Permit NumberBLD97-02860
StatusFinaled
Name MICRON TECH
Site Address 8000 S FEDERAL WAY
Project NameMIC(#26) MARLIN LOOP
Customer Number 
ePlanReviewNo
Description
MICRON BUILDING #26 MARLIN COOLING LOOP (PROJECT #2020) * TO CONSTRUCT A NEW 20'X40' (800 SQ. FT.) STEEL MECHANICAL PLATFORM AND WALKWAY SUPPORTED BY THE EXISTING ROOF STRUCTURE. THIS SECOND FLOOR STRUCTURE IS BEING CONSTRUCTED IN PREPARATION FOR THE INSTALLATION OF NEW PROCESSING EQUIPMENT. THE NEW STEEL EQUIPMENT PLATFORM IS BEING CONSTRUCTED AT THE SECOND FLOOR LEVEL OF BUILDING #26 BETWEEN GRID LINES C & D AND GRID LINES 8 & 9. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED REQUIREMENT LIST. PC#619-97/JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final4/14/19984/15/19984/15/1998PPART
DetailsJim Storey
04/15/98 301 - FNL -OK FINAL pending occ card is regenarated and other i
INSP-Final Inspection4/14/19984/15/19984/15/1998PNR
DetailsRick Jackson
MATT ###-####-WILL MEET YOU IN BLDG 25 didn't have occ card available - not sure if fire is required for sign-off.
INSP - Framing/Rough-in3/17/19983/19/19983/20/1998AFAIL
DetailsJim Storey
03/20/98 301 - MATT 90315#--BLDG 26 engineering and approved plan not avalible.