INSP - Final | 3/23/1998 | 3/23/1998 | 3/23/1998 | A | PASS |
Carl Dependahl
|
|
|
reinsp ok...lc 014539
|
INSP - Final | 3/19/1998 | 3/20/1998 | 3/20/1998 | P | NR |
Carl Dependahl
|
|
|
JOHN ###-####--DOOR OPEN--KEY OVER FRONT DOOR...nr need elec & mec
|
INSP - Energy code compliance | 2/23/1998 | 2/24/1998 | 2/24/1998 | A | PASS |
Carl Dependahl
|
|
|
john ###-####
|
INSP - Framing/Rough-in | 2/23/1998 | 2/24/1998 | 2/24/1998 | A | PASS |
Carl Dependahl
|
|
|
john ###-####
|
INSP - Framing/Rough-in | 2/20/1998 | 2/20/1998 | 2/20/1998 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - C/N NAILING, SUPPORT AT FURN PLATFORM/FLOOR JOISTS & WALL. O
|
INSP - Framing/Rough-in | 2/19/1998 | 2/19/1998 | 2/19/1998 | P | PART |
Carl Dependahl
|
|
|
###-#### john ENG'G ONLY, LEFT C/N...LOOKS OK TO CONTINUE
|
INSP - Final | 1/23/1998 | 1/23/1998 | 1/23/1998 | P | CANC |
Carl Dependahl
|
|
|
###-#### BRANDON TEMP POLE INSP
|
INSP - Propriety inspection | 1/22/1998 | 1/21/1998 | 1/21/1998 | | PASS |
|
|
|
Bond to move 12x28 foot storage shed (336 sq. ft.)from 1622 Arthur st. in Caldwell, Id. to Boise. Bond set at $2,000. which will require the following information. floor plan plot plan footing foundation refoof facia repair floor support for storage shed loading. Current floor system 2x6, 16 inches oc. and strongbacks placed about 6 feet apart but are unsupported. compying steps and landings. Doors (2) swing out. Cathy Weisehaupt ###-####. will accept the bond and their is specfic language required, I have instructed the owner to talk with Cathy so that the bond is posted correctly. The $2,000, bond does not reflect lot cleanup and none is required. A building permit is required and permits necessary to move the storage building on the road. Other conditions may be set by plan review.
|
INSP - Propriety inspection | 1/22/1998 | 1/21/1998 | 1/21/1998 | | PASS |
|
|
|
|