INSP - Final | 7/12/1999 | 7/15/1999 | 7/15/1999 | A | PASS |
Wes Worcester
|
|
|
07/14/99 342 - HOWARD ###-#### c/c issued
|
INSP - Grading Inspection | 7/12/1999 | | 7/12/1999 | | BOND |
Rita DeYoung
|
|
|
Rough grading is complete. Additional work must be done on sideslope of driveway to reduce steepness of the slope to 2:1. Engineer has recommended a $2000.00 bond to cover cost of this work.
|
INSP - Final | 7/1/1999 | 7/6/1999 | 7/6/1999 | A | FAIL |
Wes Worcester
|
|
|
07/06/99 342 - Howard ###-#### need p/w criteria,,,left msg
|
INSP - Framing/Rough-in | 6/8/1999 | 6/8/1999 | 6/8/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - CONF W/BLDR RE HANDRAILS
|
INSP - Final | 6/7/1999 | 6/7/1999 | 6/7/1999 | | PASS |
Joe Tawney
|
|
|
/ / 406 - FINAL OK ON SPKLR SYSTEM AND ALARM SYSYEM
|
INSP-Final Inspection | 6/3/1999 | 6/4/1999 | 6/4/1999 | A | FAIL |
Joe Tawney
|
|
|
06/04/99 406 - FINAL FAIL SPKLR FLOW SWITCH, ALARM PANEL
|
INSP - Framing/Rough-in | 11/5/1998 | 11/5/1998 | 11/5/1998 | P | PART |
Carl Dependahl
|
|
|
conf w/ bldr re install of glass rails at deck.
|
INSP - Framing/Rough-in | 10/29/1998 | 10/29/1998 | 10/29/1998 | A | PASS |
Carl Dependahl
|
|
|
ok to cover.
|
INSP - Energy code compliance | 10/26/1998 | 10/27/1998 | 10/27/1998 | P | PASS |
Carl Dependahl
|
|
|
HOWARD GOUL ###-#### FOR INS INSP...c/n ok, int shear ok. fire sprinklers ok per Joe T.
|
INSP - Framing/Rough-in | 10/12/1998 | 10/12/1998 | 10/12/1998 | P | FAIL |
Carl Dependahl
|
|
|
howard ###-####...need shear walls per eng'r, may have to remove fireplace to do; protect foam insul/block w/ drywall or equal; complete posts at deck & fasten hdwe; add header at mud room wall, fireblocking not complete. ok to insulate & install int shear panels.
|
INSP - Framing/Rough-in | 8/10/1998 | 8/10/1998 | 8/10/1998 | P | NR |
Carl Dependahl
|
|
|
approved insulation system at attic, need listed mat'l used.
|
INSP - Framing/Rough-in | 7/27/1998 | 7/27/1998 | 7/27/1998 | P | NR |
Carl Dependahl
|
|
|
no insp; conf w/ bldr re use of foam plastic insul in roof ass'y...gave rules for use from UBC 2602 re listing, smoke flame etc.
|
INSP - Foundation | 7/8/1998 | 7/8/1998 | 7/8/1998 | P | PART |
Carl Dependahl
|
|
|
rec'd eng's ok for ftg/ fnd system.
|
INSP - Framing/Rough-in | 7/8/1998 | 7/8/1998 | 7/8/1998 | P | NR |
Carl Dependahl
|
|
|
framing/ howard goul/ ###-####...rec'd eng's insp report for foam foundation system; conf w/ bldr: ok to cut T joist resting on wall, for plbg.
|
INSP - Concrete | 5/5/1998 | 5/5/1998 | 5/5/1998 | P | PART |
Carl Dependahl
|
|
|
HOWARD/###-#### - CONCRETE INSP. ON SUPPORT COLUMNS. looks ok, pending eng's letter
|
INSP - Foundation | 5/1/1998 | 5/1/1998 | 5/1/1998 | A | PART |
Carl Dependahl
|
|
|
spoke w/ Goul...says struct eng'r has observed, will send approval letter. ok to pour
|
INSP - Foundation | 4/30/1998 | 4/30/1998 | 4/30/1998 | P | FAIL |
Carl Dependahl
|
|
|
howard/###-#### - foundation insp. late afternoon. NO PLANS ONSITE
|
INSP - Foundation | 4/23/1998 | 4/23/1998 | 4/23/1998 | | FAIL |
Wes Worcester
|
|
|
/ / 342 - need engineer's details, stamped and signed as per ICBO and criteria options. Inspection required for ftg, fdn, rebar and stepped ft
|
INSP - Foundation | 4/23/1998 | 4/23/1998 | 4/23/1998 | P | FAIL |
Wes Worcester
|
|
|
04/23/98 342 - mother's # ???? ###-####
|