INSP - Grading Inspection | 7/8/1998 | | 7/8/1998 | | PASS |
Rita DeYoung
|
|
|
Driveway and revegetation complete. $1100.00 bond can now be released.
|
INSP - Final | 5/22/1998 | 5/26/1998 | 5/26/1998 | A | PART |
Wes Worcester
|
|
|
05/26/98 342 - Final - John, ###-####
|
INSP - Grading Inspection | 5/26/1998 | | 5/26/1998 | | BOND |
Rita DeYoung
|
|
|
Fine grading is complete. Revegetation and driveway are not complete. Grading is approved by Public Works upon receipt of an $1100.00 bond to cover these items.
|
INSP - Final | 5/21/1998 | 5/22/1928 | 5/21/1998 | P | |
Wes Worcester
|
|
|
Final - John, ###-####
|
INSP - Final | 5/7/1998 | 5/8/1998 | 5/8/1998 | A | PART |
Wes Worcester
|
|
|
05/08/98 342 - Final (courtesy) - wants you to tell him what else he has complete final - John, ###-####
|
INSP - Framing/Rough-in | 4/13/1998 | 4/13/1998 | 4/13/1998 | P | PASS |
Wes Worcester
|
|
|
04/13/98 342 - John - ###-####
|
INSP - Energy code compliance | 4/9/1998 | 4/9/1998 | 4/9/1998 | A | PASS |
Wes Worcester
|
|
|
04/09/98 342 -
|
INSP - Framing/Rough-in | 4/9/1998 | 4/9/1998 | 4/9/1998 | P | PART |
Wes Worcester
|
|
|
04/09/98 342 - John, ACS - ###-####
|
INSP - Framing/Rough-in | 4/7/1998 | 4/8/1998 | 4/8/1998 | A | CANC |
Wes Worcester
|
|
|
04/08/98 342 - cancelled til pm by John ###-####
|
INSP - Framing/Rough-in | 4/8/1998 | 4/8/1998 | 4/8/1998 | | PART |
Wes Worcester
|
|
|
/ / 342 - 8am apt
|
INSP - Framing/Rough-in | 4/8/1998 | 4/8/1998 | 4/8/1998 | P | PART |
Wes Worcester
|
|
|
|
INSP - Energy code compliance | 4/3/1998 | 4/6/1998 | 4/6/1998 | A | PASS |
Wes Worcester
|
|
|
04/05/98 342 - ###-####-MARK ì
|
INSP - Framing/Rough-in | 4/3/1998 | 4/6/1998 | 4/6/1998 | A | FAIL |
Wes Worcester
|
|
|
04/05/98 342 - still not done w/previous c/n and not on site, still need much deflection West wall, need enf fix
|
INSP - Framing/Rough-in | 4/1/1998 | 4/2/1998 | 4/2/1998 | P | PART |
Wes Worcester
|
|
|
04/02/98 342 - eng not done but ok to insulate pending fix MARK ###-####
|
INSP - Framing/Rough-in | 3/30/1998 | 3/31/1998 | 3/31/1998 | P | FAIL |
Wes Worcester
|
|
|
03/31/98 342 - need plan on site, eng for garage, 2 story alternate brac installation specs not done
|
INSP - Foundation | 2/25/1998 | 2/25/1998 | 2/25/1998 | P | PART |
Wes Worcester
|
|
|
02/25/98 342 - rick ###-#### footing insp
|
INSP - Concrete | 2/11/1998 | 2/12/1998 | 2/12/1998 | A | PASS |
Wes Worcester
|
|
|
02/12/98 342 - ###-#### Rick
|
INSP - Foundation | 2/12/1998 | 2/12/1998 | 2/12/1998 | | PART |
Wes Worcester
|
|
|
/ / 342 -
|
INSP - Foundation | 2/12/1998 | 2/12/1998 | 2/12/1998 | P | NR |
Wes Worcester
|
|
|
02/12/98 342 - REINSP
|
INSP - Conference | 1/27/1998 | 1/27/1998 | 1/27/1998 | | PART |
Wes Worcester
|
|
|
/ / 342 - called engineer
|
INSP - Framing/Rough-in | 1/27/1998 | 1/27/1998 | 1/27/1998 | P | PART |
Wes Worcester
|
|
|
john ###-#### conference....engineering being submitted
|
INSP - Framing/Rough-in | 1/26/1998 | 1/27/1998 | 1/27/1998 | A | NR |
Wes Worcester
|
|
|
01/27/98 342 - WALL--RICK--###-####
|
INSP - Footings | 1/13/1998 | 1/14/1998 | 1/14/1998 | A | FAIL |
Wes Worcester
|
|
|
01/14/98 342 - need plan, eng, rebar on dobbies as per eng and plan requ
|
INSP - Framing/Rough-in | 4/9/1998 | 4/8/1998 | 4/8/1997 | A | NR |
Wes Worcester
|
|
|
|