INSP-Final Inspection | 4/6/1999 | 4/8/1999 | 4/8/1999 | P | PASS |
Rick Jackson
|
|
|
1:30 BOB ###-#### occ approved
|
Permanent Occupancy | | 4/8/1999 | 4/8/1999 | | DONE |
|
|
|
|
INSP-Final Inspection | 10/3/1998 | 10/3/1998 | 10/3/1998 | A | PART |
Rick Jackson
|
|
|
temp occ approved. c/n issued for corrections
|
INSP - Final | 9/30/1998 | 10/2/1998 | 10/2/1998 | A | PART |
|
|
|
resubmittal
|
INSP-Final Inspection | 10/1/1998 | 10/2/1998 | 10/2/1998 | P | FAIL |
Rick Jackson
|
|
|
BOB ###-#### alarms not complete - rescheduled for am 10/3 per George Slane approval
|
INSP-Final Inspection | 9/30/1998 | 10/1/1998 | 10/1/1998 | P | NR |
Rick Jackson
|
|
|
bob ###-#### alarm panel had "fried"
|
INSP - Final | 9/25/1998 | 9/28/1998 | 9/28/1998 | A | PASS |
|
|
|
09/28/98 333 - other agencies signatures needed
|
INSP-Final Inspection | 9/17/1998 | 9/23/1998 | 9/23/1998 | P | PART |
Rick Jackson
|
|
|
SHELLY ###-#### FIRE PUMP START not a final - tested pump flow - met reuirements. still requires alarm installation
|
INSP - Final | 9/18/1998 | 9/21/1998 | 9/21/1998 | P | PART |
|
|
|
pre final cn placed other agencies not signed
|
INSP - Final | 9/10/1998 | 9/10/1998 | 9/10/1998 | P | FAIL |
|
|
|
09/10/98 333 - cn placed
|
INSP - Framing/Rough-in | 9/2/1998 | 9/2/1998 | 9/2/1998 | P | PASS |
|
|
|
09/02/98 333 - CLG -OK CEILING COVER
|
INSP - Framing/Rough-in | 8/18/1998 | 8/19/1998 | 8/19/1998 | A | PASS |
|
|
|
08/19/98 333 - shaft and draftstop ok
|
INSP - Framing/Rough-in | 8/17/1998 | 8/18/1998 | 8/17/1998 | A | CANC |
|
|
|
Scheduled by Hello!. Contact phone is [3434253]. Cancelled by Hello! (Last update by [HLO]). Contact: [3434253].
|
INSP - Framing/Rough-in | 8/12/1998 | 8/12/1998 | 8/12/1998 | P | PART |
|
|
|
08/12/98 333 - alll but front canopy
|
INSP - Framing/Rough-in | 7/23/1998 | 7/27/1998 | 7/27/1998 | A | PASS |
|
|
|
07/27/98 333 - FRAM-OK FRAMING
|
INSP - Foundation | 7/15/1998 | 7/16/1998 | 7/16/1998 | P | PART |
|
|
|
07/16/98 333 - middle pour ok retaining wall
|
INSP - Framing/Rough-in | 7/15/1998 | 7/16/1998 | 7/16/1998 | P | PART |
|
|
|
07/16/98 333 - first floor ok
|
INSP-Supply line flush | 7/14/1998 | 7/14/1998 | 7/14/1998 | A | PASS |
Rick Jackson
|
|
|
underground flush okay
|
INSP - Framing/Rough-in | 7/8/1998 | 7/9/1998 | 7/9/1998 | A | PASS |
|
|
|
07/09/98 333 - mezineene ok
|
INSP - Foundation | 7/2/1998 | 7/3/1998 | 7/2/1998 | A | |
|
|
|
Scheduled by Hello!.
|
INSP - Framing/Rough-in | 6/30/1998 | 7/1/1998 | 7/1/1998 | A | PART |
|
|
|
07/01/98 333 - ok to cover behind freezers
|
INSP - Wall cover | 6/30/1998 | 7/1/1998 | 7/1/1998 | A | PART |
|
|
|
07/01/98 333 - ok to cover behind freezers
|
INSP - Foundation | 6/29/1998 | 6/29/1998 | 6/29/1998 | | PART |
|
|
|
/ / 333 - TIS OK
|
INSP - Framing/Rough-in | 6/15/1998 | 6/15/1998 | 6/15/1998 | | PART |
|
|
|
/ / 333 - ROOFING IN PROGRESS
|
INSP - Framing/Rough-in | 6/9/1998 | 6/9/1998 | 6/9/1998 | | PART |
|
|
|
/ / 333 - EPOXY BOLTING
|
INSP - Framing/Rough-in | 6/8/1998 | 6/8/1998 | 6/8/1998 | | PART |
|
|
|
/ / 333 - ROOF DECK ON
|
INSP - Foundation | 5/27/1998 | 5/28/1998 | 5/28/1998 | A | PART |
|
|
|
05/28/98 333 - grout wall ok
|
INSP - Framing/Rough-in | 5/27/1998 | 5/27/1998 | 5/27/1998 | | PART |
|
|
|
/ / 333 - ROOF IN PROGRESS
|
INSP - Foundation | 5/20/1998 | 5/20/1998 | 5/20/1998 | A | PART |
|
|
|
05/20/98 333 - nw wall ok pend spec insp report
|
INSP - Foundation | 5/18/1998 | 5/18/1998 | 5/18/1998 | A | PART |
Jim Storey
|
|
|
05/18/98 301 - Scheduled by Hello!. covered by s,i
|
INSP - Foundation | 5/13/1998 | 5/14/1998 | 5/14/1998 | A | PART |
|
|
|
05/14/98 333 - ok pending special insp reports
|
INSP - Foundation | 5/6/1998 | 5/7/1998 | 5/7/1998 | P | PART |
|
|
|
05/07/98 333 - n\w corner
|
INSP - Foundation | 5/6/1998 | 5/6/1998 | 5/6/1998 | P | PART |
|
|
|
05/06/98 333 - ok pending special insp reports west wall
|
INSP - Foundation | 5/5/1998 | 5/5/1998 | 5/5/1998 | | PART |
|
|
|
05/05/98 333 - ok pending specilal insp
|
INSP - Foundation | 5/4/1998 | 5/5/1998 | 5/5/1998 | A | PASS |
|
|
|
05/05/98 333 - ok pending special insp rerports
|
INSP - Foundation | 5/1/1998 | 5/1/1998 | 5/1/1998 | A | PASS |
|
|
|
05/01/98 333 - ok pending special insp reports
|
INSP - Foundation | 4/29/1998 | 4/30/1998 | 4/30/1998 | A | PART |
|
|
|
04/30/98 333 - ok pend spec insp reports
|
INSP - Foundation | 4/29/1998 | 4/29/1998 | 4/29/1998 | P | PART |
|
|
|
04/29/98 333 - ok pending special insp reports
|
INSP - Foundation | 4/28/1998 | 4/28/1998 | 4/28/1998 | A | PART |
|
|
|
04/28/98 333 - ok pending special insp reports
|
INSP - Foundation | 4/27/1998 | 4/27/1998 | 4/27/1998 | P | PART |
|
|
|
04/27/98 333 - ok pending special insp reports
|
INSP - Foundation | 4/22/1998 | 4/23/1998 | 4/23/1998 | P | PART |
|
|
|
04/23/98 333 - ok pending special insp reports
|
INSP - Foundation | 4/22/1998 | 4/22/1998 | 4/22/1998 | A | PART |
|
|
|
04/22/98 333 - ok pending special insp report
|
INSP - Foundation | 4/20/1998 | 4/21/1998 | 4/21/1998 | A | PART |
|
|
|
04/21/98 333 - pending special insp reports
|
INSP - Foundation | 4/20/1998 | 4/20/1998 | 4/20/1998 | A | PART |
|
|
|
04/20/98 333 - pending special insp report
|
INSP - Foundation | 4/17/1998 | 4/17/1998 | 4/17/1998 | A | PART |
|
|
|
04/17/98 333 - ok pend spec insp report
|
INSP - Foundation | 4/16/1998 | 4/16/1998 | 4/16/1998 | A | PART |
|
|
|
04/16/98 333 - ok pending special insp reports
|
INSP - Foundation | 4/15/1998 | 4/15/1998 | 4/15/1998 | A | PART |
|
|
|
04/15/98 333 - ok pending special insp reports
|
INSP - Foundation | 4/10/1998 | 4/13/1998 | 4/13/1998 | A | PART |
|
|
|
04/13/98 333 - ok pending special ins reports
|
INSP - Framing/Rough-in | 4/8/1998 | 4/9/1998 | 4/9/1998 | A | PART |
|
|
|
04/09/98 333 - ok pend sped insp reports
|
INSP - Foundation | 4/3/1998 | 4/6/1998 | 4/7/1998 | A | PART |
|
|
|
04/06/98 333 - ok pending special insp reports
|
INSP - Foundation | 4/3/1998 | 4/3/1998 | 4/3/1998 | P | PART |
|
|
|
04/03/98 333 - ok pending special insp report
|
INSP - Concrete | 4/1/1998 | 4/1/1998 | 4/1/1998 | P | PART |
|
|
|
04/01/98 333 - north west side ok pending spec insp report
|