Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD97-02948
StatusExpired
Name MK PLAZA 1 (6TH FL & BASEMENT)
Site Address 400 S BROADWAY AVE
Project NameMK-PLAZA I
Customer Number 
ePlanReviewNo
Description
(MK PLAZA I - BUILDING UPGRADE) The fire sprinkler system is used to partially resolve life safety concerns about the existing atrium. To complete Phase I of a 6 phase project to modify an existing building to comply with the smoke management recommendations outlined in a report dated July 25, 1997 prepared by a consultant mechanical engineer. On the 6th floor, work includes installing a fire sprinkler system, installing smoke containment on the elevator doors, upgrading the 1-hr corridor "smoke barrier" where necessary, installing smoke and smoke/fire dampers, and modifying the alarm system. In the basement, work includes installing a new fire line, installing a new fire pump, modifying the existing fire sprinkler system, upgrading the 1-hr corridor "smoke barrier" where necessary, and modifying the fire alarm system. Work shall comply with the approved drawings and specifications, the smoke management engineer's recommendations, and plan check conditions on file. The fire sprinkler system shall comply with NFPA 13 as regulated by the Fire Department. Each future phase remodel requires a separate permit. The entire project, including future work, is approved to be in accordance with 1994 codes and standards. PC-629-97 **CJW** (1-27-99) A NEW PROJECT PHASING SCHEDULE WAS APPROVED. SMOKE/FIRE DAMPERS ARE NOT BEING INSTALLED UNDER THIS PERMIT. THEY WILL BE INSTALLED DURING A FUTURE CONSTRUCTION PHASE.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final2/5/19992/9/19992/9/1999APASS
Details
02/09/99 338 - made ok l/c issued # 16397
INSP - Final2/1/19992/2/19992/2/1999AFAIL
Details
02/02/99 338 - RESPONSIBLE PERSON NOT ON SITE C/N ISSUE OTHER JOBS READY
INSP - Final1/29/19992/1/19992/1/1999PNR
Details
02/01/99 338 - CHERIE ###-####
INSP-Final Inspection1/29/19992/1/19992/1/1999APASS
DetailsRick Jackson
CHERIE ###-#### occ approved; received modifications to changes in phasing of the entire project
INSP - Final1/6/19991/7/19991/7/1999PFAIL
DetailsWes Worcester
CHERIE ###-#### need approval of time line for Fire requirements
INSP-Final Inspection1/6/19991/7/19991/7/1999AFAIL
DetailsRick Jackson
###-#### CHERIE 6th floor dampers/penetrations in corridor not complete. owner rep Larry Cardinale will submit letter to PDS requesting this portion of the permit be removed and added to a follow on permit.
INSP-Final Inspection10/30/199810/30/199810/30/1998PFAIL
DetailsRick Jackson
Need pump test bypass for outside flow tests.
INSP - Framing/Rough-in7/16/19987/16/19987/16/1998 PASS
DetailsJim Storey
07/15/98 301 - 6:00 PM AS PER JIM STOREY / 3 ELEVATOR SMOKE DOORS ON THE 1-LARRY ###-#### smoke door third floor ok recieved standard for smoke leakage and header surface inpedment ok.
INSP-Final Inspection7/15/19987/15/19987/15/1998PPART
DetailsRick Jackson
tested smoke gaurd doors on 6th floor only - test okay
INSP - Final7/9/19987/14/19987/14/1998ANR
DetailsWes Worcester
07/14/98 342 - partial final/ 6th floor/ larry cardinale ###-#### ready