SQ. FT. NON-RATED WOOD FRAMED STORAGE BUILDING AND ALL RELATED SITE WORK INCLUDING TRAFFIC SIGNALS ON HIGHWAY 21 (GOWEN RD.) CU-28-97 PC#607-97 FIRE SPRINKLERS USED FOR AREA.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final11/17/199811/18/199811/19/1998APASS
DetailsRuss Owen
11/19/98 407 - Letter from structural engineer in regards to Special Ins
INSP - Final11/9/199811/9/199811/9/1998PFAIL
DetailsRuss Owen
Left a correction notice at the site next to job card,need to have 2 unresolved items addressed by engineer, noted on final letter from special inspection.
INSP - Framing/Rough-in10/30/199811/2/199811/2/1998AFAIL
Details
11/02/98 333 - given to russ
INSP-Final Inspection10/30/199810/30/199811/2/1998PPASS
DetailsTom Arcoraci
10/30/98 408 - blair ###-#### digital pager for fire insp
INSP-Final Inspection10/30/199810/30/199810/30/1998PPASS
DetailsRick Jackson
occ approved
INSP - Final10/29/199810/29/199810/29/1998PFAIL
DetailsRuss Owen
need fire life safety also special inspection letter of acceptance.
INSP - Final10/29/199810/29/199810/29/1998PPART
DetailsRuss Owen
need fire life safety,special inspection close-out.
INSP-Final Inspection10/29/199810/29/199810/29/1998AFAIL
DetailsRick Jackson
remove tape from heads, remove gas pipe from sprinkler piping, change head in generator room
INSP-Final Inspection9/14/19989/14/19989/14/1998AFAIL
DetailsRick Jackson
generator venting, fill line at openings, not tested (15 min) on hour meter; address; extinguisher tags
INSP-Sprinkler Rough-in/Hydro9/11/19989/14/19989/14/1998APASS
DetailsRick Jackson
BLAIR ###-#### PAGER tested sprinkler system - okay
INSP - Final9/8/19989/9/19989/9/1998PCANC
DetailsRuss Owen
09/09/98 407 - blair ###-#### pager/CANCEL WILL RESCHEDULE PER BLAIR
INSP - Framing/Rough-in7/14/19987/15/19987/15/1998PPART
DetailsRuss Owen
07/15/98 407 - corrections in truck bay areas suspended support for the
INSP-Sprinkler Rough-in/Hydro7/14/19987/15/19987/15/1998PPASS
DetailsRick Jackson
rick 893--0091 hydro okay (dry and wet systems)
INSP-Supply line flush7/2/19987/6/19987/6/1998APART
DetailsJoe Tawney
07/06/98 406 - rick ###-#### OK ON UNDERGROUND FLUSH ì
INSP - Energy code compliance6/8/19986/9/19986/9/1998APART
DetailsRuss Owen
06/09/98 407 - need some additional fire stoping.
INSP - Framing/Rough-in6/1/19986/2/19986/2/1998ACANC
DetailsRuss Owen
06/02/98 407 - trans to 301.
INSP - Energy code compliance6/1/19986/1/19986/1/1998PPASS
DetailsRuss Owen
06/01/98 407 - garage ok to sheetrock.
INSP-Sprinkler Rough-in/Hydro5/29/19986/1/19986/1/1998PPART
DetailsRick Jackson
rick fry/ ###-#### dry system in living quarters only okay to cover.
INSP - Framing/Rough-in5/21/19985/22/19985/22/1998APART
DetailsRuss Owen
05/22/98 407 - storage building only ok to insulate.
INSP - Framing/Rough-in5/18/19985/19/19985/19/1998APART
DetailsJim Storey
05/19/98 301 - ROOF NAILLING OK FOR COVER / TRUSS C/N POSTED FOR REPAIR
INSP - Framing/Rough-in5/8/19985/8/19985/8/1998PPART
DetailsRuss Owen
05/08/98 407 - partial inspection.nailing ok. will add a few more in som removed 8,s from hold downs and replace with 16's.
INSP - Foundation4/30/19985/1/19985/1/1998PPASS
DetailsRuss Owen
this should be the final pour at the truck bays.
INSP - Foundation4/29/19984/30/19984/30/1998APART
DetailsWes Worcester
04/30/98 342 - 10:30 AS PER 407-GROUT POURed... according to super speci earlier and Russ had looked at splices
INSP - Foundation4/27/19984/28/19984/29/1998PPART
DetailsRuss Owen
04/28/98 407 - pouring at time of inspection exposed sections look good.special insp on site said rest looked good.
INSP - Concrete4/24/19984/27/19984/27/1998APART
DetailsJim Storey
04/27/98 301 - first lift of massonary wall ok special insp on site pend
INSP - Concrete4/23/19984/24/19984/24/1998PCANC
DetailsRuss Owen
04/24/98 407 - contractor called to cancell.
INSP - Concrete4/2/19984/3/19984/3/1998APART
DetailsRuss Owen
04/03/98 407 - walls ok. Also special inspector on site.
INSP - Concrete3/30/19983/31/19983/31/1998APART
DetailsRuss Owen
03/31/98 407 - special inspection required ,I did inspection of other po
INSP - Foundation3/26/19983/27/19983/27/1998APART
DetailsRuss Owen
03/27/98 407 - Inspected what was ready at the north side still a section at the rear that needs to be completed,Special inspector has not yet been to site,told contractor not pour untill special inspectors approval.