INSP - Final | 5/13/1998 | 5/13/1998 | 5/13/1998 | P | PASS |
Carl Dependahl
|
|
|
jack ###-#### c/n ok
|
INSP - Final | 5/12/1998 | 5/12/1998 | 5/12/1998 | P | FAIL |
Carl Dependahl
|
|
|
JACK/###-#### - FINAL need air seal, clean out cover, etc.
|
INSP - Framing/Rough-in | 2/10/1998 | 2/10/1998 | 2/10/1998 | P | PART |
Carl Dependahl
|
|
|
JACK ###-####...OK TO COVER, C/N OK; NEED CHK GYP ATTACHMENT AT 1HR WALLS.
|
INSP - Framing/Rough-in | 2/4/1998 | 2/5/1998 | 2/5/1998 | P | FAIL |
Carl Dependahl
|
|
|
jack 890=-4833...c/n ok to ins
|
INSP - Carpentry | 1/12/1998 | 1/12/1998 | 1/12/1998 | P | PART |
Carl Dependahl
|
|
|
1 HR WALLS, fireblocks ok to 1st plate line; told to get further insp when ready
|
INSP - Conference | 12/31/1997 | 12/30/1997 | 12/30/1997 | P | PASS |
Carl Dependahl
|
|
|
W/ JACK BARBER, SUPT. RE; REQ'S FOR 1HR WALLS, INSP'S.
|
INSP - Footings | 12/9/1997 | 12/9/1997 | 12/9/1997 | P | PART |
Carl Dependahl
|
|
|
poured, looks ok...discussed u.g. elec/ conduit at fdn wall w/ bldr.
|