INSP - Final | 7/10/1998 | 7/10/1998 | 7/10/1998 | P | PASS |
Russ Owen
|
|
|
07/10/98 407 - final/ ###-####
|
INSP - Letter of compliance | 7/10/1998 | 7/10/1998 | 7/10/1998 | | PASS |
Russ Owen
|
|
|
/ / 407 - lc#14736
|
INSP - Letter of compliance | 7/10/1998 | 7/10/1998 | 7/10/1998 | | PASS |
Russ Owen
|
|
|
/ / 407 - lc#14736
|
INSP - Final | 7/9/1998 | 7/9/1998 | 7/9/1998 | P | FAIL |
Russ Owen
|
|
|
07/09/98 407 - left corrections.L WHEN COMING OUT
|
INSP - Energy code compliance | 5/1/1998 | 5/1/1998 | 5/2/1998 | A | PASS |
Russ Owen
|
|
|
re-inspection of framing and energy code,had a problem with the computer on friday,had promissed to go by this job,so they could get the rocking started,designer droped of letter of approval from the engineer,never came back up as computer main was down,so i went by next day saturday,called Bob A, and told him i did inspection of this one job,because i had promised to be ther friday and did not make it.Bob said no problem.
|
INSP - Energy code compliance | 4/30/1998 | 5/1/1998 | 5/1/1998 | A | CANC |
Russ Owen
|
|
|
contractor called,told him i need the enginners letter of approval and the energy compliance report.
|
INSP - Framing/Rough-in | 4/27/1998 | 4/28/1998 | 4/28/1998 | A | FAIL |
Russ Owen
|
|
|
04/28/98 407 - still have corrections. ###-#### reinspection
|
INSP - Framing/Rough-in | 4/23/1998 | 4/24/1998 | 4/24/1998 | P | FAIL |
Russ Owen
|
|
|
04/24/98 407 - left corrections.
|
INSP - Foundation | 3/3/1998 | 3/3/1998 | 3/3/1998 | P | NR |
Carl Dependahl
|
|
|
NOT FND INSP; OK FOR BSMT MODIF W/ ENG'D PLAN
|
INSP - Foundation | 3/2/1998 | 3/3/1998 | 3/3/1998 | A | PASS |
Russ Owen
|
|
|
03/03/98 407 - footings
|
INSP - Foundation | 3/2/1998 | 3/2/1998 | 3/2/1998 | P | PART |
Russ Owen
|
|
|
left some minor corrections with jim the general contractor.
|
INSP - Foundation | 2/25/1998 | 2/26/1998 | 2/26/1998 | A | NR |
Russ Owen
|
|
|
this plan has changed and needs to be re approved by the engineer before i will inspect. They have added a basement to an engineered plan.
|
INSP - Foundation | 2/26/1998 | 2/26/1998 | 2/26/1998 | A | NR |
Carl Dependahl
|
|
|
met w/ JIM JENSEN, BLDR, REQ'D REVISION BY ENG'R FOR BSMT/ SHEAR WALL CONFIGURATION CHANGED. TOLD TO PROCEED AT OWN RISK FOR FTGS AT BSMT
|
INSP - Foundation | 2/25/1998 | 2/25/1998 | 2/25/1998 | P | NR |
Carl Dependahl
|
|
|
called arch, need full eng'd plans...eng to analyze revision for bsmt
|
INSP - Foundation | 2/25/1998 | 2/25/1998 | 2/25/1998 | P | NR |
Carl Dependahl
|
|
|
|